Rooftop Solar Photovoltaic Permit in Haxtun, Colorado

Required for rooftop solar PV installations in Haxtun. Electrical connection work is subject to the State of Colorado electrical inspection process described under the Electrical Permit type; the installation itself is governed by the Colorado Model Electric Ready and Solar Ready Code (HMC § 150.09, adopted June 1, 2023 edition, via Ord. 2025-1) plus the 2023 NEC (HMC § 150.11).

Verified 2026-07-20 · Source

When you need this permit

  • Governed by the Colorado Model Electric Ready and Solar Ready Code, dated June 1, 2023 (HMC § 150.09), and the 2023 NEC (HMC § 150.11)
  • Electrical connection portions of a solar PV installation are inspected by a State of Colorado inspector, not the Town, per the Town's own permit application instructions
  • Application for Building Permit form required; plat map/sketch showing panel/array location on the property

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, general schedule)No standalone flat solar-PV fee is published; billed under the general valuation-based schedule. Re-confirmed 2026-07-20 by re-fetching the Town's live 'Application for Building Permit' PDF directly (full-text search for 'solar'/'photovoltaic' found no dedicated fee line) — the general valuation table is genuinely the current, applicable figure for a solar PV permit in Haxtun, not an unresolved gap. Also checked: Haxtun does not appear on SolarAPP+'s Colorado participant list (gosolarapp.org/landing-pages/solarapp-colorado — only Bennett, Wheat Ridge, Denver, Alamosa County, and Gilpin County offer full SolarAPP+ plan review as of this check), and Colorado's statewide solar-permit fee cap (C.R.S. 24-48.5-113, formerly cited elsewhere as 24-32-3312, which is actually an unrelated manufactured-housing statute) caps aggregate solar fees at $500 residential/$1,000 nonresidential — Haxtun's general valuation-based fee for a typical residential solar install falls well under that statutory ceiling, consistent with the town's own published table.
$10.00-$25.00 base, plus $5.00 per $1,000 above $2,500 valuation
Use Tax
4.5% of the valuation of all materials

Review timeline

Plan reviewHaxtun’s published plan-review target
Up to 3 business days

How long did your Rooftop Solar Photovoltaic Permit permit actually take in Haxtun?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    State Electrical Inspection (interconnection)

    Performed by a State of Colorado inspector; required before the system's electrical connection can be energized

  2. 2

    Final Inspection

    Racking/roof penetrations verified; permit validated by the Town's Building Inspector

See the full Haxtun inspection guide — scheduling & re-inspection fees →

Tips

  • Haxtun adopted the June 1, 2023 edition of the Colorado Model Electric Ready and Solar Ready Code fresh via Ord. 2025-1 (10-6-2025) — this is current, not a stale adoption.
  • As with all electrical work in Haxtun, expect the interconnection/electrical portion of your solar install to be inspected by the State of Colorado, separate from the Town's own building-permit sign-off.

Frequently asked questions

Haxtun requires a rooftop solar photovoltaic permit for: Governed by the Colorado Model Electric Ready and Solar Ready Code, dated June 1, 2023 (HMC § 150.09), and the 2023 NEC (HMC § 150.11); Electrical connection portions of a solar PV installation are inspected by a State of Colorado inspector, not the Town, per the Town's own permit application instructions; Application for Building Permit form required; plat map/sketch showing panel/array location on the property. If your project isn't listed, confirm with Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) at 970-774-6104 before starting work.

In Haxtun, the published Building Permit Fee (valuation-based, general schedule) is: $10.00-$25.00 base, plus $5.00 per $1,000 above $2,500 valuation. Additional published fees: Use Tax — 4.5% of the valuation of all materials. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Haxtun's published plan-review target for a rooftop solar photovoltaic permit is Up to 3 business days.

You'll need: Application for Building Permit (Town of Haxtun). See the required-documents checklist on this page for details on each.

Haxtun requires 2 inspection(s) for a rooftop solar photovoltaic permit, in order: State Electrical Inspection (interconnection), Final Inspection. Schedule each through Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) (970-774-6104).

Apply through Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) at 145 S. Colorado Ave., P.O. Box 205, Haxtun, CO 80731. Phone: 970-774-6104. Office hours: Monday-Friday 7:30 am - 4:15 pm. After-hours/utility emergencies: Phillips County Comm Center, 970-854-2735.. Official information: https://townofhaxtun.colorado.gov/building-department.

Haxtun, Colorado has adopted: 2018 International Building Code (IBC), Chapters 1-35 plus Appendices C, E, H, I & J — Haxtun Municipal Code (HMC) § 150.01, adopted by Ord. 2025-1, passed 10-6-2025; 2018 International Residential Code (IRC), Chapters 1-43 plus Appendices F, G, H & L — HMC § 150.02, adopted by Ord. 2025-1; 2018 International Mechanical Code (IMC), Chapters 1-15 — HMC § 150.03, adopted by Ord. 2025-1; 2018 International Fuel Gas Code (IFGC), Chapters 1-8 — HMC § 150.04, adopted by Ord. 2025-1; 2018 International Property Maintenance Code (IPMC), Chapters 1-8 — HMC § 150.05, adopted by Ord. 2025-1; Uniform Code for the Abatement of Dangerous Buildings, 1991 Edition (ICBO) — HMC § 150.06, adopted per C.R.S. Title 31, Art. 16, Part 2 (Ord. 2017-2, passed 4-3-2017; Ord. 2024-7, passed 11-4-2024); 2018 International Existing Building Code (IEBC), Chapters 1-16 — HMC § 150.07, adopted by Ord. 2025-1; 2021 International Energy Conservation Code (IECC), including Appendices CB and RB — HMC § 150.08, adopted by Ord. 2025-1; Colorado Model Electric Ready and Solar Ready Code, dated June 1, 2023 (Colorado Dept. of Local Affairs) — HMC § 150.09, adopted by Ord. 2025-1; 2021 International Plumbing Code (IPC), Chapters 1-13 — HMC § 150.10, adopted by Ord. 2025-1; 2023 National Electrical Code (NEC), exclusive of appendices (NFPA) — HMC § 150.11, adopted by Ord. 2025-1; Note on currency and provenance: this entire code slate (all 11 sections of HMC Chapter 150) was freshly re-adopted via Ordinance 2025-1, with second/final reading confirmed passed unanimously at the Town Council's October 6, 2025 Regular Meeting (minutes: 'A public hearing was held for Ordinance 2025-1 Adopting by reference the 2018 Editions of the International Building Codes, the 2021 Editions of the International Energy Conservation Code and the International Plumbing Code, the CO Model Solar Ready and Electric Code, and the 2023 Edition of the National Electric Code... the motion passed.'). This is unusually current for a town of Haxtun's size and directly corroborated by two independent official sources (the codified ordinance text on American Legal Publishing's code library, and the Town's own primary-source meeting minutes PDF).. Local amendments apply — see the Haxtun overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Haxtun building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.