EV Charger / EVSE Permit in La Salle, Colorado

Electric vehicle charging equipment (EVSE) installation in La Salle is processed as ordinary electrical work, issued locally by the Town (via its contracted plan-review/inspection agency, ProCode Inc., a SAFEbuilt company) under the 2020 NEC as adopted — the same mechanism documented on this file's general Electrical Permit entry. The Town's Building Permits page does not itemize EV chargers, EVSE, or charging stations as their own named project type, and no current numeric building-permit fee schedule (valuation-tier table) of any kind is published anywhere on the Town's website; the page states only the calculation method (valuation-based, including labor/materials/profit) plus a flat 2% construction use tax on material cost.

Reviewed 2026-07-20 · Source

When you need this permit

  • Electrical permit required for EVSE/EV charger circuit installation, alteration, or repair, governed by the 2020 NEC as currently enforced by the Town
  • Electricians must register with the Town/ProCode before applying for a permit and must provide current Colorado DORA State Electrical Board license credentials at registration
  • Town/ProCode staff verify DORA license status contemporaneously using DORA's licensing service
  • As a town of roughly 3,500 residents, La Salle falls below the population threshold (10,000) that makes a Colorado municipality a 'covered municipality' under HB24-1173 (Electric Vehicle Charging System Permits Act), so it was not required to take a Dec. 31, 2025 compliance action under that law

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit Fee (EVSE circuit)Valuation-based (installation labor + materials + profit); no current published fee table exists for any permit type on the Town's site — contact ProCode or Town Hall for a project-specific quote. Re-chased 2026-07-20: the Town's live Building Permits page does not name 'EV charger,' 'EVSE,' or 'charging station' as its own itemized project type, so this is modeled as ordinary electrical work rather than a distinct fee category. Also checked whether a Colorado State Electrical Board fee schedule could be cited as a fallback (Colorado law caps local electrical fees at 1.15x the state's own annually-set schedule) -- the Board's current Rules and Regulations (3 CCR 710-1, Colorado Secretary of State) govern licensing and NEC adoption but do not themselves publish the dollar fee table, and DORA's own fee-schedule web pages return HTTP 403 to automated fetches, so no current, citable state figure could be located either. Re-chased 2026-07-23: Municode's current codification (Sec. 18-48, current through Ordinance No. 19-2025, 12/9/2025) reconfirms electrical permit fees are set 'from time to time by resolution of the board of trustees and set forth in the town fee schedule' rather than being codified — matching every other trade in this file. No numeric figure exists on any live channel checked.
Not published — contact the department
Construction Use Tax
2% of total material cost

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in La Salle?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment; contemporaneous DORA license review may occur

  2. 2

    Final Inspection

    EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified; system energized

See the full La Salle inspection guide — scheduling & re-inspection fees →

Tips

  • La Salle's Building Permits page does not name 'EV charger' or 'EVSE' as its own itemized project type — like solar, EVSE installation is inferred to fall under the Town's general Electrical Permit process. Confirm directly with ProCode whether a distinct workflow or fee category applies.
  • La Salle is below the 10,000-population threshold that triggers HB24-1173's Dec. 31, 2025 EV-charger-permitting compliance requirement for Colorado municipalities, so no state-mandated expedited review process applies here the way it might in a larger covered municipality.

Frequently asked questions

La Salle requires an ev charger / evse permit for: Electrical permit required for EVSE/EV charger circuit installation, alteration, or repair, governed by the 2020 NEC as currently enforced by the Town; Electricians must register with the Town/ProCode before applying for a permit and must provide current Colorado DORA State Electrical Board license credentials at registration; Town/ProCode staff verify DORA license status contemporaneously using DORA's licensing service; As a town of roughly 3,500 residents, La Salle falls below the population threshold (10,000) that makes a Colorado municipality a 'covered municipality' under HB24-1173 (Electric Vehicle Charging System Permits Act), so it was not required to take a Dec. 31, 2025 compliance action under that law. If your project isn't listed, confirm with Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) at 970-305-3161 before starting work.

La Salle does not publish a plan-review timeline for this permit. Contact Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) at 970-305-3161 for current turnaround.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

La Salle requires 2 inspection(s) for an ev charger / evse permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) (970-305-3161).

Apply through Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) at 128 N 2nd Street, La Salle, CO 80645. Phone: 970-305-3161. Office hours: Town of La Salle main line 970-284-6931. Building Inspections direct line 970-305-3161 (inspection requests ext. 1, general ext. 0). Building Official: Jonathan Gesick. Building permit review and inspections are contracted to ProCode Inc., a SAFEbuilt company (regional office: 39 S. Parish Avenue, Suite 220, Johnstown, CO 80534; COemail@safebuilt.com). General town office hours are not published on the Building Permits, Directory, or Municipal Code pages as of this review; not stated rather than assumed.. Official information: https://www.lasalletown.com/2169/Building-Permits.

La Salle, Colorado has adopted: 2018 International Building Code (IBC) — per the Town of La Salle Building Permits page: 'The Town of LaSalle has adopted and is currently enforcing the 2018 International Codes, 2012 Energy Conservation Code, and 2020 National Electrical Code.'; 2018 International Residential Code (IRC); 2018 International Mechanical Code (IMC); 2018 International Plumbing Code (IPC); 2018 International Fuel Gas Code (IFGC) (bundled under the page's 'International Codes' reference; not itemized by individual code title on the live page); 2012 International Energy Conservation Code (IECC) — the live page names this specifically as '2012 Energy Conservation Code,' an older cycle than the 2018 base I-Codes it is paired with; 2020 National Electrical Code (NEC); 2025 Colorado Wildfire Resiliency Code (Colorado Division of Fire Prevention and Control model code, dfpc.colorado.gov/WRCB) — listed as adopted on the Town's Building Permits page; Model Colorado Electric and Solar Ready Code (Colorado Energy Office, energyoffice.colorado.gov/building-energy-codes-toolkit) — listed as adopted on the Town's Building Permits page; Note on document currency and code-cycle discrepancy: the Town's Municode-codified Chapter 18 (Building Regulations), as of this review, still recites the 2003 IBC/IRC/IPC/IMC/IFGC, 1999 NEC, and 1997 Uniform Code for Abatement of Dangerous Buildings, with a 1977/1978-vintage Colorado energy standard — none of which match the 2018 I-Codes / 2012 IECC / 2020 NEC the Town's actively-maintained Building Permits webpage states it is 'currently enforcing.' Consistent with this corpus's established pattern (e.g. Vail), the live, actively-maintained Building Permits page is treated as the current governing statement of adopted codes, since Municode codification frequently lags the underlying adopting ordinances and La Salle's own current-enforcement statement is unambiguous and specific (exact code years named). The codified Chapter 18 text is retained here only as a source of durable local AMENDMENT language (definitions, frost depth, sleeping-room rules, refund provisions, fee-authorization mechanism) that is very likely still in force, since local amendments of this kind are typically carried forward from cycle to cycle rather than dropped, but the umbrella code EDITIONS themselves follow the live page.; Note on HB22-1362 (statewide energy floor, window July 2023-July 2026): the Town's stated 2012 IECC base energy code edition does NOT itself meet HB22-1362's requirement that jurisdictions updating their code during this window adopt at least the 2021 IECC. However, the Town's Building Permits page separately lists the 'Model Colorado Electric and Solar Ready Code' as adopted alongside the 2025 Colorado Wildfire Resiliency Code — meaning La Salle appears to have layered on the HB22-1362 electric/solar-ready provisions as a standalone addition without upgrading its underlying energy-code base edition to 2021 IECC. This is reported honestly as observed; this file does not assume full HB22-1362 compliance, only that the electric/solar-ready model code specifically has been adopted per the Town's own published list.; MAJOR RE-CHASE UPDATE, 2026-07-23 — Municode reversal: this file's prior methodology (see the two notes above) treated the Town's Municode-hosted codification as a stale 2003-era snapshot and deferred to the live Building Permits webpage for current code editions. A direct re-chase of library.municode.com/co/lasalle on 2026-07-23 found this assumption is NO LONGER CORRECT: La Salle's Municode codification is now current through Ordinance No. 5-2026 (enacted 3-24-2026), online content updated 7-1-2026, and Chapter 18 was comprehensively overhauled by Ordinance No. 19-2025 (adopted 12-9-2025) — confirmed by reading each article's adoption section directly: Sec. 18-18 now adopts the 2024 IBC (not 2018), Sec. 18-43 the 2023 NEC (not 2020), Sec. 18-68 the 2024 IPC (not 2018), Sec. 18-93 the 2024 IMC (not 2018), Sec. 18-143 the 2024 IRC (not 2018), and Sec. 18-166 the 2024 IECC (not 2012 — which would also resolve the HB22-1362 gap flagged in the note above, since 2024 IECC exceeds the 2021 IECC statewide floor). Chapter 18 was also restructured into 16 articles, adding new Article IX (2024 International Fire Code), Article XI (International Property Maintenance Code), Article XII (International Existing Building Code), Article XIII (International Swimming Pool and Spa Code), and Article XVI (Graywater Systems) — none of which are reflected in the Town's own Building Permits webpage, which as of this same re-chase (2026-07-23) still states only '2018 International Codes, 2012 Energy Conservation Code, and 2020 National Electrical Code.' The two Town-controlled channels now directly conflict, and the codified ordinance (more recently dated, and the Town's actual governing law) appears to be the accurate one, while the informational webpage appears to be the stale one — the reverse of this file's original assumption. Local-amendment LANGUAGE spot-checked against the new codification (120 sq ft accessory-structure exemption, 180-day permit expiration/half-fee renewal, 80% refund provisions, sleeping-room definition) was found carried forward unchanged into the 2024-edition articles, so those specific amendment provisions remain reliable. However, a full re-verification of every permitType's code-edition citations, and of the five newly-added articles, was OUT OF SCOPE for this partial-chase pass (which targeted only fee/timeline gaps) and should be treated as a distinct, dedicated follow-up chase rather than assumed complete. Sources: https://library.municode.com/co/lasalle (Chapter 18, Article II Sec. 18-18; Article III Sec. 18-43; Article IV Sec. 18-68; Article V Sec. 18-93; Article VII Sec. 18-143; Article VIII Sec. 18-166 — all citing Ord. No. 19-2025, 12-9-2025).. Local amendments apply — see the La Salle overview page for the full list.

The Town's Building Permits page does not itemize a separate named EV charger/EVSE permit category; installations are understood to fall under the Town's general Electrical Permit process, issued locally via ProCode Inc. under the 2020 NEC. La Salle is also below the population threshold that would make it a 'covered municipality' under Colorado's HB24-1173 EV Charging System Permits Act.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the La Salle building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.