Residential Building Permit (New Construction) in Haxtun, Colorado

Required for new single-family home construction in the Town of Haxtun. Reviewed under the 2018 IRC (as locally adopted and amended by HMC § 150.02, Ord. 2025-1) plus the town's completed Climatic and Geographic Design Criteria (30 psf ground snow load, 115 mph wind design speed, 30-inch frost depth, ice barrier underlayment required). Issued via the Town's 'Application for Building Permit' form and validated/signed by the Town's Building Inspector.

Verified 2026-07-06 · Source

When you need this permit

  • Plans must comply with the 2018 IRC as locally amended, and meet Haxtun's completed Climatic and Geographic Design Criteria: 30 psf ground snow load, 115 mph wind design speed (Seismic Design Category B), 30-inch minimum frost line depth, ice barrier underlayment required
  • Foundation design must be based on an engineer's soils report and stamped by a Colorado-registered design professional (IRC R401.2 as amended); a site certification by a Colorado-registered design professional is required for setback verification on new Group R-3 occupancies
  • Foundation drains must be designed and inspected by a Colorado-registered design professional (IRC R405.1 as amended)
  • A plat map of the project on an 8.5 x 11 sheet showing footages from boundaries and type of construction must be included with the application
  • Electrical work must be inspected by a State of Colorado inspector (State Electrical Board/DORA), not the Town, per the Town's own permit application instructions
  • Permit holders must call UNCC (811) for all utility locates before any excavation
  • A large construction project (new home or extensive remodel) requires the contractor/homeowner to rent a roll-off dumpster for trash disposal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $0 to $1,000Town of Haxtun Application for Building Permit form (current, live)
$10.00
Building Permit Fee — valuation $1,001 to $2,500
$25.00
Building Permit Fee — valuation $2,501 and up
$25.00 plus $5.00 per $1,000 of valuation
Use Tax
4.5% of the valuation of all materials
Water Tap Fee (normal residential 3/4-inch)1-inch and larger taps include the tap fee plus cost of larger pipe and meter
$2,000.00
Sewer Tap Fee (normal residential 4-inch)Larger sewer taps include the tap fee plus cost of additional material
$2,000.00
Electric Tap Fee (normal residential single-phase 200-Amp service)Additional electrical needs above normal service billed time and materials
$1,000.00
Re-permitting fee after 180-day expiration (work not commenced/suspended)Only if no changes to original plans and suspension/abandonment has not exceeded 1 year; HMC § 150.02(B) amending IRC R108.5-equivalent expiration section
One-half of the original permit fee

Review timeline

Plan reviewHaxtun’s published plan-review target
3–3 business days

How long did your Residential Building Permit (New Construction) permit actually take in Haxtun?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete pour, per 30-inch minimum frost line depth; foundation drains inspected by a Colorado-registered design professional per local IRC amendment

  2. 2

    Insulation Inspection

    After completed and approved rough inspection, following installation of wall/ceiling/floor insulation and exterior windows, before wall coverings are installed (HMC § 150.02(B)(6), IRC R109.1.5.2 as added locally)

  3. 3

    Rough Electrical (State of Colorado Inspector)

    All new electrical installations must be inspected by a State of Colorado inspector before electricity can be supplied; allow up to 3 days for this inspection

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes; permit must be validated/signed by the Town of Haxtun Building Inspector

See the full Haxtun inspection guide — scheduling & re-inspection fees →

Tips

  • Haxtun's fee schedule is a simple flat/incremental table ($10-$25 base plus $5/$1,000 above $2,500) rather than a modern ICC valuation table — do not assume a peer-jurisdiction fee structure applies here.
  • Electrical work is inspected by a State of Colorado inspector (not the Town) — call the number on your permit and allow up to 3 days for that specific inspection, separate from the Town's own 3-working-day permit processing commitment.
  • Water, sewer, and electric tap fees ($2,000 / $2,000 / $1,000 respectively) are charged by the Town as the utility provider, in addition to the building permit fee and use tax — budget for these separately on new construction.
  • Foundation design must be stamped by a Colorado-registered design professional and based on an engineer's soils report — this is a real, current local amendment (IRC R401.2 as amended by Ord. 2025-1), not boilerplate.

Frequently asked questions

Haxtun requires a residential building permit (new construction) for: Plans must comply with the 2018 IRC as locally amended, and meet Haxtun's completed Climatic and Geographic Design Criteria: 30 psf ground snow load, 115 mph wind design speed (Seismic Design Category B), 30-inch minimum frost line depth, ice barrier underlayment required; Foundation design must be based on an engineer's soils report and stamped by a Colorado-registered design professional (IRC R401.2 as amended); a site certification by a Colorado-registered design professional is required for setback verification on new Group R-3 occupancies; Foundation drains must be designed and inspected by a Colorado-registered design professional (IRC R405.1 as amended); A plat map of the project on an 8.5 x 11 sheet showing footages from boundaries and type of construction must be included with the application; Electrical work must be inspected by a State of Colorado inspector (State Electrical Board/DORA), not the Town, per the Town's own permit application instructions; Permit holders must call UNCC (811) for all utility locates before any excavation; A large construction project (new home or extensive remodel) requires the contractor/homeowner to rent a roll-off dumpster for trash disposal. If your project isn't listed, confirm with Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) at 970-774-6104 before starting work.

In Haxtun, the published Building Permit Fee — valuation $0 to $1,000 is: $10.00. Additional published fees: Building Permit Fee — valuation $1,001 to $2,500 — $25.00; Building Permit Fee — valuation $2,501 and up — $25.00 plus $5.00 per $1,000 of valuation; Use Tax — 4.5% of the valuation of all materials; Water Tap Fee (normal residential 3/4-inch) — $2,000.00; Sewer Tap Fee (normal residential 4-inch) — $2,000.00; Electric Tap Fee (normal residential single-phase 200-Amp service) — $1,000.00; Re-permitting fee after 180-day expiration (work not commenced/suspended) — One-half of the original permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Haxtun's published plan-review target for a residential building permit (new construction) is 3–3 business days.

You'll need: Application for Building Permit (Town of Haxtun); Plat Map / Site Sketch; Foundation Design and Soils Report. See the required-documents checklist on this page for details on each.

Haxtun requires 4 inspection(s) for a residential building permit (new construction), in order: Foundation, Insulation Inspection, Rough Electrical (State of Colorado Inspector), Final Inspection. Schedule each through Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) (970-774-6104).

Apply through Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) at 145 S. Colorado Ave., P.O. Box 205, Haxtun, CO 80731. Phone: 970-774-6104. Office hours: Monday-Friday 7:30 am - 4:15 pm. After-hours/utility emergencies: Phillips County Comm Center, 970-854-2735.. Official information: https://townofhaxtun.colorado.gov/building-department.

The State of Colorado (State Electrical Board), not the Town of Haxtun. The Town's own Building Permit Application states that all new electrical installations and improvements must be inspected by a State of Colorado inspector before electricity can be supplied, and to allow up to three days for that inspection.

No. HMC § 150.02(B) deletes IRC R309.5 (fire sprinklers), R313.1 (townhouse automatic fire sprinkler systems), and R313.2 (one- and two-family automatic fire sprinkler systems) in their entirety.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Haxtun building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.