Haxtun does not publish a standalone 'Change of Use' or 'Change of Occupancy' permit application — the Town's Building Department page and Building Permit Application form cover general construction permitting. In Colorado, a final Certificate of Occupancy is generally contingent on satisfying all local departments with applicable jurisdiction (which may include Fire, in addition to Building). A use/occupancy change is presumed to be processed through the Town's general Building Permit Application; contact the Building Department to confirm requirements and applicable code edition for a specific project.

Reviewed 2026-08-13 · Source

When you need this permit

  • No standalone change-of-use or change-of-occupancy application is published on the Town's website as of this review
  • In Colorado, a final Certificate of Occupancy is generally contingent on satisfying all local departments with applicable jurisdiction, which may include Fire, in addition to the Building Department
  • Processed, if at all, through the Town's general Building Permit Application; contact the Building Department (970-774-6104) to confirm requirements for a specific change-of-use project
  • Haxtun Municipal Code § 150.07 adopts the 2018 International Existing Building Code (IEBC), Chapters 1-16, per Ordinance 2025-1 — this file's own code-adoption research confirms this edition governs existing-building/change-of-occupancy analysis within the Town

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (if construction accompanies the change)Contact the Building Department (970-774-6104) for a current fee quote
Not published as a standalone change-of-use fee line

Review timeline

Plan review
Not published — contact the department

How long did your Change of Use / Change of Occupancy permit actually take in Haxtun?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection / Certificate of Occupancy

    Certificate of Occupancy generally contingent on satisfying all local departments with applicable jurisdiction, which may include Fire

See the full Haxtun inspection guide — scheduling & re-inspection fees →

Tips

  • Haxtun has adopted the 2018 IEBC (Chapters 1-16) via Municipal Code § 150.07 (Ordinance 2025-1) — this is the governing code for existing-building/change-of-occupancy analysis, even though the Town has no separate change-of-use application form.

Frequently asked questions

Haxtun requires a change of use / change of occupancy permit for: No standalone change-of-use or change-of-occupancy application is published on the Town's website as of this review; In Colorado, a final Certificate of Occupancy is generally contingent on satisfying all local departments with applicable jurisdiction, which may include Fire, in addition to the Building Department; Processed, if at all, through the Town's general Building Permit Application; contact the Building Department (970-774-6104) to confirm requirements for a specific change-of-use project; Haxtun Municipal Code § 150.07 adopts the 2018 International Existing Building Code (IEBC), Chapters 1-16, per Ordinance 2025-1 — this file's own code-adoption research confirms this edition governs existing-building/change-of-occupancy analysis within the Town. If your project isn't listed, confirm with Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) at 970-774-6104 before starting work.

In Haxtun, the published Building Permit Fee (if construction accompanies the change) is: Not published as a standalone change-of-use fee line. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Haxtun does not publish a plan-review timeline for this permit. Contact Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) at 970-774-6104 for current turnaround.

You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

Haxtun requires 1 inspection(s) for a change of use / change of occupancy permit, in order: Final Inspection / Certificate of Occupancy. Schedule each through Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) (970-774-6104).

Apply through Town of Haxtun (Town Superintendent / Building Inspector function; Town Hall administers permits) at 145 S. Colorado Ave., P.O. Box 205, Haxtun, CO 80731. Phone: 970-774-6104. Office hours: Monday-Friday 7:30 am - 4:15 pm. After-hours/utility emergencies: Phillips County Comm Center, 970-854-2735.. Official information: https://townofhaxtun.colorado.gov/building-department.

Haxtun, Colorado has adopted: 2018 International Building Code (IBC), Chapters 1-35 plus Appendices C, E, H, I & J — Haxtun Municipal Code (HMC) § 150.01, adopted by Ord. 2025-1, passed 10-6-2025; 2018 International Residential Code (IRC), Chapters 1-43 plus Appendices F, G, H & L — HMC § 150.02, adopted by Ord. 2025-1; 2018 International Mechanical Code (IMC), Chapters 1-15 — HMC § 150.03, adopted by Ord. 2025-1; 2018 International Fuel Gas Code (IFGC), Chapters 1-8 — HMC § 150.04, adopted by Ord. 2025-1; 2018 International Property Maintenance Code (IPMC), Chapters 1-8 — HMC § 150.05, adopted by Ord. 2025-1; Uniform Code for the Abatement of Dangerous Buildings, 1991 Edition (ICBO) — HMC § 150.06, adopted per C.R.S. Title 31, Art. 16, Part 2 (Ord. 2017-2, passed 4-3-2017; Ord. 2024-7, passed 11-4-2024); 2018 International Existing Building Code (IEBC), Chapters 1-16 — HMC § 150.07, adopted by Ord. 2025-1; 2021 International Energy Conservation Code (IECC), including Appendices CB and RB — HMC § 150.08, adopted by Ord. 2025-1; Colorado Model Electric Ready and Solar Ready Code, dated June 1, 2023 (Colorado Dept. of Local Affairs) — HMC § 150.09, adopted by Ord. 2025-1; 2021 International Plumbing Code (IPC), Chapters 1-13 — HMC § 150.10, adopted by Ord. 2025-1; 2023 National Electrical Code (NEC), exclusive of appendices (NFPA) — HMC § 150.11, adopted by Ord. 2025-1; Note on currency and provenance: this entire code slate (all 11 sections of HMC Chapter 150) was freshly re-adopted via Ordinance 2025-1, with second/final reading confirmed passed unanimously at the Town Council's October 6, 2025 Regular Meeting (minutes: 'A public hearing was held for Ordinance 2025-1 Adopting by reference the 2018 Editions of the International Building Codes, the 2021 Editions of the International Energy Conservation Code and the International Plumbing Code, the CO Model Solar Ready and Electric Code, and the 2023 Edition of the National Electric Code... the motion passed.'). This is unusually current for a town of Haxtun's size and directly corroborated by two independent official sources (the codified ordinance text on American Legal Publishing's code library, and the Town's own primary-source meeting minutes PDF).. Local amendments apply — see the Haxtun overview page for the full list.

No standalone permit or application distinct from the general Building Permit process was found published. The Town has adopted the 2018 International Existing Building Code (Municipal Code § 150.07) for existing-building/occupancy analysis. Contact the Building Department (970-774-6104) to confirm requirements for a specific project.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-08-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Haxtun building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.