Demolition Permit in Ketchum, Idaho

Required for demolition of structures in Ketchum, whether an entire structure or internal/partial demolition. Demo-Entire Structure and Demo-Internal Only or Partial Structure are both in the City's Short review tier.

Verified 2026-07-08 · Source

When you need this permit

  • Demolition of an entire structure or internal/partial demolition requires a City of Ketchum building permit
  • Demo-Internal Only or Partial Structure projects outside the Community Core may use a CAP Affidavit in place of a full Construction Activity Plan

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition PermitCity of Ketchum Permit, Impact & Water Fees schedule, 'Various Permits' table, effective October 1, 2024
$1,100

Review timeline

Plan reviewKetchum’s published plan-review target
7–7 business days

How long did your Demolition Permit permit actually take in Ketchum?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Site verified clear and safe following demolition

See the full Ketchum inspection guide — scheduling & re-inspection fees →

Tips

  • Demo permits (entire structure or internal/partial) are in the Short review tier: 7 calendar days for first review.
  • The flat $1,100 fee applies regardless of project valuation.

Frequently asked questions

Ketchum requires a demolition permit for: Demolition of an entire structure or internal/partial demolition requires a City of Ketchum building permit; Demo-Internal Only or Partial Structure projects outside the Community Core may use a CAP Affidavit in place of a full Construction Activity Plan. If your project isn't listed, confirm with City of Ketchum Planning & Building Department at (208) 726-7801 before starting work.

The City of Ketchum charges a flat $1,100 fee for a Demolition Permit, per the Permit, Impact & Water Fees schedule effective October 1, 2024.

Ketchum's published plan-review target for a demolition permit is 7–7 business days.

You'll need: Building Permit Application (CommunityConnect). Depending on your project, Ketchum may also ask for: CAP Affidavit. See the required-documents checklist on this page for details on each.

Ketchum requires 1 inspection(s) for a demolition permit, in order: Final. Schedule each through City of Ketchum Planning & Building Department ((208) 726-7801).

Apply through City of Ketchum Planning & Building Department at 191 5th St. West (P.O. Box 2315), Ketchum, ID 83340. Phone: (208) 726-7801, email: participate@ketchumidaho.org. Office hours: Mon–Fri 8:30 AM – 5:00 PM. Official information: https://www.ketchumidaho.org/planning-building/page/building-services.

Ketchum, Idaho has adopted: 2018 International Building Code (IBC) — as amended by the Idaho Building Code Board, with Appendix O; 2018 International Residential Code (IRC) — as amended by the Idaho Building Code Board, Parts I–III and IX, with Appendix F; 2018 International Energy Conservation Code (IECC) — as amended by the Idaho Building Code Board; 2018 International Existing Building Code (IEBC) — as amended by the Idaho Building Code Board; 2018 International Swimming Pool and Spa Code (ISPSC) — adopted by State and City without amendment; 2018 International Property Maintenance Code (IPMC) — adopted by City of Ketchum; 2018 International Fire Code (IFC) — with Appendix Chapters B, C, D, E, and F; ICC A117.1 — Accessible and Usable Buildings and Facilities (as referenced in the adopted IBC); Electrical, plumbing, and mechanical trade work is regulated and permitted by the State of Idaho Division of Building Safety (DBS) / Division of Occupational and Professional Licenses (DOPL) — Ketchum does not issue its own trade permits; Modular buildings and structures are regulated by the State of Idaho Division of Building Safety (DBS). Local amendments apply — see the Ketchum overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ketchum building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.