Solar Permit (Photovoltaic) — Craig, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://www.ci.craig.co.us/departments/residential_solar_installation_checklist.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Permit (Photovoltaic) in Craig, Colorado
Required for residential solar installations. The Craig/Moffat County Regional Building Department handles structural/racking/fire-access plan review and inspection; the electrical portion is handled entirely separately and independently by the State of Colorado, with State approval required BEFORE the local Building Permit is issued.
Verified 2026-07-06 · Source
When you need this permit
- 3 sets of plans, minimum 11x17 inches, submitted to the Community Development Department at 300 W 4th Street, Craig CO 81625 or emailed to meckhoff@ci.craig.co.us; larger plans may also require paper copies even if submitted electronically
- All plans must be stamped by a Colorado State licensed engineer (exceptions may apply) Contractor
- The local Building Department reviews and inspects: racking systems, fire access setbacks, wind zones, snow and wind loads, and existing roof structure
- A SEPARATE electrical permit is required from the Colorado Department of Regulatory Agencies (DORA), Division of Professions & Occupations — the State reviews and inspects the electrical portion; State approval is required PRIOR to the local Building Permit being issued
- Plans must show: all disconnects, modules, batteries, inverters, grounding conductors; racking system locations/attachment details per manufacturer; dimensions/clearances around equipment; firefighter access paths per the 2018 IFC (typically 36 inches); existing roof vents/penetrations/structure (if roof-mounted); design criteria; safety/disconnect labeling locations; panel locations, amperages, and line diagrams
- Design criteria specific to solar: ground snow load 57 psf countywide, but 40 psf non-reducible roof snow load design value used locally (up to 100 psf at higher west-county elevations — location/elevation must be disclosed); 115 mph wind speed; 48-inch frost depth; adopted codes 2018 IFC/IRC/IBC plus the Colorado-adopted NEC edition (enforced by the State, not locally)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Inspection (Structural/Racking)
Performed by the local Building Department
- 2
Rough & Final Electrical Inspection
Performed by a State of Colorado DORA inspector, not the local department
- 3
Final Building Inspection
See the full Craig inspection guide — scheduling & re-inspection fees →
Tips
- Bring or email 3 sets of plans at a minimum of 11x17 inches — larger-format plans may still require a paper copy submission even if you also submit electronically.
- The local Building Department's plan review explicitly covers fire-access setbacks per the 2018 IFC (typically a 36-inch firefighter access path) — make sure your racking layout plans show this clearance.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Craig building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Craig
Solar Permit (Photovoltaic) in other cities
Compare solar permit (photovoltaic) fees across Colorado →
Look up this fee in a different city →