Eaton building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Eaton, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Town of Eaton, 223 1st St, Eaton, CO 80615
- Phone
- 970-305-3161 (SAFEbuilt, Contract Building Inspector); (970) 454-3338 (Town Clerk's Office / main line); fax (970) 454-3339
- Office hours
- Not separately published on the Building and Permitting page as of the last verification; the Town's main contact line is (970) 454-3338.
- Website
- Official site
Published scheduling rules
- Schedule inspections at least 24 hours in advance by calling 970-305-3161 ext. 1 (SAFEbuilt); clean up all debris and clear gutters before calling for final inspection. (Roofing Permit (Re-Roof))
Inspection sequence
Applies to: Residential Building Permit (New Construction / Addition / Remodel / Repair / Basement Finish)
- 1
Foundation/Footing
Prior to concrete placement
- 2
Structural Rough / Framing
Framing complete before cover
- 3
Insulation Inspection
Required following installation of wall, ceiling, and floor insulation and exterior windows, and before wall coverings are installed, per Ordinance No. 664's IRC Sec. R109.1.5.2 amendment
- 4
Electrical Rough / Mechanical Rough / Plumbing Rough
Trade rough-ins before concealment
- 5
Final Building
All work complete per approved plans; Energy Compliance Certificate and leak-test reports required before Certificate of Occupancy
Applies to: Commercial Building Permit (New Building / Addition / Remodel-Tenant Improvement / Change of Occupancy)
- 1
Foundation/Footing
Prior to concrete placement
- 2
Structural Rough / Framing
Structural frame complete before cover
- 3
Electrical Rough / Mechanical Rough / Plumbing Rough
Trade rough-ins before concealment; the applicant must give the building inspector at least one working day's notice per the application's notice terms
- 4
Final Building / Certificate of Occupancy
All work complete per approved plans; Energy Compliance Certificate and leak-test reports required before CO. Upon completion of all workflow steps in CommunityCore the final CO/TCO/CC is printed, then signed and emailed by the Town
Applies to: Residential/Commercial Solar Permit
- 1
Electrical Rough
Conduit runs and wire sizing before cover
- 2
Electrical Permanent Meter
Production meter installation verified
- 3
Electrical Final
System energized and verified
Applies to: Change of Use / Change of Occupancy Permit
- 1
Life Safety / Plan Compliance Review
Confirms the space meets the life-safety, egress, and fire-separation requirements of the new occupancy classification before work proceeds
- 2
Final Inspection / Certificate of Occupancy
All work complete per approved plans; a new Certificate of Occupancy is issued reflecting the changed use/occupancy classification
Applies to: Electrical Permit
- 1
Electrical Rough
Wiring and panel installed before concealment
- 2
Electrical Final
Devices installed, system energized
Applies to: EV Charger / EVSE Permit (Billed as General Electrical Work)
- 1
Electrical Rough
Charger circuit wiring and breaker sizing before concealment
- 2
Electrical Final
EVSE installed, GFCI/disconnect verified, system energized
Applies to: Fire Sprinkler & Fire Alarm System Permit
- 1
Rough-In Inspection
Piping/wiring installed before concealment
- 2
Final/Acceptance Inspection
System tested and verified operational; one inspection per project phase is included in the permit fee, additional inspections billed at $75.00/hr
Applies to: Mechanical / HVAC Permit (Furnace, Air Conditioning, Gas Line, Gas Fireplace)
- 1
Mechanical Rough (incl. Gas Test where applicable)
Equipment/ductwork before concealment
- 2
Mechanical Final
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit (Water Line/Sewer Repair, Backflow, Water Heater)
- 1
Plumbing Rough / Underground
Before concealment
- 2
Plumbing Final
Fixtures connected, system tested
Applies to: Roofing Permit (Re-Roof)
- 1
Mid-Roof Inspection
Required for tile roofs and commercial flat roofs only
- 2
Final Inspection
Verifies completed roof is up to code and all debris removed; a secured ladder must be provided for the inspector; Remote Video Inspection (RVI) option available
Final inspection only: Demolition Permit, Fence Permit, Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Applications & forms
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eaton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Eaton building permits
Get alerts for Eaton
We'll email you when Eaton's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.