Required for plumbing installation, alteration, or repair in La Salle, issued locally by the Town (via ProCode) under the 2018 IPC as adopted, with local frost-depth and sewer-depth amendments carried forward from codified Chapter 18. Plumbers must hold a current Colorado State Plumbing Board (DORA) license, contemporaneously verified by the Town/ProCode per HB19-1086.

Verified 2026-07-06 · Source

When you need this permit

  • Governed by the 2018 IPC as currently enforced by the Town
  • Exterior water supply piping required not less than 6 inches below the frost line and not less than 48 inches below finish grade (local Chapter 18 amendment)
  • Plumbers must register with the Town/ProCode before applying for a permit and provide current Colorado DORA State Plumbing Board license credentials, subject to contemporaneous verification
  • Two dedicated documents on the Town's Building Permits page address plumbing contemporaneous review specifically (2019 SOP and a general contemporaneous-reviews procedure)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plumbing Permit FeeValuation-based; no current published fee table — contact ProCode or Town Hall for a quote
Not published — contact the department
Construction Use Tax
2% of total material cost

Review timeline

Plan review
Not published — contact the department

How long did your Plumbing Permit permit actually take in La Salle?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment, per local frost/sewer-depth amendments

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

See the full La Salle inspection guide — scheduling & re-inspection fees →

Tips

  • La Salle has a dedicated 2019 'SOP Plmg Contempo Review' document specifically for plumbing, in addition to the general electrical+plumbing contemporaneous-review guide — plumbing licensure enforcement has been a specific point of local emphasis since at least 2019.
  • Exterior water supply piping in La Salle must be buried deeper than the bare IPC default (6 inches below frost line, 48 inches below finish grade minimum) — confirm your plumber is pricing to this local amendment, not a generic assumption.

Frequently asked questions

La Salle requires a plumbing permit for: Governed by the 2018 IPC as currently enforced by the Town; Exterior water supply piping required not less than 6 inches below the frost line and not less than 48 inches below finish grade (local Chapter 18 amendment); Plumbers must register with the Town/ProCode before applying for a permit and provide current Colorado DORA State Plumbing Board license credentials, subject to contemporaneous verification; Two dedicated documents on the Town's Building Permits page address plumbing contemporaneous review specifically (2019 SOP and a general contemporaneous-reviews procedure). If your project isn't listed, confirm with Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) at 970-305-3161 before starting work.

La Salle does not publish a plan-review timeline for this permit. Contact Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) at 970-305-3161 for current turnaround.

You'll need: Plumbing Permit Application. See the required-documents checklist on this page for details on each.

La Salle requires 2 inspection(s) for a plumbing permit, in order: Rough Plumbing, Final Inspection. Schedule each through Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) (970-305-3161).

Apply through Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) at 128 N 2nd Street, La Salle, CO 80645. Phone: 970-305-3161. Office hours: Town of La Salle main line 970-284-6931. Building Inspections direct line 970-305-3161 (inspection requests ext. 1, general ext. 0). Building Official: Jonathan Gesick. Building permit review and inspections are contracted to ProCode Inc., a SAFEbuilt company (regional office: 39 S. Parish Avenue, Suite 220, Johnstown, CO 80534; COemail@safebuilt.com). General town office hours are not published on the Building Permits, Directory, or Municipal Code pages as of this review; not stated rather than assumed.. Official information: https://www.lasalletown.com/2169/Building-Permits.

La Salle, Colorado has adopted: 2018 International Building Code (IBC) — per the Town of La Salle Building Permits page: 'The Town of LaSalle has adopted and is currently enforcing the 2018 International Codes, 2012 Energy Conservation Code, and 2020 National Electrical Code.'; 2018 International Residential Code (IRC); 2018 International Mechanical Code (IMC); 2018 International Plumbing Code (IPC); 2018 International Fuel Gas Code (IFGC) (bundled under the page's 'International Codes' reference; not itemized by individual code title on the live page); 2012 International Energy Conservation Code (IECC) — the live page names this specifically as '2012 Energy Conservation Code,' an older cycle than the 2018 base I-Codes it is paired with; 2020 National Electrical Code (NEC); 2025 Colorado Wildfire Resiliency Code (Colorado Division of Fire Prevention and Control model code, dfpc.colorado.gov/WRCB) — listed as adopted on the Town's Building Permits page; Model Colorado Electric and Solar Ready Code (Colorado Energy Office, energyoffice.colorado.gov/building-energy-codes-toolkit) — listed as adopted on the Town's Building Permits page; Note on document currency and code-cycle discrepancy: the Town's Municode-codified Chapter 18 (Building Regulations), as of this review, still recites the 2003 IBC/IRC/IPC/IMC/IFGC, 1999 NEC, and 1997 Uniform Code for Abatement of Dangerous Buildings, with a 1977/1978-vintage Colorado energy standard — none of which match the 2018 I-Codes / 2012 IECC / 2020 NEC the Town's actively-maintained Building Permits webpage states it is 'currently enforcing.' Consistent with this corpus's established pattern (e.g. Vail), the live, actively-maintained Building Permits page is treated as the current governing statement of adopted codes, since Municode codification frequently lags the underlying adopting ordinances and La Salle's own current-enforcement statement is unambiguous and specific (exact code years named). The codified Chapter 18 text is retained here only as a source of durable local AMENDMENT language (definitions, frost depth, sleeping-room rules, refund provisions, fee-authorization mechanism) that is very likely still in force, since local amendments of this kind are typically carried forward from cycle to cycle rather than dropped, but the umbrella code EDITIONS themselves follow the live page.; Note on HB22-1362 (statewide energy floor, window July 2023-July 2026): the Town's stated 2012 IECC base energy code edition does NOT itself meet HB22-1362's requirement that jurisdictions updating their code during this window adopt at least the 2021 IECC. However, the Town's Building Permits page separately lists the 'Model Colorado Electric and Solar Ready Code' as adopted alongside the 2025 Colorado Wildfire Resiliency Code — meaning La Salle appears to have layered on the HB22-1362 electric/solar-ready provisions as a standalone addition without upgrading its underlying energy-code base edition to 2021 IECC. This is reported honestly as observed; this file does not assume full HB22-1362 compliance, only that the electric/solar-ready model code specifically has been adopted per the Town's own published list.; MAJOR RE-CHASE UPDATE, 2026-07-23 — Municode reversal: this file's prior methodology (see the two notes above) treated the Town's Municode-hosted codification as a stale 2003-era snapshot and deferred to the live Building Permits webpage for current code editions. A direct re-chase of library.municode.com/co/lasalle on 2026-07-23 found this assumption is NO LONGER CORRECT: La Salle's Municode codification is now current through Ordinance No. 5-2026 (enacted 3-24-2026), online content updated 7-1-2026, and Chapter 18 was comprehensively overhauled by Ordinance No. 19-2025 (adopted 12-9-2025) — confirmed by reading each article's adoption section directly: Sec. 18-18 now adopts the 2024 IBC (not 2018), Sec. 18-43 the 2023 NEC (not 2020), Sec. 18-68 the 2024 IPC (not 2018), Sec. 18-93 the 2024 IMC (not 2018), Sec. 18-143 the 2024 IRC (not 2018), and Sec. 18-166 the 2024 IECC (not 2012 — which would also resolve the HB22-1362 gap flagged in the note above, since 2024 IECC exceeds the 2021 IECC statewide floor). Chapter 18 was also restructured into 16 articles, adding new Article IX (2024 International Fire Code), Article XI (International Property Maintenance Code), Article XII (International Existing Building Code), Article XIII (International Swimming Pool and Spa Code), and Article XVI (Graywater Systems) — none of which are reflected in the Town's own Building Permits webpage, which as of this same re-chase (2026-07-23) still states only '2018 International Codes, 2012 Energy Conservation Code, and 2020 National Electrical Code.' The two Town-controlled channels now directly conflict, and the codified ordinance (more recently dated, and the Town's actual governing law) appears to be the accurate one, while the informational webpage appears to be the stale one — the reverse of this file's original assumption. Local-amendment LANGUAGE spot-checked against the new codification (120 sq ft accessory-structure exemption, 180-day permit expiration/half-fee renewal, 80% refund provisions, sleeping-room definition) was found carried forward unchanged into the 2024-edition articles, so those specific amendment provisions remain reliable. However, a full re-verification of every permitType's code-edition citations, and of the five newly-added articles, was OUT OF SCOPE for this partial-chase pass (which targeted only fee/timeline gaps) and should be treated as a distinct, dedicated follow-up chase rather than assumed complete. Sources: https://library.municode.com/co/lasalle (Chapter 18, Article II Sec. 18-18; Article III Sec. 18-43; Article IV Sec. 18-68; Article V Sec. 18-93; Article VII Sec. 18-143; Article VIII Sec. 18-166 — all citing Ord. No. 19-2025, 12-9-2025).. Local amendments apply — see the La Salle overview page for the full list.

The Town of La Salle issues plumbing permits locally via its contracted agency ProCode Inc. The Colorado State Plumbing Board licenses the plumbers themselves; the Town verifies that DORA license status contemporaneously at registration and, at inspectors' discretion, in the field.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the La Salle building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.