Solar Photovoltaic (PV) Permit in Hailey, Idaho

Required for installation of rooftop or ground-mount solar photovoltaic systems within Hailey city limits. The City's own permit is officially named the 'Alternative Energy Permit' (see the sibling alternative-energy-permit entry in this dataset for the full record) and covers the structural/mounting review; it uses a flat application-fee model rather than valuation-based fees, established by Hailey Ordinance No. 1119 specifically to base charges on actual staff time rather than system value. A separate State of Idaho DOPL electrical permit is required for the wiring/interconnection scope.

Verified 2026-07-20 · Source

When you need this permit

  • Alternative Energy Permit application (the City's official name for its solar/renewable-energy permit) submitted to the City of Hailey Building Division for the structural/mounting scope
  • Electrical connection work falls under the State of Idaho DOPL electrical permitting program, not the City -- on the DOPL Contractor Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy'
  • Hailey deliberately moved this permit from valuation-based to flat-fee pricing via Ordinance No. 1119, reasoning that structural review effort does not scale with system cost
  • Renewable energy installations require a plan check prior to final inspection on the state electrical side, per the DOPL Electrical Permit Worksheet

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Alternative Energy Permit -- application feeFY2026 Hailey Municipal Fee Schedule, effective October 1, 2025 (up from $103 + 65% in FY2025); established by Hailey Ordinance No. 1119 to move alternative energy permits from valuation-based to flat-fee pricing
$106, plus 67% of the fee for Plan Review
State DOPL Electrical Permit -- Solar/Renewable Energy, up to $10,000 system costIdaho DOPL Contractor Electrical Permit Worksheet (Fee Schedule), Rev. 8/17/2022
(total system cost x 0.02) + $60
State DOPL Electrical Permit -- Solar/Renewable Energy, $10,001-$100,000 system costIdaho DOPL Contractor Electrical Permit Worksheet, Rev. 8/17/2022
((system cost - $10,000) x 0.01) + $260

Review timeline

Plan review
Not published — contact the department

How long did your Solar Photovoltaic (PV) Permit permit actually take in Hailey?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    State Electrical Inspection

    Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection

  2. 2

    City Final Inspection (Building)

    Racking/roof-penetration attachment and structural compliance verified by the City's Building Division

See the full Hailey inspection guide — scheduling & re-inspection fees →

Tips

  • In Hailey, the City's solar permit is officially called the 'Alternative Energy Permit' -- search for that term on the City's fee schedule and forms, not 'solar permit.'
  • Hailey deliberately moved this permit to a flat fee (rather than a valuation-based fee) via Ordinance No. 1119, reasoning that review effort does not scale with system cost -- this makes Hailey's structural/mounting fee more predictable than most neighboring Idaho jurisdictions.
  • A separate electrical permit through the State of Idaho DOPL is required for the wiring/interconnection portion of any solar installation -- the City's Alternative Energy Permit covers only the structural/mounting review.

Frequently asked questions

Hailey requires a solar photovoltaic (pv) permit for: Alternative Energy Permit application (the City's official name for its solar/renewable-energy permit) submitted to the City of Hailey Building Division for the structural/mounting scope; Electrical connection work falls under the State of Idaho DOPL electrical permitting program, not the City -- on the DOPL Contractor Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy'; Hailey deliberately moved this permit from valuation-based to flat-fee pricing via Ordinance No. 1119, reasoning that structural review effort does not scale with system cost; Renewable energy installations require a plan check prior to final inspection on the state electrical side, per the DOPL Electrical Permit Worksheet. If your project isn't listed, confirm with City of Hailey Community Development Department — Building Services at (208) 788-9815 before starting work.

The City's Alternative Energy Permit is a flat $106 plus 67% of that fee for plan review. The electrical portion is a separate State of Idaho DOPL permit, calculated as (system cost x 0.02) + $60 for systems up to $10,000.

Hailey does not publish a plan-review timeline for this permit. Contact City of Hailey Community Development Department — Building Services at (208) 788-9815 for current turnaround.

You'll need: Alternative Energy Permit Application; Idaho DOPL Contractor (or Homeowner) Electrical Permit Application. See the required-documents checklist on this page for details on each.

Hailey requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: State Electrical Inspection, City Final Inspection (Building). Schedule each through City of Hailey Community Development Department — Building Services ((208) 788-9815).

Apply through City of Hailey Community Development Department — Building Services at 115 S Main Street, Hailey, ID 83333. Phone: (208) 788-9815, email: yadira.ward@haileycityhall.org. Office hours: Mon–Thu 9:00 AM – 5:00 PM; Fri 9:00 AM – 12:00 PM (closed weekends and holidays). Official information: https://haileycityhall.org/community-development/building-services/.

Hailey, Idaho has adopted: 2018 International Building Code (IBC), as amended by the Idaho Building Code Board, including new Appendix O (Radon Control Methods); 2018 International Residential Code (IRC), Parts I–III and IX, as amended by the Idaho Building Code Board, including Appendix F (Radon Control Methods), Appendix Q (Tiny Houses), and Appendix T (Solar Ready Provisions — Detached One- and Two-Family Dwellings and Townhouses); 2018 International Energy Conservation Code (IECC), as amended by the Idaho Building Code Board; 2018 International Swimming Pool and Spa Code (ISPSC); 2018 International Existing Building Code (IEBC), as amended by the Idaho Building Code Board; Idaho State Plumbing Code (ISPC), as adopted and amended by the Idaho Plumbing Board — required plumbing fixture counts per IBC Table 2902.1; National Electrical Code (NEC), latest edition approved by the Idaho Electrical Board — administered and inspected by the State of Idaho, not the City of Hailey. Local amendments apply — see the Hailey overview page for the full list.

Yes, but it is officially named the 'Alternative Energy Permit,' not a 'solar permit.' It costs a flat $106 application fee plus 67% of that fee for plan review (FY2026 Municipal Fee Schedule), covering the structural/mounting scope. A separate electrical permit through the State of Idaho DOPL is required for the wiring and interconnection.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hailey building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.