Change of Use / Change of Occupancy Permit — Eaton, Colorado · Requirements sheet
Verified 2026-08-13 · Source: https://www.eatonco.org/media/166
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Change of Occupancy Permit in Eaton, Colorado
Required when a building or structure's use or occupancy classification changes in Eaton. The Town publishes no separate Change of Use or Change of Occupancy permit type, application form, or fee line — 'CHANGE OF OCCUPANCY' is one of the checkbox options under 'Purpose of Permit' directly on the Town's own Commercial Building Permit application (the same form used for new commercial buildings, additions, remodels, and tenant improvements), and is billed under the same valuation-based Non-Residential Construction fee table. Reviewed under the 2024 International Existing Building Code (IEBC), Chapter 10 (Change of Occupancy), and the 2024 IBC, both adopted by Ordinance No. 664.
Verified 2026-08-13 · Source
When you need this permit
- Filed on the Town's Commercial Building Permit application (media/166) by checking 'CHANGE OF OCCUPANCY' under Purpose of Permit — Eaton publishes no separate change-of-use/change-of-occupancy application, fee line, or process page (checked the Building and Permitting page, Fee Schedule, and the Commercial and Counter Building Permit application forms directly)
- Reviewed under the 2024 International Existing Building Code (IEBC), Chapter 10 (Change of Occupancy provisions), and the 2024 IBC, as adopted by Ordinance No. 664
- Life safety and code study plan, designed and stamped by an architect, addressing the new occupancy classification — the same commercial-only submittal item required for new commercial construction
- 1st/2nd occupancy classification (A, B, E, F, H, I, M, S, U) fields must be declared on the application, along with building height/stories and floor-by-floor square footage
- Fire sprinkler determination ('FIRE SPRINKLER REQUIRED') and Fire District approval ('FIRE DISTRICT APPROVAL') fields on the application apply to change-of-occupancy submittals the same as new construction — coordinate with SAFEbuilt and the Eaton Fire Protection District where the new occupancy classification triggers fire-protection requirements
- Per the application's own notice text: 'Any change in the use or occupancy of the building or structure must be approved prior to proceeding with construction'
- Applicant is responsible for the plan review fee and administrative review fee regardless of whether the permit is ultimately obtained, per the application's signed acknowledgement
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Life Safety / Plan Compliance Review
Confirms the space meets the life-safety, egress, and fire-separation requirements of the new occupancy classification before work proceeds
- 2
Final Inspection / Certificate of Occupancy
All work complete per approved plans; a new Certificate of Occupancy is issued reflecting the changed use/occupancy classification
See the full Eaton inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate Change of Use or Change of Occupancy permit type in Eaton, the same pattern already documented in this file for tenant improvements: it's a checkbox purpose ('CHANGE OF OCCUPANCY') on the same Commercial Building Permit form used for new buildings, additions, and remodels/TI work, confirmed directly on the Town's own application PDF.
- The Commercial Building Permit application's own printed notice states plainly that 'any change in the use or occupancy of the building or structure must be approved prior to proceeding with construction' — don't begin work or reconfigure a space for a new use before that approval is in hand.
- Because occupancy-classification changes routinely trigger fire-protection requirements (sprinklers, alarms, egress changes), coordinate early with both SAFEbuilt (970-305-3161) and the Eaton Fire Protection District (970-454-2115) — the application's separate 'Fire Sprinkler Required' and 'Fire District Approval' fields apply here as much as to new construction.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eaton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Eaton
Change of Use / Change of Occupancy Permit in other cities
Compare change of use / change of occupancy permit fees across Colorado →
Look up this fee in a different city →