EV Charger / EVSE Permit — La Salle, Colorado · Requirements sheet
Reviewed 2026-07-20 · Source: https://www.lasalletown.com/2169/Building-Permits
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in La Salle, Colorado
Electric vehicle charging equipment (EVSE) installation in La Salle is processed as ordinary electrical work, issued locally by the Town (via its contracted plan-review/inspection agency, ProCode Inc., a SAFEbuilt company) under the 2020 NEC as adopted — the same mechanism documented on this file's general Electrical Permit entry. The Town's Building Permits page does not itemize EV chargers, EVSE, or charging stations as their own named project type, and no current numeric building-permit fee schedule (valuation-tier table) of any kind is published anywhere on the Town's website; the page states only the calculation method (valuation-based, including labor/materials/profit) plus a flat 2% construction use tax on material cost.
Reviewed 2026-07-20 · Source
When you need this permit
- Electrical permit required for EVSE/EV charger circuit installation, alteration, or repair, governed by the 2020 NEC as currently enforced by the Town
- Electricians must register with the Town/ProCode before applying for a permit and must provide current Colorado DORA State Electrical Board license credentials at registration
- Town/ProCode staff verify DORA license status contemporaneously using DORA's licensing service
- As a town of roughly 3,500 residents, La Salle falls below the population threshold (10,000) that makes a Colorado municipality a 'covered municipality' under HB24-1173 (Electric Vehicle Charging System Permits Act), so it was not required to take a Dec. 31, 2025 compliance action under that law
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Wiring and panel installed before concealment; contemporaneous DORA license review may occur
- 2
Final Inspection
EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified; system energized
See the full La Salle inspection guide — scheduling & re-inspection fees →
Tips
- La Salle's Building Permits page does not name 'EV charger' or 'EVSE' as its own itemized project type — like solar, EVSE installation is inferred to fall under the Town's general Electrical Permit process. Confirm directly with ProCode whether a distinct workflow or fee category applies.
- La Salle is below the 10,000-population threshold that triggers HB24-1173's Dec. 31, 2025 EV-charger-permitting compliance requirement for Colorado municipalities, so no state-mandated expedited review process applies here the way it might in a larger covered municipality.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the La Salle building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in La Salle
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your La Salle project checklist
Describe your project once and get every permit, document, and fee it triggers in La Salle — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →