Building Permit (New Construction, Additions, Remodels — Commercial & Residential) in Hailey, Idaho

Required for erecting, constructing, enlarging, altering, repairing, moving, improving, removing, converting, or demolishing any part of a building in Hailey, including new single-family and multi-family residential construction, new commercial construction, residential remodels, and commercial remodels/tenant improvements (TI). Hailey does NOT have a separate 'Commercial Building Permit' or 'Tenant Improvement Permit' product — commercial work uses this identical application, checked as COMMERCIAL. Painting, residing, and replacing floor coverings are exempt; window replacement requires a permit.

Verified 2026-08-02 · Source

When you need this permit

  • New construction (commercial, single-family residential, or multi-family residential)
  • Remodels (commercial or residential) — a commercial remodel/tenant improvement is filed on this same form, checked 'REMODEL: COMMERCIAL'
  • Garages, basements, carports, foundations
  • Accessory structures over 120 square feet (sheds, decks, pergolas, porches)
  • Window replacement
  • Construction documents must be submitted electronically for residential projects; two or more paper sets for commercial projects, prepared by an Idaho-licensed architect or structural engineer where required
  • Commercial construction documents must additionally demonstrate IECC Commercial Energy Efficiency compliance (Section C407): a COMcheck energy analysis for buildings under 20,000 sq ft, or building-department-approved energy modeling software (e.g., eQuest, Trace, Carrier HAP, EnergyPlus) for buildings 20,000 sq ft or more

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit — valuation $1 to $500Hailey Building Permit Fee Table 1-A, effective October 1, 2025
$27.78
Building Permit — valuation $501 to $2,000Hailey Building Permit Fee Table 1-A, effective October 1, 2025
$27.78 for the first $500, plus $3.23 for each additional $100 or fraction thereof, to and including $2,000
Building Permit — valuation $2,001 to $25,000Hailey Building Permit Fee Table 1-A, effective October 1, 2025
$124.23 for the first $2,000, plus $19.65 for each additional $1,000 or fraction thereof, to and including $25,000
Building Permit — valuation $25,001 to $50,000Hailey Building Permit Fee Table 1-A, effective October 1, 2025
$556.84 for the first $25,000, plus $12.93 for each additional $1,000 or fraction thereof, to and including $50,000
Building Permit — valuation $50,001 to $100,000Hailey Building Permit Fee Table 1-A, effective October 1, 2025
$915.03 for the first $50,000, plus $5.74 for each additional $1,000 or fraction thereof, to and including $100,000
Building Permit — valuation $100,001 to $500,000Hailey Building Permit Fee Table 1-A, effective October 1, 2025
$1,412.52 for the first $100,000, plus $7.11 for each additional $1,000 or fraction thereof, to and including $500,000
Building Permit — valuation $500,001 to $1,000,000Hailey Building Permit Fee Table 1-A, effective October 1, 2025
$4,596.45 for the first $500,000, plus $6.14 for each additional $1,000 or fraction thereof, to and including $1,000,000
Building Permit — valuation $1,000,001 and upHailey Building Permit Fee Table 1-A, effective October 1, 2025
$7,971.90 for the first $1,000,000, plus $4.52 for each additional $1,000 or fraction thereof
Plan Check FeePer Hailey Municipal Fee Schedule effective October 1, 2025 and confirmed on the Building Permit Application (rev. 12/01/2025)
67% of the base Building Permit Fee
Planning Review FeePer Building Permit Application (rev. 12/01/2025)
34% of the Plan Check Fee
Hailey Fire Dept. Plan Review FeePer Hailey Municipal Fee Schedule effective October 1, 2025 and the Building Permit Application (rev. 12/01/2025)
44% of the Plan Check Fee, where applicable
Development Impact Fee — new single-family dwelling, 600 sq ft or less net floor areaDevelopment Impact Fee Schedule effective 12/01/2025; scales up to $12,465 per unit for 3,001+ sq ft
$3,464 per dwelling unit (Parks & Recreation $898 + Circulation $1,407 + Fire $1,018 + Police $141)
Hailey Clean Energy Deposit — new single-family, ADU associated with new construction, or townhomeClean Energy Deposit Fee effective 05/18/2022, confirmed at $1,288 in the FY2026 Municipal Fee Schedule
$1,288.00 flat
Building Permit Extension (180-day extension)FY2026 Hailey Municipal Fee Schedule; up to 4 extensions permitted
$170
Temporary Certificate of Occupancy — CommercialFY2026 Hailey Municipal Fee Schedule (Building section), effective October 1, 2025 (up from $583 in FY2025) — read directly from the fee-schedule PDF, not a distinct permit fee, a genuine commercial-vs-residential rate difference
$600, nonrefundable
Temporary Certificate of Occupancy — ResidentialFY2026 Hailey Municipal Fee Schedule (Building section), effective October 1, 2025 (up from $234 in FY2025); listed for direct comparison against the commercial rate
$241, nonrefundable
Development Impact Fee — Nonresidential (Commercial), per 1,000 sq ft net floor areaDevelopment Impact Fee Schedule effective 12/01/2025, reverse side of the Building Permit Application (rev. 12/01/2025); a distinct nonresidential table separate from the per-dwelling-unit residential DIF table above
$9,864 total (Parks & Recreation $134 + Circulation $7,945 + Fire $1,563 + Police $222)
Development Impact Fee — Nonresidential (Office / Industrial / Institutional / Lodging), per 1,000 sq ft (Lodging is per room)Development Impact Fee Schedule effective 12/01/2025, reverse side of the Building Permit Application (rev. 12/01/2025)
Office $5,867; Industrial $2,085; Institutional $8,128; Lodging $7,972 per room
Hailey Clean Energy Deposit — new mixed use, commercial, industrial, or institutionalClean Energy Deposit Fee effective 05/18/2022, confirmed on the reverse side of the Building Permit Application (rev. 12/01/2025); distinct from the $1,288 flat rate for new single-family/ADU/townhome
$1,250 per 10,000 sq ft

Review timeline

Plan reviewHailey’s published plan-review target
10–10 business days

How long did your Building Permit (New Construction, Additions, Remodels — Commercial & Residential) permit actually take in Hailey?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footings

    Before concrete pour — verify forms, rebar, and anchor bolts meet 24-inch minimum frost depth

  2. 2

    Framing

    After framing and rough-in trades are complete, before insulation or wall cover

  3. 3

    Insulation / Energy

    Insulation and IECC Climate Zone 16 compliance verified before drywall

  4. 4

    Final

    All work complete per approved plans, ready for occupancy

See the full Hailey inspection guide — scheduling & re-inspection fees →

Tips

  • Idaho Code 39-4117 (effective 2025) requires a local government to determine whether a residential building permit application is complete within 10 business days of receipt (20 business days for commercial); this is a completeness-review timeframe, not a full plan-approval SLA — Hailey has not published its own full plan-review-to-issuance turnaround time.
  • Electrical and plumbing permits/inspections in Hailey are handled directly by the State of Idaho Division of Occupational and Professional Licenses (DOPL), not the City — schedule DOPL inspections at 1-208-332-4700 or edopl.idaho.gov/OnlineServices.
  • Hailey's fee schedule folds the plan check fee (67%), planning review fee (34% of plan check), and fire department review fee (44% of plan check, where applicable) on top of the base Table 1-A permit fee — budget for all four line items.
  • Original permits are valid for 548 days; a maximum of four 180-day extensions are allowed; a permit becomes null and void if inspections have not been completed for 180 days.
  • The Hailey Clean Energy Deposit ($1,288 flat for new single-family/ADU/townhome) is separate from and in addition to the Development Impact Fee.
  • Hailey has NO distinct 'Commercial Building Permit' or 'Tenant Improvement Permit' product — per the Building Permit Application form (rev. 12/01/2025), Hailey Municipal Code 15.08.020, and the FY2026 Municipal Fee Schedule (Building section). Commercial new construction and commercial remodels or TI are both filed on this same universal application, checking COMMERCIAL under New Construction or Remodel, and priced off the same Table 1-A valuation-based base fee as residential. Where commercial genuinely differs: 2+ paper plan sets versus electronic-only for residential; IECC Commercial Energy Efficiency compliance (COMcheck under 20,000 sq ft, energy modeling software at 20,000 sq ft and above); a 20-business-day Idaho Code 39-4117 completeness-review window versus 10 business days for residential; a $600 nonrefundable Temporary Certificate of Occupancy fee versus $241 for residential; a separate nonresidential Development Impact Fee table, for example $9,864 per 1,000 sq ft for Commercial use; and a $1,250-per-10,000-sq-ft Clean Energy Deposit rate versus the flat $1,288 residential rate.
  • Searchers looking for a 'TI permit': the 'TI' checkbox on Hailey's Building Permit Application (alongside zoning codes A, B, GR, LR-1, LR-2, TN, LB, LI, SCI-I, SCI-SO, RGB, NB) is a zoning-district abbreviation, not a Tenant Improvement permit type.

Frequently asked questions

Yes. Hailey requires a permit to erect, construct, enlarge, alter, repair, move, improve, remove, convert, or demolish any part of a building. Painting, residing, and floor covering replacement are exempt, but window replacement does require a permit.

In Hailey, the published Building Permit — valuation $1 to $500 is: $27.78. Additional published fees: Building Permit — valuation $501 to $2,000 — $27.78 for the first $500, plus $3.23 for each additional $100 or fraction thereof, to and including $2,000; Building Permit — valuation $2,001 to $25,000 — $124.23 for the first $2,000, plus $19.65 for each additional $1,000 or fraction thereof, to and including $25,000; Building Permit — valuation $25,001 to $50,000 — $556.84 for the first $25,000, plus $12.93 for each additional $1,000 or fraction thereof, to and including $50,000; Building Permit — valuation $50,001 to $100,000 — $915.03 for the first $50,000, plus $5.74 for each additional $1,000 or fraction thereof, to and including $100,000; Building Permit — valuation $100,001 to $500,000 — $1,412.52 for the first $100,000, plus $7.11 for each additional $1,000 or fraction thereof, to and including $500,000; Building Permit — valuation $500,001 to $1,000,000 — $4,596.45 for the first $500,000, plus $6.14 for each additional $1,000 or fraction thereof, to and including $1,000,000; Building Permit — valuation $1,000,001 and up — $7,971.90 for the first $1,000,000, plus $4.52 for each additional $1,000 or fraction thereof; Plan Check Fee — 67% of the base Building Permit Fee; Planning Review Fee — 34% of the Plan Check Fee; Hailey Fire Dept. Plan Review Fee — 44% of the Plan Check Fee, where applicable; Development Impact Fee — new single-family dwelling, 600 sq ft or less net floor area — $3,464 per dwelling unit (Parks & Recreation $898 + Circulation $1,407 + Fire $1,018 + Police $141); Hailey Clean Energy Deposit — new single-family, ADU associated with new construction, or townhome — $1,288.00 flat; Building Permit Extension (180-day extension) — $170; Temporary Certificate of Occupancy — Commercial — $600, nonrefundable; Temporary Certificate of Occupancy — Residential — $241, nonrefundable; Development Impact Fee — Nonresidential (Commercial), per 1,000 sq ft net floor area — $9,864 total (Parks & Recreation $134 + Circulation $7,945 + Fire $1,563 + Police $222); Development Impact Fee — Nonresidential (Office / Industrial / Institutional / Lodging), per 1,000 sq ft (Lodging is per room) — Office $5,867; Industrial $2,085; Institutional $8,128; Lodging $7,972 per room; Hailey Clean Energy Deposit — new mixed use, commercial, industrial, or institutional — $1,250 per 10,000 sq ft. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Idaho Code 39-4117 requires the City to determine whether a residential application is complete within 10 business days of submission (20 business days for commercial). The City of Hailey has not published a separate full plan-review-to-approval timeframe beyond this statutory completeness-review requirement.

You'll need: Application for Building Permit; Construction Drawings; Zoning Review Checklist. Depending on your project, Hailey may also ask for: Floodplain Development Permit Application. See the required-documents checklist on this page for details on each.

Hailey requires 4 inspection(s) for a building permit (new construction, additions, remodels — commercial & residential), in order: Foundation / Footings, Framing, Insulation / Energy, Final. Schedule each through City of Hailey Community Development Department — Building Services ((208) 788-9815).

Apply through City of Hailey Community Development Department — Building Services at 115 S Main Street, Hailey, ID 83333. Phone: (208) 788-9815, email: yadira.ward@haileycityhall.org. Office hours: Mon–Thu 9:00 AM – 5:00 PM; Fri 9:00 AM – 12:00 PM (closed weekends and holidays). Official information: https://haileycityhall.org/community-development/building-services/.

Hailey, Idaho has adopted: 2018 International Building Code (IBC), as amended by the Idaho Building Code Board, including new Appendix O (Radon Control Methods); 2018 International Residential Code (IRC), Parts I–III and IX, as amended by the Idaho Building Code Board, including Appendix F (Radon Control Methods), Appendix Q (Tiny Houses), and Appendix T (Solar Ready Provisions — Detached One- and Two-Family Dwellings and Townhouses); 2018 International Energy Conservation Code (IECC), as amended by the Idaho Building Code Board; 2018 International Swimming Pool and Spa Code (ISPSC); 2018 International Existing Building Code (IEBC), as amended by the Idaho Building Code Board; Idaho State Plumbing Code (ISPC), as adopted and amended by the Idaho Plumbing Board — required plumbing fixture counts per IBC Table 2902.1; National Electrical Code (NEC), latest edition approved by the Idaho Electrical Board — administered and inspected by the State of Idaho, not the City of Hailey. Local amendments apply — see the Hailey overview page for the full list.

No. Hailey does not issue a distinct 'Commercial Building Permit' or 'Tenant Improvement Permit.' Commercial new construction and commercial remodels (TI work) both go through this same 'Application for Building Permit,' checked as COMMERCIAL under either New Construction or Remodel, and are charged using the same Table 1-A valuation-based fee schedule as residential projects. Commercial projects do carry some distinct requirements and fees: 2 or more paper plan sets (vs. electronic submittal for residential), IECC Commercial Energy Efficiency compliance, a 20-business-day statutory completeness-review window (vs. 10 for residential), a $600 nonrefundable Temporary Certificate of Occupancy fee (vs. $241 residential), a separate nonresidential Development Impact Fee table, and a Clean Energy Deposit of $1,250 per 10,000 sq ft (vs. a flat $1,288 for new single-family homes).

Hailey's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Hailey yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Hailey lands. Privacy.