Skip to main content
PermitBase

Woodland Park building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Woodland Park, Colorado.

Verified 2026-07-19 · Source

How to schedule

Inspections are requested through the building department below.

Address
City of Woodland Park Planning & Building Department, 220 W. South Avenue, P.O. Box 9007, Woodland Park, CO 80866 — Pikes Peak Regional Building Department, 2880 International Circle, Colorado Springs, CO 80910
Phone
City Planning & Building: 719-687-5202 — Pikes Peak Regional Building Department: 719-327-2880
Office hours
City Planning & Building Department: Monday-Thursday 7:30 a.m.-5:00 p.m.; Friday 7:30 a.m.-4:00 p.m.

Published scheduling rules

  • Garage sale signs: may not be attached to telephone/stop/other public poles, may not be installed more than 24 hours before the sale or left up more than 24 hours after, and may not be installed within the street right-of-way (Sign Permit)

Inspection sequence

Applies to: Building Permit (Pikes Peak Regional Building Department)

  1. 1

    Footing (BFT)

    Per PPRBD's Required Inspections listing for single-family new construction.

  2. 2

    Foundation (BFN)

    Per PPRBD's Required Inspections listing; foundation drain (BFD) and foundation insulation (BFI) inspections may also apply depending on scope.

  3. 3

    Frame (BFR)

    Structural framing inspection, per PPRBD's Required Inspections listing.

  4. 4

    Insulation (BIN)

    Per PPRBD's Required Inspections listing.

  5. 5

    Final and Energy Final

    Final building inspection and separate energy-code final, per PPRBD's Required Inspections listing.

Applies to: Multi-Use Zoning Development Permit (Additions, Garages, Decks, Sheds, Accessory Structures, Alterations)

  1. 1

    Footing

    For garages, additions, and decks requiring a footing (per PPRBD's Required Inspections listing for residential accessory structures such as decks).

  2. 2

    Frame

    Structural framing inspection, per PPRBD's Required Inspections listing.

  3. 3

    Final

    Final inspection prior to use/occupancy, per PPRBD's Required Inspections listing.

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Electrical Rough-In

    Conduit runs, wire sizing, and disconnect placement before cover, per PPRBD's adopted NEC edition

  2. 2

    Final and Energy Final

    Racking, roof/ground-mount attachment, and electrical connections verified; per PPRBD's Required Inspections listing for structural work generally

Re-inspection fees

Building Permit (Pikes Peak Regional Building Department)Re-inspection Fee · PPRBD 2023 Building Permit Fee Schedule - Woodland Park (Table D.Q).
$50.00 for 1st incident; $100.00 for 2nd incident; $200.00 for 3rd incident (plus a 2-work-day inspection delay)

Woodland Park building permits

Get alerts for Woodland Park

We'll email you when Woodland Park's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.