Change of Use / Change of Occupancy Permit in Windsor, Colorado
Required whenever a building's use changes in Windsor. The Town's own guidance states that a change of use is treated as new construction — the building must be upgraded to current code requirements for the proposed use, and a new Certificate of Occupancy must be obtained. Governed by the Town's adopted 2024 International Existing Building Code (WMC Sec. 18-9-10).
Verified 2026-08-14 · Source
When you need this permit
- Town of Windsor guidance (Accessory Dwelling Unit Application Packet, Site Plan Submittal Requirements): 'When there is a change of use for a building, it is treated as a new building and must be upgraded to current code requirements for the proposed use, and a Certificate of Occupancy must be obtained'
- WMC Sec. 18-9-10 adopts the 2024 International Existing Building Code, Chapters 1 through 16 inclusive, by reference as the Town's governing code for existing buildings, which the change of use must comply with
- Because a change of use is treated as new construction, the proposed use must meet current 2024 I-Code requirements (effective January 1, 2026) rather than the code in force when the building was originally permitted
- SAFEbuilt (under contract to the Town) administers plan review and inspection for any construction/upgrade work associated with the change of use; the Town of Windsor remains the permit-issuing authority
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Building Division Inspection
Required for any construction/upgrade work performed to bring the space into compliance with current code for the proposed new use
See the full Windsor inspection guide — scheduling & re-inspection fees →
Tips
- Budget for a full code-compliance review, not a light-touch review — Windsor's own guidance treats a change of use as equivalent to new construction, meaning the space must meet CURRENT 2024 I-Code requirements regardless of when it was originally built.
- Contact the Town's Permit Technician (Robin Volner, rvolner@windsorgov.com, 970-674-2436) early for a project-specific fee estimate, since no flat or published change-of-use fee exists separate from the standard valuation-based building permit process.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-14.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Windsor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Windsor
Change of Use / Change of Occupancy Permit in other cities
Compare change of use / change of occupancy permit fees across Colorado →