Required for installation of rooftop residential or commercial solar photovoltaic systems within the Town of Windsor. Building permit review and inspection is contracted to SAFEbuilt, the same third party that administers all other Windsor building permits; the electrical portion is governed by the 2023 NEC. No dedicated solar/PV fee line item is published in the Town's Fee Schedule — solar is billed under the same SAFEbuilt valuation-based Building Permit Fee plus the Town's 25% Administration Fee, subject to Colorado's statewide solar permit fee cap.
Verified 2026-07-20 · Source
When you need this permit
- Building permit required for the structural/roof-mounting portion, reviewed and inspected by SAFEbuilt under contract to the Town of Windsor
- Electrical permit required for PV wiring/interconnection, governed by the 2023 NEC (effective for applications submitted on or after January 1, 2024); no separate Town of Windsor contractor license required, but the electrician must hold a current Colorado Electrical Board (DORA) license Contractor
- Under Colorado's statewide solar permit fee cap (C.R.S. § 24-48.5-113, enacted by HB21-1284), a covered local jurisdiction's total building-permit-related fees for a residential solar PV system may not exceed $500, and $1,000 for commercial systems, regardless of project valuation
- Windsor is subject to Colorado's automated-permitting mandate for cities over 5,000 population (HB25-1096); confirm with SAFEbuilt/the Permit Technician whether an automated online solar plan-review pathway (e.g. SolarAPP+) is currently offered
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical (SAFEbuilt)
Conduit runs, wire sizing, and disconnect placement before cover, per the 2023 NEC
- 2
Final (SAFEbuilt)
Racking, roof penetrations, and electrical connections verified
See the full Windsor inspection guide — scheduling & re-inspection fees →
Tips
- Windsor's building permit fee for solar is calculated by SAFEbuilt (the Town's contracted building-permit administrator) using the same valuation-based structure as any other building permit, plus the Town's 25% Administration Fee — no solar-specific discount or flat fee is published.
- Colorado's statewide solar permit fee cap (C.R.S. § 24-48.5-113) still limits what Windsor can charge in total building-permit fees for a residential solar PV system to $500 ($1,000 commercial), even though the Town's own Fee Schedule has no dedicated solar line item — confirm the cap is being applied if the SAFEbuilt valuation-based fee calculates higher.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Windsor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Windsor
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Windsor project checklist
Describe your project once and get every permit, document, and fee it triggers in Windsor — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →