Electrical Permit in Yuma, Colorado

Electrical permits and inspections within City of Yuma limits are administered by the Colorado State Electrical Board (Division of Professions and Occupations, DORA/DPO) rather than the City itself. Yuma County does not appear on the State's published list of counties with their own local Electrical Inspection Program, so State jurisdiction applies. Governed by the National Electrical Code (NEC) edition currently adopted by the State Electrical Board.

Verified 2026-07-06 · Source

When you need this permit

  • Confirmed NOT locally administered: Yuma County is absent from the Colorado DPO 'Electrical Local Inspection Areas' exception list (Adams, Arapahoe, Boulder, Broomfield, Chaffee, City of Pueblo/Town of Boone, Delta (City of Delta only), Denver, Douglas, Eagle, El Paso, Jefferson, Larimer, Mesa, Pitkin, Pueblo, Routt, San Miguel (Telluride/Mountain Village), Summit, Teller, Weld) — meaning the State, not the City, holds inspection jurisdiction
  • Yuma County's own official Land Use Contact List page directs applicants to the State's online electrical permit system (dpo.colorado.gov/Electrical) rather than a City or County office
  • Permit purchased through the State's Online Permitting System; a valid credit card, job site address, and (for electrical) square footage of living space to be wired, power supplier name, and materials/labor cost are required at application
  • Per State policy, the contractor/contractor representative or an adult homeowner (18+) or their representative must be present for inspection of occupied dwelling units
  • A homeowner may self-perform electrical work at their own residence and pull the permit themselves; a hired Electrical Contractor is responsible for obtaining the permit, and the homeowner should not submit the application themselves in that case Owner-builder

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

State Electrical Permit FeeFee amounts are determined by the State's own published Electrical Board fee schedule (dpo.colorado.gov/Electrical), not by the City of Yuma's Resolution #46 Fee Schedule, since the City does not administer this permit type
Set by the Colorado State Electrical Board fee schedule (not a City of Yuma fee)

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Yuma?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    State Electrical Inspection

    Scheduled directly with the assigned State Electrical Inspector (not the City of Yuma Building Inspector) after permit purchase

See the full Yuma inspection guide — scheduling & re-inspection fees →

Tips

  • Do not apply for an electrical permit through City of Yuma's Building Inspector — electrical work in Yuma is governed by the State Electrical Board, and the permit must be purchased through the State's own Online Permitting System (dpo.colorado.gov/Electrical), not the City's Building Permit Application.
  • If you are a homeowner hiring a licensed Electrical Contractor, the contractor is responsible for pulling the permit — as the homeowner, you should not submit the State's permit application yourself in that scenario, per the State's own Notice to Homeowner guidance.
  • The City of Yuma's Rooftop Solar FAQ independently confirms this state-administered pathway, describing the required electrical inspection for solar PV interconnection as being performed by the 'county building safety codes department' rather than a City inspector.

Frequently asked questions

Yuma requires an electrical permit for: Confirmed NOT locally administered: Yuma County is absent from the Colorado DPO 'Electrical Local Inspection Areas' exception list (Adams, Arapahoe, Boulder, Broomfield, Chaffee, City of Pueblo/Town of Boone, Delta (City of Delta only), Denver, Douglas, Eagle, El Paso, Jefferson, Larimer, Mesa, Pitkin, Pueblo, Routt, San Miguel (Telluride/Mountain Village), Summit, Teller, Weld) — meaning the State, not the City, holds inspection jurisdiction; Yuma County's own official Land Use Contact List page directs applicants to the State's online electrical permit system (dpo.colorado.gov/Electrical) rather than a City or County office; Permit purchased through the State's Online Permitting System; a valid credit card, job site address, and (for electrical) square footage of living space to be wired, power supplier name, and materials/labor cost are required at application; Per State policy, the contractor/contractor representative or an adult homeowner (18+) or their representative must be present for inspection of occupied dwelling units; A homeowner may self-perform electrical work at their own residence and pull the permit themselves; a hired Electrical Contractor is responsible for obtaining the permit, and the homeowner should not submit the application themselves in that case. If your project isn't listed, confirm with City of Yuma Building Inspection / Code Enforcement at 970-848-3878 (City Hall); 970-630-7118 (Building Inspector direct line) before starting work.

In Yuma, the published State Electrical Permit Fee is: Set by the Colorado State Electrical Board fee schedule (not a City of Yuma fee). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Yuma does not publish a plan-review timeline for this permit. Contact City of Yuma Building Inspection / Code Enforcement at 970-848-3878 (City Hall); 970-630-7118 (Building Inspector direct line) for current turnaround.

You'll need: State of Colorado Online Electrical Permit (via DORA/DPO Online Permitting System). See the required-documents checklist on this page for details on each.

Yuma requires 1 inspection(s) for an electrical permit, in order: State Electrical Inspection. Schedule each through City of Yuma Building Inspection / Code Enforcement (970-848-3878 (City Hall); 970-630-7118 (Building Inspector direct line)).

Apply through City of Yuma Building Inspection / Code Enforcement at 320 South Main Street, Yuma, CO 80759 (mailing: PO Box 265, Yuma, CO 80759). Phone: 970-848-3878 (City Hall); 970-630-7118 (Building Inspector direct line), email: building.inspector@yumacolo.org. Office hours: Monday to Friday, 8:00 a.m. to 5:00 p.m. (City Hall, 320 South Main Street). Official information: https://cityofyuma.colorado.gov/building-inspection.

No. Yuma County (which includes the City of Yuma) does not appear on the Colorado Division of Professions and Occupations' list of counties with a local Electrical Inspection Program, so electrical permits and inspections are handled by the State Electrical Board through its own Online Permitting System, not by the City's Building Inspector.

Whatever National Electrical Code edition the Colorado State Electrical Board currently has adopted applies, since the City of Yuma does not administer or amend its own electrical code — verify the current edition directly at dpo.colorado.gov/Electrical before starting work.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Yuma building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.