EV Charger / EVSE Permit (Billed as General Electrical Work) in Eaton, Colorado

Required for installation of a Level 2 (or higher) electric vehicle charger/EVSE in Eaton. The Town has no dedicated EV-charger fee line item, application form, or ordinance distinct from the Colorado HB24-1173 EV-charger-permitting statute's requirements — Eaton's own population (approx. 6,000 per Census QuickFacts) is below the 10,000-population threshold that makes a municipality a 'covered municipality' under HB24-1173 (Electric Vehicle Charging System Permits Act, effective Aug. 7, 2024), so the Town is not required to adopt the Colorado Energy Office's model EV-charger permitting code or a dedicated objective-standards ordinance. An EV charger circuit is billed under the Town's general 'All Other Electrical Work (by valuation)' fee tier on the same Fee Schedule used for other electrical work not tied to new living space, and reviewed under the 2023 NEC Article 625 (Electric Vehicle Power Transfer System) as adopted by Ordinance No. 664.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical Permit application (via the Residential Building Permit / Commercial Permit / Counter Building Permit forms, which each include an Electrical Contractor section) submitted through CommunityCore
  • Licensed electrical contractor information, or the Town's contractor registration for homeowner-performed work Contractor
  • Electrical plan review required for all electrical permits (residential and non-residential)
  • No dedicated EV-charger checklist, model-code adoption, or 3-business-day HB24-1173 notification commitment was found published by the Town — Eaton is below the 10,000-population 'covered municipality' threshold that triggers HB24-1173's requirements

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

All Other Electrical Work (by valuation) — $1.00 to $2,000.00Town of Eaton Fee Schedule, Electrical Permit Fees, p.2 — the general valuation-based tier that governs an EV charger/EVSE circuit, since it is not new living space and no dedicated EV line item exists
$100.00
All Other Electrical Work (by valuation) — over $2,000.00
$200.00 plus $10.00 for each additional $1,000.00 of value
Electrical Plan Review (Residential and Non-Residential)
65% of Electrical Permit Fee
Electrical Re-Inspection Fee
$85.00

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit (Billed as General Electrical Work) permit actually take in Eaton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Rough

    Charger circuit wiring and breaker sizing before concealment

  2. 2

    Electrical Final

    EVSE installed, GFCI/disconnect verified, system energized

See the full Eaton inspection guide — scheduling & re-inspection fees →

Tips

  • Eaton has no EV-charger-specific permit, form, or fee line — a home EV charger/EVSE is billed under the general valuation-based 'All Other Electrical Work' tier ($100 minimum for work valued $1-$2,000; $200 plus $10 per additional $1,000 above that), the same table used for panel upgrades and other non-living-space electrical work.
  • Colorado's HB24-1173 (EV Charging System Permits Act) requires 'covered municipalities' (population 10,000+) to adopt streamlined EV-charger permitting standards by Dec. 31, 2025 — Eaton, at roughly 6,000 residents, falls below that threshold and is not bound by the Act's model-code-or-ordinance mandate or its 3-business-day decision-notification clock.
  • Electrical Plan Review is a separate 65%-of-permit-fee line item added on top of the base electrical permit fee, applicable to EV charger circuits as to any other electrical work.

Frequently asked questions

Eaton requires an ev charger / evse permit (billed as general electrical work) for: Electrical Permit application (via the Residential Building Permit / Commercial Permit / Counter Building Permit forms, which each include an Electrical Contractor section) submitted through CommunityCore; Licensed electrical contractor information, or the Town's contractor registration for homeowner-performed work; Electrical plan review required for all electrical permits (residential and non-residential); No dedicated EV-charger checklist, model-code adoption, or 3-business-day HB24-1173 notification commitment was found published by the Town — Eaton is below the 10,000-population 'covered municipality' threshold that triggers HB24-1173's requirements. If your project isn't listed, confirm with Town of Eaton Building Department (permits issued by the Town Clerk's Office; inspections and plan review contracted to SAFEbuilt) at 970-305-3161 (SAFEbuilt, Contract Building Inspector); (970) 454-3338 (Town Clerk's Office / main line); fax (970) 454-3339 before starting work.

Eaton has no dedicated EV-charger fee. It is billed under the Town's general 'All Other Electrical Work (by valuation)' tier: $100.00 minimum for work valued $1.00-$2,000.00, or $200.00 plus $10.00 per additional $1,000.00 of value above that, per the Town of Eaton Fee Schedule.

Eaton does not publish a plan-review timeline for this permit. Contact Town of Eaton Building Department (permits issued by the Town Clerk's Office; inspections and plan review contracted to SAFEbuilt) at 970-305-3161 (SAFEbuilt, Contract Building Inspector); (970) 454-3338 (Town Clerk's Office / main line); fax (970) 454-3339 for current turnaround.

You'll need: Electrical Permit Application (CommunityCore). See the required-documents checklist on this page for details on each.

Eaton requires 2 inspection(s) for an ev charger / evse permit (billed as general electrical work), in order: Electrical Rough, Electrical Final. Schedule each through Town of Eaton Building Department (permits issued by the Town Clerk's Office; inspections and plan review contracted to SAFEbuilt) (970-305-3161 (SAFEbuilt, Contract Building Inspector); (970) 454-3338 (Town Clerk's Office / main line); fax (970) 454-3339).

Apply through Town of Eaton Building Department (permits issued by the Town Clerk's Office; inspections and plan review contracted to SAFEbuilt) at Town of Eaton, 223 1st St, Eaton, CO 80615. Phone: 970-305-3161 (SAFEbuilt, Contract Building Inspector); (970) 454-3338 (Town Clerk's Office / main line); fax (970) 454-3339, email: coemail@safebuilt.com (SAFEbuilt inspections/permit processing). Office hours: Not separately published on the Building and Permitting page as of this review; the Town's main contact line is (970) 454-3338.. Official information: https://www.eatonco.org/building-and-permitting.

Eaton, Colorado has adopted: 2024 International Building Code (IBC), Chapters 1-33 and Appendix Chapters H and I — adopted by Ordinance No. 664, amending Eaton Municipal Code Sec. 6-1-1, passed on second/final reading November 20, 2025; 2024 International Residential Code (IRC), Chapters 1-43 and Appendix AB — Ordinance No. 664, Sec. 6-1-2; 2024 International Mechanical Code (IMC); 2024 International Fuel Gas Code (IFGC); 2024 International Plumbing Code (IPC); 2024 International Energy Conservation Code (IECC); 2024 International Property Maintenance Code (IPMC); 2024 International Existing Building Code (IEBC); 2023 National Electrical Code (NEC); 2024 International Swimming Pool and Spa Code (ISPSC); Colorado Model Electric and Solar Ready Code, 2023 Edition — Ordinance No. 664, re-numbered as Eaton Municipal Code Sec. 6-1-12; Colorado Wildfire Resiliency Code, 2025 Edition — Ordinance No. 664, re-numbered as Eaton Municipal Code Sec. 6-1-13; All codes adopted pursuant to Title 31, Article 16, Part 2, C.R.S. Ordinance No. 664 was introduced/approved on first reading October 16, 2025, and passed as amended on final reading November 20, 2025; the Town's own Building and Permitting page states these codes 'will go into effect January 1, 2026,' a later effective date than the ordinance's own standard 30-day-after-publication clause (Section 17) — both dates are disclosed since the Town does not itself reconcile them on a single page. This corpus treats January 1, 2026 (the Town's own explicit statement on its current Building and Permitting page) as the operative date for practical purposes.; NOTE (data-integrity flag): A ProCode Inc.-branded 'Solar Permit Submissions and FAQs' handout linked from the Town's own Building and Permitting page (V4.5.22, dated April 2022, still bearing a Johnstown, CO return address) cites a stale 'Adopted Codes' list (2018 IFC, 2020 NEC, 2018 IBC, 2018 IRC) that predates both the Town's 2024 I-Code adoption (Ordinance No. 664) and the ProCode-to-SAFEbuilt rebrand. This corpus does NOT treat that stale document as a governing code citation; the current codes above (per the Building and Permitting page and Ordinance No. 664 itself) govern. The same handout's technical figures for wind speed (115 mph) and ground snow load (30 psf) are corroborated independently by Ordinance No. 664's own Table R301.2(1) and are treated as current on that independent basis, not on the stale handout's authority.. Local amendments apply — see the Eaton overview page for the full list.

No. HB24-1173 only binds 'covered municipalities' with population 10,000 or more. Eaton's population is approximately 6,000 per Census QuickFacts, so the Town is not required to adopt the Colorado Energy Office's model EV-charger permitting code, an objective-standards ordinance, or the Act's 3-business-day permit-decision notification requirement.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eaton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.