Commercial Building Permit (New Structure) in Craig, Colorado
Required for new commercial buildings within the Craig/Moffat County Regional Building Department's joint jurisdiction (City of Craig plus all of Moffat County except the Town of Dinosaur). There is NO separately-branded commercial permit application or process here: the department's own Checklists for Obtaining Permits & Scheduling Inspections handout runs commercial buildings through the same 'New Structure Permits' checklist as residential — its heading reads 'New Structure Permits (Includes single and two family dwellings, multi-family dwellings and commercial buildings)' — with commercial-specific plan-detail requirements layered on top. Governed by the jointly-adopted 2018 IBC/IMC/IFGC/IPC/IECC/IFC; electrical permitting, plan review, and inspection are handled entirely by the State of Colorado (DORA), not this department.
Verified 2026-08-02 · Source
When you need this permit
- 2 sets of plans required, same base checklist as residential new construction: Site Plan (physical address, owner name/mailing address/phone, footprint drawn to scale with distances from lot lines and existing/proposed structures, all adjacent streets/alleys/easements), Soils Analysis/Report, Foundation Design Drawings stamped by a Colorado-licensed engineer, Elevation drawings (roof slope, roofing type, exterior coverings), Floor plan with all plumbing/HVAC fixture locations plus window/door locations and sizes, Framing details for all load-bearing components, drawings/specifications for any engineered beams, girders, joists, and floor or ceiling trusses
- Commercial-specific plan standard, quoted from the department's own checklist: 'for commercial projects plans must be more detailed and include details and specifications for plumbing, mechanical/HVAC plans'
- ResCheck (or comparable analysis) of building envelope and fenestration for energy-code compliance, plus Heat Gain/Loss analysis IAW ASHRAE Manual J indicating size of proposed heating, cooling, and water heating appliances (the checklist cites '2006 IEEC' for the envelope analysis even though the department's adopted code set is the 2018 IECC — follow the Building Official's direction on which vintage to run)
- Names of General, Plumbing, and Mechanical contractors required at application; a properly licensed contractor is mandatory for ALL commercial work — per the City's Permits & Inspections page, the owner-self-perform allowance 'applies to one and two-family dwellings only, all commercial properties require a properly licensed contractor to acquire the permit and perform the work' Contractor
- Contractors must hold a City of Craig Contractor License for work inside city limits or Moffat County Contractor Registry registration for unincorporated county work; plumbers must additionally be state-registered Contractor
- Sewer/Water Tap Application required, with address and legal designation of subdivision/block/lot, property owner name/signature/mailing address/phone, and the plumbing contractor's business name, authorized-rep signature, and license number
- Electrical work is NOT part of this permit's scope — a separate electrical permit must be obtained directly from DORA's State Electrical Board, and rough/final electrical inspections are performed by a State inspector
- Applications received on or after July 1, 2026 are subject to the 2025 Colorado Wildfire Resiliency Code (CWRC); applicability (none/Class 1/Class 2) is determined by address/parcel lookup on the Colorado Resiliency Code Map
- Prior to ANY excavation activity, the owner/contractor must contact the Utility Notification Center of Colorado (UNCC) at 1-800-922-1987
- A Certificate of Occupancy is required before moving into a business, per Moffat County's own Building Permit Information page — basic CO requirements include a complete and approved electrical system, functional bathroom and sink with hot/cold running water, approved sewage disposal, functional heating, no hazardous conditions, and the address posted conspicuously
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 8 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Setbacks / Footings
- 2
Slab-Floor / Foundation Wall / Damp-proofing & Foundation Drainage
- 3
Sheathing (roof & walls) / Framing
Framing may only be performed after electrical, mechanical, and plumbing rough-in inspections (electrical rough-in performed by the State inspector)
- 4
Roofing / Siding / Insulation / Sheetrock-Plaster
- 5
Public Safety
Egress & Lighting; Fire Protection / Suppression System / Fire-Smoke Alarms & Detectors; Maximum Occupancy Load Posted — listed on the department's own Standard Building Inspections record and most relevant to commercial occupancies
- 6
Final / Certificate of Occupancy
May only be performed after or simultaneously with electrical (State), mechanical, and plumbing final inspections; a Temporary Certificate of Occupancy is also listed as an available inspection step
See the full Craig inspection guide — scheduling & re-inspection fees →
Tips
- There is no separately-branded commercial permit here — commercial new construction runs through the exact same 'New Structure Permits' checklist and $100 flat-fee structure as residential, just with a mandatory licensed contractor and more detailed plumbing/mechanical/HVAC plan specifications. Contractor
- Tenant improvement / tenant finish is NOT a distinct permit type in this jurisdiction: no TI-specific application, checklist, fee, or webpage exists on either the City's or County's site. Interior commercial remodel work falls under the department's 'Minor Additions/Modifications/Repairs, Renovations and Remodeling Projects' checklist (2 sets of plans: site plan, footing/foundation drawings if applicable, elevations, floor plan, framing details), with the commercial constraint that a licensed contractor must pull the permit and perform the work — owner self-performance is limited to 1-2 family dwellings only. Contractor
- Electrical is the big scheduling trap on commercial jobs: the entire electrical trade — permit, plan review, rough and final inspections — is state-administered by DORA's State Electrical Board, and framing inspection cannot happen until the State's electrical rough-in is done. Build the state inspector's availability into your critical path.
- No distinct heavy-industrial permitting track is published by this building department. Despite Craig's coal-economy profile (Craig Station power plant, Trapper Mine — both facing mid-2020s closure/transition), nothing on the City's or County's building-department pages establishes a separate industrial building-permit process; a conventional industrial/commercial building would run through this same New Structure track, while mine and utility-scale facilities are governed by state-level regulatory programs outside this local building-permit process entirely. Verify scope directly with the Building Official for any energy-transition redevelopment project.
- If your commercial project starts on/after July 1, 2026, check the Colorado Resiliency Code Map by address first — CWRC Class 1/Class 2 wildfire-resiliency requirements now apply to applications received on or after that date.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Craig building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Craig.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Craig
Commercial Building Permit (New Structure) in other cities
Compare commercial building permit (new structure) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Craig project checklist
Describe your project once and get every permit, document, and fee it triggers in Craig — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →