Required for demolition work within the Craig/Moffat County Regional Building Department's joint jurisdiction. Asbestos inspection and CDPHE notification are mandatory prerequisites administered at the state level, in addition to a local General Demolition Application.

Verified 2026-07-06 · Source

When you need this permit

  • A local General Demolition Information and Application must be submitted to the Craig/Moffat County Regional Building Department
  • A certified asbestos building inspection is required before any demolition work takes place, per Colorado Department of Public Health and Environment (CDPHE) requirements
  • A minimum 10-business-day notification to CDPHE is required before commencement of demolition, via an Asbestos Abatement Notification and Permit Application plus a state permit fee, if asbestos-containing material is present or must be ruled out
  • Applicants should reference CDPHE's own General Information on Asbestos and Asbestos Inspection Flow Chart documents, both linked directly from the City's Demolition and Asbestos Abatement page

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Local Demolition Permit FeeChecked the City's Demolition and Asbestos Abatement page directly — it links to application/informational documents but does not itself state a local dollar fee figure.
Not separately published as a standalone figure distinct from the general $100 flat structure permit fee
CDPHE Asbestos Abatement Notification and Permit fee (state, if applicable)Separate state-level fee tied to the asbestos notification/permit process, distinct from any local demolition permit fee.
Set by CDPHE, not the local jurisdiction

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit permit actually take in Craig?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Pre-Demolition Asbestos Inspection

    State-certified inspector, required before any demolition begins

See the full Craig inspection guide — scheduling & re-inspection fees →

Tips

  • Budget at least 10 business days of lead time for the CDPHE asbestos notification requirement before any demolition can legally commence, even if the local Building Department's own application turns around quickly.

Frequently asked questions

Craig requires a demolition permit for: A local General Demolition Information and Application must be submitted to the Craig/Moffat County Regional Building Department; A certified asbestos building inspection is required before any demolition work takes place, per Colorado Department of Public Health and Environment (CDPHE) requirements; A minimum 10-business-day notification to CDPHE is required before commencement of demolition, via an Asbestos Abatement Notification and Permit Application plus a state permit fee, if asbestos-containing material is present or must be ruled out; Applicants should reference CDPHE's own General Information on Asbestos and Asbestos Inspection Flow Chart documents, both linked directly from the City's Demolition and Asbestos Abatement page. If your project isn't listed, confirm with Craig/Moffat County Regional Building Department at 970-826-2013 before starting work.

In Craig, the published Local Demolition Permit Fee is: Not separately published as a standalone figure distinct from the general $100 flat structure permit fee. Additional published fees: CDPHE Asbestos Abatement Notification and Permit fee (state, if applicable) — Set by CDPHE, not the local jurisdiction. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Craig does not publish a plan-review timeline for this permit. Contact Craig/Moffat County Regional Building Department at 970-826-2013 for current turnaround.

You'll need: General Demolition Information and Application; Asbestos Inspection Report. Depending on your project, Craig may also ask for: CDPHE Asbestos Abatement Notification and Permit Application. See the required-documents checklist on this page for details on each.

Craig requires 1 inspection(s) for a demolition permit, in order: Pre-Demolition Asbestos Inspection. Schedule each through Craig/Moffat County Regional Building Department (970-826-2013).

Apply through Craig/Moffat County Regional Building Department at Craig City Hall, 300 W 4th Street, Craig, CO 81625. Phone: 970-826-2013, email: meckhoff@ci.craig.co.us. Office hours: Monday-Friday 8:00 am-5:00 pm. Building Official: Marlin Eckhoff (Office 970-826-2013, Cell 970-326-3645, meckhoff@ci.craig.co.us). Building Administrator: Sierra Arellano (970-826-2024, sarellano@ci.craig.co.us) handles contractor licensing/registration. The department is located upstairs within Craig City Hall, in the Community Development Department. Verified identically on both the City of Craig's and Moffat County's own department pages.. Official information: https://www.ci.craig.co.us/departments/building.php.

Craig, Colorado has adopted: 2018 International Building Code (IBC) — City of Craig and Moffat County, effective for all plan review and inspections as of January 1, 2020; 2018 International Residential Code (IRC); 2018 International Existing Building Code (IEBC); 2018 International Mechanical Code (IMC); 2018 International Fuel Gas Code (IFGC); 2018 International Plumbing Code (IPC); 2018 International Energy Conservation Code (IECC); 2018 International Property Maintenance Code (IPMC) — City of Craig ONLY, not adopted by Moffat County for unincorporated areas; 2018 International Fire Code (IFC) — cited directly in the Residential Solar Installation Checklist for firefighter access path requirements (typically 36 inches); National Electrical Code (NEC), the version adopted by the State of Colorado — NOT locally enforced; the City of Craig and Moffat County both defer ALL electrical permits, plan review, and inspections to the Colorado Department of Regulatory Agencies (DORA), Division of Professions and Occupations, State Electrical Board; 2025 Colorado Wildfire Resiliency Code (CWRC), effective July 1, 2026 — verified directly from the City's own Colorado Wildfire Resiliency Code page; any complete Building Permit Application received by 5:30pm on June 30, 2026 is exempt from CWRC requirements provided the permit fee is paid within 30 days of approval notification; applications received July 1, 2026 or later are subject to CWRC. Applicability (Class 1 vs Class 2 requirements) is determined by an address/parcel lookup on the Colorado Resiliency Code Map (unshaded = no requirements, yellow = Class 1, orange/red = Class 2).; Local IRC deletions (verified from the City's own Adopted Codes page): IRC Section R313 (Automatic Fire Sprinkler Systems) is deleted — sprinkler systems are NOT required in one- and two-family dwellings; IRC Section N1102.4.1.2 (Testing / blower door tests) is deleted — blower door tests are NOT required; IRC Section N1102.4.4 (Rooms containing fuel-burning appliances) is deleted; IRC Section R302.13 (Fire protection of floors) is deleted.. Local amendments apply — see the Craig overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Craig building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.