Solar Photovoltaic (PV) Permit — Hailey, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://haileycityhall.org/wp-content/uploads/2020/12/Ord-1119-building-energy-codes.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit in Hailey, Idaho
Required for installation of rooftop or ground-mount solar photovoltaic systems within Hailey city limits. The City's own permit is officially named the 'Alternative Energy Permit' (see the sibling alternative-energy-permit entry in this dataset for the full record) and covers the structural/mounting review; it uses a flat application-fee model rather than valuation-based fees, established by Hailey Ordinance No. 1119 specifically to base charges on actual staff time rather than system value. A separate State of Idaho DOPL electrical permit is required for the wiring/interconnection scope.
Verified 2026-07-20 · Source
When you need this permit
- Alternative Energy Permit application (the City's official name for its solar/renewable-energy permit) submitted to the City of Hailey Building Division for the structural/mounting scope
- Electrical connection work falls under the State of Idaho DOPL electrical permitting program, not the City -- on the DOPL Contractor Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy'
- Hailey deliberately moved this permit from valuation-based to flat-fee pricing via Ordinance No. 1119, reasoning that structural review effort does not scale with system cost
- Renewable energy installations require a plan check prior to final inspection on the state electrical side, per the DOPL Electrical Permit Worksheet
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State Electrical Inspection
Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection
- 2
City Final Inspection (Building)
Racking/roof-penetration attachment and structural compliance verified by the City's Building Division
See the full Hailey inspection guide — scheduling & re-inspection fees →
Tips
- In Hailey, the City's solar permit is officially called the 'Alternative Energy Permit' -- search for that term on the City's fee schedule and forms, not 'solar permit.'
- Hailey deliberately moved this permit to a flat fee (rather than a valuation-based fee) via Ordinance No. 1119, reasoning that review effort does not scale with system cost -- this makes Hailey's structural/mounting fee more predictable than most neighboring Idaho jurisdictions.
- A separate electrical permit through the State of Idaho DOPL is required for the wiring/interconnection portion of any solar installation -- the City's Alternative Energy Permit covers only the structural/mounting review.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hailey building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Hailey
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Idaho →