Residential Building Permit (New Construction) in Haxtun, Colorado
Required for new single-family home construction in the Town of Haxtun. Reviewed under the 2018 IRC (as locally adopted and amended by HMC § 150.02, Ord. 2025-1) plus the town's completed Climatic and Geographic Design Criteria (30 psf ground snow load, 115 mph wind design speed, 30-inch frost depth, ice barrier underlayment required). Issued via the Town's 'Application for Building Permit' form and validated/signed by the Town's Building Inspector.
Verified 2026-07-06 · Source
When you need this permit
- Plans must comply with the 2018 IRC as locally amended, and meet Haxtun's completed Climatic and Geographic Design Criteria: 30 psf ground snow load, 115 mph wind design speed (Seismic Design Category B), 30-inch minimum frost line depth, ice barrier underlayment required
- Foundation design must be based on an engineer's soils report and stamped by a Colorado-registered design professional (IRC R401.2 as amended); a site certification by a Colorado-registered design professional is required for setback verification on new Group R-3 occupancies
- Foundation drains must be designed and inspected by a Colorado-registered design professional (IRC R405.1 as amended)
- A plat map of the project on an 8.5 x 11 sheet showing footages from boundaries and type of construction must be included with the application
- Electrical work must be inspected by a State of Colorado inspector (State Electrical Board/DORA), not the Town, per the Town's own permit application instructions
- Permit holders must call UNCC (811) for all utility locates before any excavation
- A large construction project (new home or extensive remodel) requires the contractor/homeowner to rent a roll-off dumpster for trash disposal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour, per 30-inch minimum frost line depth; foundation drains inspected by a Colorado-registered design professional per local IRC amendment
- 2
Insulation Inspection
After completed and approved rough inspection, following installation of wall/ceiling/floor insulation and exterior windows, before wall coverings are installed (HMC § 150.02(B)(6), IRC R109.1.5.2 as added locally)
- 3
Rough Electrical (State of Colorado Inspector)
All new electrical installations must be inspected by a State of Colorado inspector before electricity can be supplied; allow up to 3 days for this inspection
- 4
Final Inspection
All work complete per approved plans and applicable codes; permit must be validated/signed by the Town of Haxtun Building Inspector
See the full Haxtun inspection guide — scheduling & re-inspection fees →
Tips
- Haxtun's fee schedule is a simple flat/incremental table ($10-$25 base plus $5/$1,000 above $2,500) rather than a modern ICC valuation table — do not assume a peer-jurisdiction fee structure applies here.
- Electrical work is inspected by a State of Colorado inspector (not the Town) — call the number on your permit and allow up to 3 days for that specific inspection, separate from the Town's own 3-working-day permit processing commitment.
- Water, sewer, and electric tap fees ($2,000 / $2,000 / $1,000 respectively) are charged by the Town as the utility provider, in addition to the building permit fee and use tax — budget for these separately on new construction.
- Foundation design must be stamped by a Colorado-registered design professional and based on an engineer's soils report — this is a real, current local amendment (IRC R401.2 as amended by Ord. 2025-1), not boilerplate.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Haxtun building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Haxtun
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Haxtun project checklist
Describe your project once and get every permit, document, and fee it triggers in Haxtun — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →