EV Charger / EVSE Permit in Haxtun, Colorado

Haxtun has no dedicated EV charger or EVSE permit and no distinct fee line item for electric vehicle charging equipment. An EV charger installation is billed under the Town's general valuation-based Application for Building Permit (the same combined form and fee table used for all building-related work, including the rooftop solar PV permit's structural scope), and the electrical/circuit work must be inspected by a State of Colorado electrical inspector rather than the Town, exactly as with any other new electrical installation. Colorado's HB24-1173 (Electric Vehicle Charging System Permits, 2024) requires expedited EV-charger permitting only for counties with 20,000+ population and municipalities with 10,000+ population -- Haxtun (population under 1,000) falls well below that threshold and is not a covered municipality under the statute.

Verified 2026-07-20 · Source

When you need this permit

  • Application for Building Permit (Town of Haxtun) required for the installation, using the general valuation-based fee schedule -- no dedicated EV/EVSE fee line exists
  • All new electrical installations and electrical improvements, including EV charger circuits, must be inspected by a State of Colorado electrical inspector before electricity can be supplied -- allow up to 3 days for that inspection, per the Town's own permit application instructions
  • Haxtun is below the population thresholds (10,000 for municipalities) set by Colorado HB24-1173, so the statute's mandatory model-code/expedited-review requirement for EV charger permits does not apply here
  • Permit holders must call UNCC (811) for all utility locates before work begins

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, general schedule) -- $0-$1,000 valuationTown of Haxtun Application for Building Permit (live PDF, re-fetched 2026-07-20); no standalone EV/EVSE fee line exists -- checked directly, full-text search for 'electric vehicle'/'EV'/'charging' found no dedicated fee item
$10.00
Building Permit Fee (valuation-based, general schedule) -- $1,001-$2,500 valuationTown of Haxtun Application for Building Permit (live PDF)
$25.00
Building Permit Fee (valuation-based, general schedule) -- $2,501 and upTown of Haxtun Application for Building Permit (live PDF)
$25.00 plus $5.00 per $1,000
Use TaxTown of Haxtun Application for Building Permit (live PDF)
4.5% of the valuation of all materials

Review timeline

Plan reviewHaxtun’s published plan-review target
Up to 3 business days

How long did your EV Charger / EVSE Permit permit actually take in Haxtun?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    State Electrical Inspection

    Performed by a State of Colorado inspector (phone 1-800-955-5770); required before the charger circuit can be energized -- allow up to 3 days

  2. 2

    Final Inspection

    Verified by the Town's Building Inspector

See the full Haxtun inspection guide — scheduling & re-inspection fees →

Tips

  • Haxtun has no EV-specific permit or fee -- an EV charger install is billed under the Town's general valuation-based Building Permit fee table, the same one used for any other small electrical/construction project.
  • As with solar and all other electrical work in Haxtun, expect the electrical/circuit portion of the install to be inspected by the State of Colorado, separate from the Town's own building-permit sign-off.
  • Colorado's HB24-1173 requires expedited, standardized EV-charger permitting only in counties of 20,000+ and municipalities of 10,000+ population -- Haxtun does not meet that threshold, so this statutory mandate does not apply here.

Frequently asked questions

Haxtun requires an ev charger / evse permit for: Application for Building Permit (Town of Haxtun) required for the installation, using the general valuation-based fee schedule -- no dedicated EV/EVSE fee line exists; All new electrical installations and electrical improvements, including EV charger circuits, must be inspected by a State of Colorado electrical inspector before electricity can be supplied -- allow up to 3 days for that inspection, per the Town's own permit application instructions; Haxtun is below the population thresholds (10,000 for municipalities) set by Colorado HB24-1173, so the statute's mandatory model-code/expedited-review requirement for EV charger permits does not apply here; Permit holders must call UNCC (811) for all utility locates before work begins. If your project isn't listed, confirm with Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) at 970-774-6104 before starting work.

In Haxtun, the published Building Permit Fee (valuation-based, general schedule) -- $0-$1,000 valuation is: $10.00. Additional published fees: Building Permit Fee (valuation-based, general schedule) -- $1,001-$2,500 valuation — $25.00; Building Permit Fee (valuation-based, general schedule) -- $2,501 and up — $25.00 plus $5.00 per $1,000; Use Tax — 4.5% of the valuation of all materials. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Haxtun's published plan-review target for an ev charger / evse permit is Up to 3 business days.

You'll need: Application for Building Permit (Town of Haxtun). See the required-documents checklist on this page for details on each.

Haxtun requires 2 inspection(s) for an ev charger / evse permit, in order: State Electrical Inspection, Final Inspection. Schedule each through Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) (970-774-6104).

Apply through Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) at 145 S. Colorado Ave., P.O. Box 205, Haxtun, CO 80731. Phone: 970-774-6104. Office hours: Monday-Friday 7:30 am - 4:15 pm. After-hours/utility emergencies: Phillips County Comm Center, 970-854-2735.. Official information: https://townofhaxtun.colorado.gov/building-department.

Haxtun, Colorado has adopted: 2018 International Building Code (IBC), Chapters 1-35 plus Appendices C, E, H, I & J — Haxtun Municipal Code (HMC) § 150.01, adopted by Ord. 2025-1, passed 10-6-2025; 2018 International Residential Code (IRC), Chapters 1-43 plus Appendices F, G, H & L — HMC § 150.02, adopted by Ord. 2025-1; 2018 International Mechanical Code (IMC), Chapters 1-15 — HMC § 150.03, adopted by Ord. 2025-1; 2018 International Fuel Gas Code (IFGC), Chapters 1-8 — HMC § 150.04, adopted by Ord. 2025-1; 2018 International Property Maintenance Code (IPMC), Chapters 1-8 — HMC § 150.05, adopted by Ord. 2025-1; Uniform Code for the Abatement of Dangerous Buildings, 1991 Edition (ICBO) — HMC § 150.06, adopted per C.R.S. Title 31, Art. 16, Part 2 (Ord. 2017-2, passed 4-3-2017; Ord. 2024-7, passed 11-4-2024); 2018 International Existing Building Code (IEBC), Chapters 1-16 — HMC § 150.07, adopted by Ord. 2025-1; 2021 International Energy Conservation Code (IECC), including Appendices CB and RB — HMC § 150.08, adopted by Ord. 2025-1; Colorado Model Electric Ready and Solar Ready Code, dated June 1, 2023 (Colorado Dept. of Local Affairs) — HMC § 150.09, adopted by Ord. 2025-1; 2021 International Plumbing Code (IPC), Chapters 1-13 — HMC § 150.10, adopted by Ord. 2025-1; 2023 National Electrical Code (NEC), exclusive of appendices (NFPA) — HMC § 150.11, adopted by Ord. 2025-1; Note on currency and provenance: this entire code slate (all 11 sections of HMC Chapter 150) was freshly re-adopted via Ordinance 2025-1, with second/final reading confirmed passed unanimously at the Town Council's October 6, 2025 Regular Meeting (minutes: 'A public hearing was held for Ordinance 2025-1 Adopting by reference the 2018 Editions of the International Building Codes, the 2021 Editions of the International Energy Conservation Code and the International Plumbing Code, the CO Model Solar Ready and Electric Code, and the 2023 Edition of the National Electric Code... the motion passed.'). This is unusually current for a town of Haxtun's size and directly corroborated by two independent official sources (the codified ordinance text on American Legal Publishing's code library, and the Town's own primary-source meeting minutes PDF).. Local amendments apply — see the Haxtun overview page for the full list.

No. Haxtun has no dedicated EV/EVSE permit or fee line item. An EV charger install is billed under the Town's general valuation-based Building Permit fee schedule ($10-$25 base, plus $5 per $1,000 above $2,500, plus 4.5% use tax on materials), and the electrical/circuit work is inspected by a State of Colorado inspector rather than the Town.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Haxtun building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.