Residential Building Permit (New Construction) in La Salle, Colorado

Required for new single-family/duplex construction in the Town of La Salle. Reviewed under the 2018 IRC/IBC as currently enforced by the Town, plus the 2012 IECC energy provisions and local Chapter 18 amendments (engineered foundation/soils report requirement, stud/joist spacing, egress and sleeping-room definitions). Plan review and inspections are performed by ProCode Inc. (SAFEbuilt) under contract to the Town.

Reviewed 2026-07-06 · Source

When you need this permit

  • Plans must comply with the 2018 IRC/IBC as currently enforced by the Town, the 2012 IECC, and the 2020 NEC
  • Foundation design and construction drawings must be stamped by a Colorado-registered professional engineer or licensed architect, based on an engineer's soils report (per codified Chapter 18 IRC local amendment)
  • A site certification prepared by a State-licensed professional engineer or land surveyor is required for new Group R Division 3 (single-family/duplex) occupancies prior to certificate of occupancy Contractor
  • Floor joists spaced a maximum of 19.2 inches on center, or engineered to an L/480 deflection limit; exterior and load-bearing wall studs spaced no more than 16 inches on center
  • Electrical and plumbing contractors must hold current Colorado DORA (State Electrical Board / State Plumbing Board) licenses, registered with the Town/ProCode and subject to contemporaneous license verification per the Colorado Chapter ICC 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (HB19-1086, SB19-156)
  • Application submitted through the Town's Community Core online permitting system; a hard copy of reviewed/stamped plans must be kept on the job site — this remains the applicant's responsibility even after electronic approval

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeValuation-based (labor + materials + profit, including electrical/plumbing scope); no current numeric valuation-tier fee table is published by the Town or ProCode as of this review — contact ProCode (970-305-3161) or Town Hall (970-284-6931) for a project-specific quote. Codified Chapter 18 (current codification renumbers this Sec. 18-24, 'Fees') references 'the current fee schedule contained in the 2003 International Building Code' as amendable by Town Board resolution, but no such current resolution is published online. Re-chased 2026-07-23: confirmed live via Municode's CURRENT codification (library.municode.com/co/lasalle, codified through Ordinance No. 19-2025, adopted 12/9/2025 — verified this is not a stale snapshot) that Sec. 18-24 is unchanged and still delegates to the 2003 IBC schedule/board-resolution mechanism; also checked ProCode's LaSalle community resource page (safebuilt.com/about/our-companies/procode/la-salle, dateModified 2026-03-09) directly for a fee handout among its ~18 published documents — none exists. Gap is durable, not a stale-codification artifact.
Not published — contact the department
Construction Use TaxPer the Town's Building Permits page: 'The Town also has a 2% use tax on the total cost of the material.'
2% of total material cost
Credit Card Processing FeeCredit card transactions are not accepted above $350.00 total
$3.00 per phone transaction

Review timeline

Plan review
Not published — contact the department

How long did your Residential Building Permit (New Construction) permit actually take in La Salle?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete pour, per engineered foundation design and soils report

  2. 2

    Framing

    Structural framing complete, joist/stud spacing per local amendments, before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment; contemporaneous DORA license review may occur at this stage

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes; site certification required before certificate of occupancy

See the full La Salle inspection guide — scheduling & re-inspection fees →

Tips

  • Because plan review and inspections are contracted to ProCode Inc. (a SAFEbuilt company), route detailed technical questions to ProCode (970-305-3161) rather than only the Town's general line — ProCode staff hold the current fee and scheduling specifics.
  • Request inspections before 4 PM to be scheduled for the following business day; the Town's inspection scheduling has migrated to the Community Connect platform as of March 1, 2026.
  • Confirm your foundation engineer provides both a soils report and a stamped foundation design — this is a hard local requirement layered onto the base 2018 IRC/IBC, not merely a best practice.

Frequently asked questions

La Salle requires a residential building permit (new construction) for: Plans must comply with the 2018 IRC/IBC as currently enforced by the Town, the 2012 IECC, and the 2020 NEC; Foundation design and construction drawings must be stamped by a Colorado-registered professional engineer or licensed architect, based on an engineer's soils report (per codified Chapter 18 IRC local amendment); A site certification prepared by a State-licensed professional engineer or land surveyor is required for new Group R Division 3 (single-family/duplex) occupancies prior to certificate of occupancy; Floor joists spaced a maximum of 19.2 inches on center, or engineered to an L/480 deflection limit; exterior and load-bearing wall studs spaced no more than 16 inches on center; Electrical and plumbing contractors must hold current Colorado DORA (State Electrical Board / State Plumbing Board) licenses, registered with the Town/ProCode and subject to contemporaneous license verification per the Colorado Chapter ICC 'Procedure for Contemporaneous Reviews of Electrical and Plumbing Licenses' (HB19-1086, SB19-156); Application submitted through the Town's Community Core online permitting system; a hard copy of reviewed/stamped plans must be kept on the job site — this remains the applicant's responsibility even after electronic approval. If your project isn't listed, confirm with Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) at 970-305-3161 before starting work.

La Salle does not publish a plan-review timeline for this permit. Contact Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) at 970-305-3161 for current turnaround.

You'll need: Building Permit Application; Stamped Structural/Foundation Plans; Site Certification. See the required-documents checklist on this page for details on each.

La Salle requires 4 inspection(s) for a residential building permit (new construction), in order: Foundation, Framing, Rough Electrical / Plumbing / Mechanical, Final Inspection. Schedule each through Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) (970-305-3161).

Apply through Town of La Salle Building Inspections (contracted to ProCode Inc. / SAFEbuilt) at 128 N 2nd Street, La Salle, CO 80645. Phone: 970-305-3161. Office hours: Town of La Salle main line 970-284-6931. Building Inspections direct line 970-305-3161 (inspection requests ext. 1, general ext. 0). Building Official: Jonathan Gesick. Building permit review and inspections are contracted to ProCode Inc., a SAFEbuilt company (regional office: 39 S. Parish Avenue, Suite 220, Johnstown, CO 80534; COemail@safebuilt.com). General town office hours are not published on the Building Permits, Directory, or Municipal Code pages as of this review; not stated rather than assumed.. Official information: https://www.lasalletown.com/2169/Building-Permits.

Per the Town's Building Permits page, La Salle has adopted and is currently enforcing the 2018 International Codes, the 2012 Energy Conservation Code, and the 2020 National Electrical Code, along with the 2025 Colorado Wildfire Resiliency Code and the Model Colorado Electric and Solar Ready Code.

The Town of La Salle issues its own building permits for all work within town limits, but contracts plan review and inspection services to ProCode Inc., a SAFEbuilt company. Applications are submitted through the Town's Community Core online portal.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the La Salle building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.