Commercial Building Permit (New Building / Addition / Remodel-Tenant Improvement / Change of Occupancy) in Eaton, Colorado
Required for commercial construction in Eaton — new buildings, additions, remodels (including tenant improvements/finishes), repair/replacement, office/warehouse projects, changes of occupancy, and new systems — using the Town's own dedicated 'Commercial Building Permit' application form, which is distinct from the Residential Building Permit form. Reviewed under the 2024 IBC as adopted by Ordinance No. 664 (Town states effective January 1, 2026); plan review and inspections performed under contract by SAFEbuilt, with permits issued by the Town Clerk's Office and processed through the CommunityCore online portal.
Verified 2026-08-02 · Source
When you need this permit
- Completed and signed Commercial Building Permit application (PURPOSE OF PERMIT checkboxes on the Town's own form: New Building, Addition, Remodel, Repair/Replacement, Office/Warehouse, Change of Occupancy, New System, Other)
- Digital submittal (flash drive, emailed, or uploaded via CommunityCore)
- Building plans: wall sections, floor plan, framing plan, elevations, door and window schedule, cabinet layout
- Life safety and code study plan designed and stamped by an architect
- Engineered foundation/structural drawings
- Plot plan showing all distances to lot lines and structures
- Site grading plan stamped by a civil engineer
- Mechanical, plumbing, and electrical drawings stamped by an engineer
- Energy code compliance documents (the application form's checklist still says '2012 Energy Code compliance documents' — a stale reference on the form itself; the Town has adopted the 2024 IECC via Ordinance No. 664 and separately requires an Energy Compliance Certificate with ductwork and building-envelope leak-test reports before Certificate of Occupancy)
- Fire sprinkler determination and Fire District approval are captured on the application (FIRE SPRINKLER REQUIRED yes/no, FIRE DISTRICT APPROVAL yes/no) — coordinate with the local fire protection district
- IBC construction type (IA-VB), occupancy classification(s) (A, B, E, F, H, I, M, S, U), building height/stories, and floor-by-floor square footage and valuations must be declared on the application
- Contractors must register/be verified in CommunityCore and pay the Town's $50/year Contractor Fee before applying online (plumbers and electricians exempt from that fee)
- Applicant is responsible for the plan review fee and administrative review fee regardless of whether the permit is ultimately obtained, per the application's signed acknowledgement
- Any change of plans, layout, use, or occupancy must be approved before proceeding; permits expire if no progress is made after 180 days of issuance and between inspections
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 8 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Prior to concrete placement
- 2
Structural Rough / Framing
Structural frame complete before cover
- 3
Electrical Rough / Mechanical Rough / Plumbing Rough
Trade rough-ins before concealment; the applicant must give the building inspector at least one working day's notice per the application's notice terms
- 4
Final Building / Certificate of Occupancy
All work complete per approved plans; Energy Compliance Certificate and leak-test reports required before CO. Upon completion of all workflow steps in CommunityCore the final CO/TCO/CC is printed, then signed and emailed by the Town
See the full Eaton inspection guide — scheduling & re-inspection fees →
Tips
- Eaton publishes NO separate tenant-improvement/tenant-finish permit type, form, or fee line — TI work is filed on the same Commercial Building Permit form under the 'Remodel' (and, where applicable, 'Change of Occupancy') purpose checkboxes, and is billed on the same valuation-based non-residential fee table. Confirmed by enumerating every permit application the Town publishes (Over the Counter, Residential Building Permit, Commercial Permit) — there is no fourth, TI-specific form.
- The commercial form's submittal checklist still says '2012 Energy Code compliance documents' — a stale reference on the form itself. The Town adopted the 2024 IECC via Ordinance No. 664 (Town states effective January 1, 2026) and requires an Energy Compliance Certificate plus ductwork/building-envelope leak-test reports before Certificate of Occupancy; follow the 2024 IECC, not the form's stale line.
- Budget for non-residential impact fees on new development — they can dwarf the permit fee itself (e.g. retail street impact alone is $14.036/sq ft under Ordinance No. 660, effective April 27, 2025). They are charged separately from building permit and plan-review fees.
- The signed application makes you liable for the plan review fee and administrative review fee even if you never pull the permit — and any delinquent permit fees on the property must be paid before a new permit will issue.
- Fire sprinkler determination and Fire District approval are explicit fields on the commercial application — coordinate with the local fire protection district early, alongside SAFEbuilt (970-305-3161) for technical questions.
- No review-timeline SLA is published by the Town for commercial (or any) permits — payment is invoiced by email after reviews complete, and the permit is issued only once approved and paid; contact SAFEbuilt directly to gauge current review queue times.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eaton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Eaton.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Eaton
Commercial Building Permit (New Building / Addition / Remodel-Tenant Improvement / Change of Occupancy) in other cities
Look up this fee in a different city →
Now live
Build your Eaton project checklist
Describe your project once and get every permit, document, and fee it triggers in Eaton — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →