How to schedule
Inspections are requested through the building department below.
- Address
- Craig City Hall, 300 W 4th Street, Craig, CO 81625
- Phone
- 970-826-2013
- Office hours
- Monday-Friday 8:00 am-5:00 pm. Building Official: Marlin Eckhoff (Office 970-826-2013, Cell 970-326-3645, meckhoff@ci.craig.co.us). Building Administrator: Sierra Arellano (970-826-2024, sarellano@ci.craig.co.us) handles contractor licensing/registration. The department is located upstairs within Craig City Hall, in the Community Development Department. Verified identically on both the City of Craig's and Moffat County's own department pages.
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Setbacks / Footings
- 2
Foundation Wall / Damp-proofing / Foundation Drainage
- 3
Framing
May only be performed after electrical, mechanical, and plumbing rough-in inspections (electrical rough-in performed by the State inspector)
- 4
Roofing / Siding / Insulation / Sheetrock
- 5
Final / Certificate of Occupancy
May only be performed after or simultaneously with electrical (State), mechanical, and plumbing final inspections
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork, rough openings for supply/return, machinery installation and structural support, piping within walls
- 2
Combustion Air / Return Air / Appliance Vent-Chimney
- 3
Gas Piping
- 4
Final Inspection
Applies to: Plumbing Permit
- 1
Underground (Service Line Connections)
- 2
Rough-In / Top Out
Concealed piping under slabs and within walls; includes pressure test of DWV & water distribution piping
- 3
Fixtures / Water Heaters / Backflow Preventer
- 4
Gas Piping
Applies to: Residential Addition / Remodel Permit
- 1
Footings / Foundation
- 2
Framing
After electrical (State), mechanical, and plumbing rough-ins
- 3
Final / Certificate of Occupancy
Applies to: Solar Permit (Photovoltaic)
- 1
Rough Inspection (Structural/Racking)
Performed by the local Building Department
- 2
Rough & Final Electrical Inspection
Performed by a State of Colorado DORA inspector, not the local department
- 3
Final Building Inspection
Applies to: Electrical Permit (State-Administered)
- 1
Rough Electrical (State Inspector)
- 2
Final Electrical (State Inspector)
Applies to: Roofing Permit (Re-Roof)
- 1
Pre-Roof Inspection
For re-roofing projects specifically, before work begins
- 2
Roofing / Final Inspection
Final inspection only: Demolition Permit, Electric Vehicle Charging Station Permit (State-Administered), Fence / Retaining Wall Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Craig building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Craig building permits
Get alerts for Craig
We'll email you when Craig's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.