Demolition Permit — Craig, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://www.ci.craig.co.us/departments/demolition_and_asbestos_abatement.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Craig, Colorado
Required for demolition work within the Craig/Moffat County Regional Building Department's joint jurisdiction. Asbestos inspection and CDPHE notification are mandatory prerequisites administered at the state level, in addition to a local General Demolition Application.
Verified 2026-07-06 · Source
When you need this permit
- A local General Demolition Information and Application must be submitted to the Craig/Moffat County Regional Building Department
- A certified asbestos building inspection is required before any demolition work takes place, per Colorado Department of Public Health and Environment (CDPHE) requirements
- A minimum 10-business-day notification to CDPHE is required before commencement of demolition, via an Asbestos Abatement Notification and Permit Application plus a state permit fee, if asbestos-containing material is present or must be ruled out
- Applicants should reference CDPHE's own General Information on Asbestos and Asbestos Inspection Flow Chart documents, both linked directly from the City's Demolition and Asbestos Abatement page
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition Asbestos Inspection
State-certified inspector, required before any demolition begins
See the full Craig inspection guide — scheduling & re-inspection fees →
Tips
- Budget at least 10 business days of lead time for the CDPHE asbestos notification requirement before any demolition can legally commence, even if the local Building Department's own application turns around quickly.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Craig building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Craig
Demolition Permit in other cities
Compare demolition permit fees across Colorado →