Fire Sprinkler / Fire Alarm System Permit — Severance, Colorado · Requirements sheet
Verified 2026-08-14 · Source: https://www.wsfr.us/plan-review-application-and-fee-schedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Fire Sprinkler / Fire Alarm System Permit in Severance, Colorado
Windsor Severance Fire Rescue (WSFR), a Colorado special-district fire protection district serving a roughly 100-110 square mile area including the Towns of Windsor and Severance (headquarters: 100 N. 7th Street, Windsor, CO 80550, 970-686-2626), issues fire alarm and fire sprinkler permits through its Community Risk Reduction Division — entirely separate from the Town of Severance's own SAFEbuilt-administered general building permit process documented elsewhere in this file. Plan review applies the 2024 IFC WSFR Amendments (in effect August 1, 2025). Fees are valuation-tiered per WSFR's own Consolidated Schedule of Rates, Charges, and Fees, and WSFR publishes a specific plan-review turnaround: up to 10 business days from the time of payment.
Verified 2026-08-14 · Source
When you need this permit
- Fire Alarm Permit submittals must include: a valid contractor's license or equivalent certification; a completed permit application with correct address and valuation; three sets of plans at minimum 1/8" scale (a maximum of three sets will be stamped; digital plans also accepted); a PE or NICET Level III stamp on all plans; a minimum of one set of material cut sheets; voltage drop calculations; battery calculations; a symbol list; and a riser diagram Contractor
- Fire Sprinkler Permit submittals must include: a valid contractor's license or equivalent certification; a completed permit application with correct address and valuation; three sets of plans at minimum 1/8" scale (digital accepted); a PE or NICET Level III stamp on all plans; a minimum of one set of material cut sheets; hydraulic calculations; and water supply information including a flow test less than 1 year old Contractor
- Plans will not be reviewed until fees are received; plan reviews may then take up to 10 business days to complete
- Work completed without a permit is billed at double the original plan review and permit fee, per WSFR's own Plan Review & Fee Schedule page (the fee table separately caps the Delinquent Permit Fee — for work WSFR independently discovers is unpermitted — at double the original permit fee up to $1,000)
- Permits are valid for one year from issuance unless otherwise noted; an expired permit requires reapplication and an Expired Permit Fee of 65% of the original permit fee
- WSFR performs rough and final inspections of fire-protection systems for structures in Windsor, Severance, Larimer County, and Weld County; the final fire-protection-system inspection must be scheduled for the same time as the general building-permit final inspection, with all applicable contractors present, in order for the owner/occupant to obtain a Certificate of Occupancy or Letter of Completion
- Applicants should reference the 2024 IFC WSFR Amendments (in effect August 1, 2025) along with other applicable codes and standards when submitting plans
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough Inspection (Fire Protection System)
Performed by WSFR for the fire alarm or fire sprinkler installation
- 2
Final Inspection (Fire Protection System)
Must be scheduled for the same time as the general building-permit final inspection with all applicable contractors present; required (along with the general building final) before a Certificate of Occupancy or Letter of Completion is issued
See the full Severance inspection guide — scheduling & re-inspection fees →
Tips
- WSFR's fire-protection-system permits and fees are entirely separate from the Town of Severance's own SAFEbuilt-administered building permit process documented elsewhere in this file — budget for and submit to both.
- The 10-business-day plan review clock doesn't start until WSFR receives payment, not at submittal — pay promptly to avoid an invisible delay before review even begins.
- Coordinate scheduling early: the final fire-protection-system inspection must happen at the same time as the general building-permit final inspection, with all applicable contractors present, per WSFR's own Fire Inspections policy.
- Working without a permit is expensive twice over — WSFR bills double the original plan review and permit fee once it independently discovers unpermitted work, in addition to issuing a stop-work order.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-14.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Severance building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Severance
Fire Sprinkler / Fire Alarm System Permit in other cities
Compare fire sprinkler / fire alarm system permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Severance project checklist
Describe your project once and get every permit, document, and fee it triggers in Severance — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →