Solar Photovoltaic (PV) Permit — Town Planning Clearance + Mesa County Building Permit — Palisade, Colorado · Requirements sheet
Verified 2026-07-19 · Source: https://www.mesacounty.us/sites/default/files/2026-04/Photovoltaic%20Guide%207-20-2023.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit — Town Planning Clearance + Mesa County Building Permit in Palisade, Colorado
Required for rooftop or ground-mount solar photovoltaic installation on property within the Town of Palisade. The actual building/electrical permit is issued and inspected by the Mesa County Building Department (not the Town), applying the Mesa County Photovoltaic Guide. Critically, the Mesa County Photovoltaic Guide explicitly names Palisade — together with De Beque and Collbran — as one of the jurisdictions where a residential roof-mount PV system requires a Town Planning Clearance BEFORE Mesa County will issue the building/electrical permit; this Town clearance step is NOT required for roof-mount systems in Grand Junction itself. Ground-mount PV systems require a Town/City planning clearance regardless of jurisdiction per the same Guide.
Verified 2026-07-19 · Source
When you need this permit
- STEP 1 (Town prerequisite for Palisade specifically): Obtain a Town of Palisade Planning Clearance from the Community Development Department (175 East 3rd Street / P.O. Box 128, Palisade, CO 81526; planning@townofpalisade.org; (970) 464-5602) before Mesa County will issue the PV building/electrical permit — the Basic Planning Clearance application form ($10 flat fee) covers 'service upgrades and/or similar actions which do not change the scale, use or character of a structure,' with an 'Electrical Work Included' checkbox, and is the most likely applicable clearance category for a roof-mount solar installation, though the form does not explicitly enumerate 'solar' or 'photovoltaic' as a named example
- STEP 2: Submit the Mesa County Building Department PV permit application per the Mesa County Photovoltaic Guide (rev. 7/20/2023) — structural certification report verifying the existing roof framing supports the array (115 mph wind speed design criteria), three-line diagram, component spec sheets, and roof layout
- Total project valuation (modules, inverters, remaining electrical work, structural alterations) determines the Mesa County permit fee per Table 2 of the County's fee schedule
- Ground-mount PV systems require a Town of Palisade planning clearance regardless of jurisdiction, per the Mesa County Photovoltaic Guide's explicit statewide-jurisdiction list
- All commercial and ground-mount PV system designs require structural, foundation, and electrical drawings stamped and signed by a Colorado Professional Engineer, per the Mesa County Photovoltaic Guide
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Performed by Mesa County Building Department; conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Mesa County final electrical inspection; a final building inspection is required prior to any solar installation/reinstallation on a reroofed structure, per the Mesa County Photovoltaic Guide
See the full Palisade inspection guide — scheduling & re-inspection fees →
Tips
- Palisade is one of only three jurisdictions (with De Beque and Collbran) that the Mesa County Photovoltaic Guide explicitly names as requiring a Town/City planning clearance for a residential ROOF-MOUNT solar system before the County will issue the PV permit — Grand Junction itself does NOT require this extra step for roof-mount systems.
- Ground-mount PV systems require a Town of Palisade planning clearance regardless of jurisdiction, per the same Mesa County Photovoltaic Guide.
- The Town's Basic Planning Clearance form does not list 'solar' or 'photovoltaic' as a named example project type (it lists reroof, residing, interior remodel, window replacement, demo, and service upgrades) — confirm with Town Community Development (970-464-5602) which specific clearance category applies to your installation before submitting.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Palisade building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Palisade
Solar Photovoltaic (PV) Permit — Town Planning Clearance + Mesa County Building Permit in other cities