Haxtun building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Haxtun, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 145 S. Colorado Ave., P.O. Box 205, Haxtun, CO 80731
- Phone
- 970-774-6104
- Office hours
- Monday-Friday 7:30 am - 4:15 pm. After-hours/utility emergencies: Phillips County Comm Center, 970-854-2735.
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour, per 30-inch minimum frost line depth; foundation drains inspected by a Colorado-registered design professional per local IRC amendment
- 2
Insulation Inspection
After completed and approved rough inspection, following installation of wall/ceiling/floor insulation and exterior windows, before wall coverings are installed (HMC § 150.02(B)(6), IRC R109.1.5.2 as added locally)
- 3
Rough Electrical (State of Colorado Inspector)
All new electrical installations must be inspected by a State of Colorado inspector before electricity can be supplied; allow up to 3 days for this inspection
- 4
Final Inspection
All work complete per approved plans and applicable codes; permit must be validated/signed by the Town of Haxtun Building Inspector
Applies to: EV Charger / EVSE Permit
- 1
State Electrical Inspection
Performed by a State of Colorado inspector (phone 1-800-955-5770); required before the charger circuit can be energized -- allow up to 3 days
- 2
Final Inspection
Verified by the Town's Building Inspector
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, gas piping (min. 18-inch burial depth) before concealment
- 2
Final Inspection
Equipment operational, venting/combustion air verified; permit validated by the Town's Building Inspector
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment, per 2021 IPC as locally amended
- 2
Final Inspection
Fixtures connected, no leaks; permit validated/signed by the Town of Haxtun Building Inspector
Applies to: Residential Addition / Remodel Permit
- 1
Rough Framing/Trades
Framing and trade rough-ins before concealment, scope-dependent
- 2
Final Inspection
All work complete per approved plans; permit validated/signed by the Town of Haxtun Building Inspector
Applies to: Rooftop Solar Photovoltaic Permit
- 1
State Electrical Inspection (interconnection)
Performed by a State of Colorado inspector; required before the system's electrical connection can be energized
- 2
Final Inspection
Racking/roof penetrations verified; permit validated by the Town's Building Inspector
Final inspection only: Demolition Permit, Electrical Permit, Re-Roof Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Haxtun building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Haxtun building permits
Get alerts for Haxtun
We'll email you when Haxtun's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.