How to schedule
Inspections are requested through the building department below.
- Address
- City of Woodland Park Planning & Building Department, 220 W. South Avenue, P.O. Box 9007, Woodland Park, CO 80866 — Pikes Peak Regional Building Department, 2880 International Circle, Colorado Springs, CO 80910
- Phone
- City Planning & Building: 719-687-5202 — Pikes Peak Regional Building Department: 719-327-2880
- Office hours
- City Planning & Building Department: Monday-Thursday 7:30 a.m.-5:00 p.m.; Friday 7:30 a.m.-4:00 p.m.
- Website
- Official site
Inspection sequence
Applies to: Building Permit (Pikes Peak Regional Building Department)
- 1
Footing (BFT)
Per PPRBD's Required Inspections listing for single-family new construction.
- 2
Foundation (BFN)
Per PPRBD's Required Inspections listing; foundation drain (BFD) and foundation insulation (BFI) inspections may also apply depending on scope.
- 3
Frame (BFR)
Structural framing inspection, per PPRBD's Required Inspections listing.
- 4
Insulation (BIN)
Per PPRBD's Required Inspections listing.
- 5
Final and Energy Final
Final building inspection and separate energy-code final, per PPRBD's Required Inspections listing.
Applies to: Multi-Use Zoning Development Permit (Additions, Garages, Decks, Sheds, Accessory Structures, Alterations)
- 1
Footing
For garages, additions, and decks requiring a footing (per PPRBD's Required Inspections listing for residential accessory structures such as decks).
- 2
Frame
Structural framing inspection, per PPRBD's Required Inspections listing.
- 3
Final
Final inspection prior to use/occupancy, per PPRBD's Required Inspections listing.
Applies to: Solar Photovoltaic (PV) Permit
- 1
Electrical Rough-In
Conduit runs, wire sizing, and disconnect placement before cover, per PPRBD's adopted NEC edition
- 2
Final and Energy Final
Racking, roof/ground-mount attachment, and electrical connections verified; per PPRBD's Required Inspections listing for structural work generally
Final inspection only: EV Charger / Electric Vehicle Charging Station Permit, Fence, Dumpster Enclosure & Retaining Wall Zoning Development Permit, Sign Zoning Development Permit (Permanent, Portable/Temporary, and Banner), Zoning Development Permit — Single Family Residence, Townhome, or Condominium
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Woodland Park building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Woodland Park building permits
Get alerts for Woodland Park
We'll email you when Woodland Park's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.