Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) — Hailey, Idaho · Requirements sheet
Verified 2026-08-26 · Source: https://haileycityhall.org/community-development/building-services/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) in Hailey, Idaho
Covers new commercial construction, commercial additions, and commercial remodels or tenant improvements in Hailey. There is no distinct 'Commercial Building Permit' or 'Tenant Improvement Permit' product: commercial work is filed on the same universal Application for Building Permit used for residential projects, checked COMMERCIAL under New Construction or Remodel, and priced off the same Table 1-A valuation schedule. What genuinely differs from residential on this same application: two or more paper plan sets instead of electronic-only submittal; IECC Section C407 commercial energy-efficiency compliance; a separate Design Review Application fee for Commercial or Mixed-Use projects; a nonresidential Development Impact Fee table; a higher Clean Energy Deposit basis; a $600 nonrefundable Temporary Certificate of Occupancy fee; and a 20-business-day (versus 10) statutory completeness-review window under Idaho Code 39-4117.
Verified 2026-08-26 · Source
When you need this permit
- New commercial construction, commercial additions, or commercial remodels/tenant improvements, filed on the same Application for Building Permit used for residential work, checked COMMERCIAL under New Construction or Remodel
- Reviewed under the 2018 International Building Code, adopted at Hailey Municipal Code 15.08.010(A) as amended by the Idaho Building Code Board, including new Appendix O
- Construction documents submitted in two or more paper sets (versus electronic-only for residential applications), prepared by an Idaho-licensed architect or structural engineer where required, per Hailey Municipal Code 15.08.020, Section 107.1
- Buildings under 20,000 square feet must demonstrate IECC Section C407 Total Building Performance compliance using a COMcheck energy analysis; buildings 20,000 square feet or more must use building-department-approved energy modeling software (eQuest, Trace, Carrier HAP, EnergyPlus, or equivalent), per Hailey Municipal Code 15.08.020(C)(2)(a)
- A separate Design Review Application fee applies to projects categorized as Commercial or Mixed-Use, billed apart from the Building Permit and Plan Check fees; the City's Design Review process is administered under Hailey Municipal Code Title 17, Chapter 17.06 — the fee schedule confirms this category and its fee, but the chapter's specific applicability triggers for exterior commercial work could not be confirmed in this session because the code library's Chapter 17.06 pages did not render readable text through a browser-header fetch
- Electrical and plumbing work is permitted and inspected directly by the State of Idaho Division of Occupational and Professional Licenses (DOPL), not the City of Hailey
- Fire Department plan review is performed by the City's own Hailey Fire & Rescue Department (which conducts its own plan reviews for new construction according to its department page), billed as part of the Plan Check Fee stack rather than as a separate permit; no evidence was found that Hailey contracts commercial fire plan review out to Wood River Fire & Rescue or any other district
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footings
Before concrete pour — verify forms, rebar, and anchor bolts meet the 24-inch minimum frost depth
- 2
Framing
After framing and rough-in trades are complete, before insulation or wall cover
- 3
Energy Compliance
COMcheck analysis or energy modeling software output verified against IECC Section C407 before drywall
- 4
Final
All work complete per approved plans, ready for occupancy; Fire Department final sign-off is coordinated through the City's own Hailey Fire & Rescue Department
See the full Hailey inspection guide — scheduling & re-inspection fees →
Tips
- Hailey has no distinct 'Commercial Building Permit' or 'Tenant Improvement Permit' — commercial new construction and commercial remodels/TI both go through the same Application for Building Permit used for residential work, checked COMMERCIAL, and priced off the same Table 1-A valuation schedule.
- Budget for the full fee stack: the base Table 1-A Building Permit Fee, plus 67% Plan Check Fee, plus 34% of that for Planning Review, plus (where applicable) 44% of Plan Check for Hailey Fire Dept. review, plus the nonresidential Development Impact Fee, plus the Clean Energy Deposit, plus a Design Review Application fee if the project is categorized Commercial or Mixed-Use.
- The Design Review Application fee for Commercial or Mixed-Use projects ($1,350 plus $64.00 per 1,000 gross square feet) is billed by the Planning Department separately from the Building Permit and Plan Check fees; confirm with Community Development whether a specific project triggers this review.
- Commercial construction documents require two or more paper plan sets; residential applications instead submit electronically — a difference specific to the class of work checked on the application.
- Fire plan review in Hailey is performed in-house by the City's own Hailey Fire & Rescue Department and billed through the Plan Check Fee stack, not a separate fire-district permit — this differs from some neighboring Blaine County jurisdictions that contract fire review out to a separate district.
- The Arts and Historic Preservation Commission review applies specifically to demolition of structures built wholly or in part before 1941 — no separate historic-preservation review requirement attaching to commercial exterior remodels or alterations short of demolition was found on the City's Building Services or Planning pages.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-26.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hailey building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Hailey.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Hailey
Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) in other cities
Look up this fee in a different city →
Now live
Build your Hailey project checklist
Describe your project once and get every permit, document, and fee it triggers in Hailey — in one checklist. Free, for any city and any number of projects.
Get started →