Re-Roof Permit in Severance, Colorado
Required for re-roofing work in Severance (one permit per building on the property). Governed by the 2024 IRC as adopted; the Town publishes a dedicated 2024-IRC Residential Re-Roofing guide (SAFEbuilt, published 1.1.2026).
Verified 2026-07-06 · Source
When you need this permit
- One permit is required per building on the property for re-roofing
- No more than two (2) layers of roofing are allowed upon completion of installation
- Roof sheathing must provide a rigid surface for complete tear-offs; warped/cracked/delaminated boards must be repaired or replaced
- New minimum 15# asphalt-saturated felt underlayment required on a dry deck for complete tear-offs, with lap requirements varying by roof slope (one layer for 4:12+ slopes; 19-inch laps for 2:12-4:12 slopes)
- Fasteners must penetrate through the total roofing thickness and a minimum of 3/4 inch into the decking material
- Existing roof jacks/vents in poor condition, badly rusted, or deteriorated must be replaced
- Homeowners may perform their own re-roof work Owner-builder
- Shingle repair/replacement not exceeding 100 sq ft of coverage per building is exempt from permitting
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Town of Severance 2026 Fee Schedule (rev. Show full citationHide
Town of Severance 2026 Fee Schedule (rev. 12/9/2025), Building Permit Fees table — Use Tax at a 3% tax assessment on 60% of the total valuation of improvement as determined by SafeBuilt. The schedule prints § 4-2-40 against this row, but that section is the Conservation Trust Fund; the use tax itself is imposed by Sec. 4-3-90.Review timeline
Inspection process
- 1
Mid-Roof Inspection
May be required; consult the Building Department upon permit issuance
- 2
Final Roof Inspection
Permit holder must call for this inspection
See the full Severance inspection guide — scheduling & re-inspection fees →
Tips
- Only two layers of roofing are allowed total — full tear-off is required if the roof already has two layers.
- Shingle repair/replacement under 100 sq ft per building does not require a permit, but any larger repair or a full re-roof does.
- If your property is in an HOA, the Town's own guide recommends contacting your HOA before changing roof covering materials, separate from the Town permit process.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Severance building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Severance's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Severance yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Severance lands. Privacy.
Other permits in Severance
Re-Roof Permit in other cities
Compare re-roof permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Severance project checklist
Describe your project once and get every permit, document, and fee it triggers in Severance — in one checklist. Free, for any city and any number of projects.
Get started →