Residential Building Permit (New Construction / Additions) in Ketchum, Idaho

Required for new single-family dwellings and additions in Ketchum. Covers structural construction, framing, envelope, and associated systems reviewed against the 2018 IBC/IRC/IECC as locally amended. As of February 27, 2026, the City buckets permit review into Short/Medium/Standard timelines based on project complexity; new construction and additions fall in the Standard tier.

Verified 2026-07-08 · Source

When you need this permit

  • All new residential construction and additions require a building permit and plan review approval from Planning & Building
  • Submit via the CommunityConnect online permitting platform
  • Plans must meet the 2018 IBC/IRC/IECC as amended by the Idaho Building Code Board and Ketchum Municipal Code Chapter 15.04
  • Construction Activity Plan (CAP) required for projects in the Community Core/downtown; a CAP Affidavit may substitute for less complex projects outside the Community Core
  • Building Permit must be visibly posted on site during construction

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — valuation $501 to $2,000City of Ketchum Permit, Impact & Water Fees schedule, effective October 1, 2024 (updated 8/30/24)
$24.75 for the first $500, plus $3.20 for each additional $100 or fraction thereof
Building Permit — valuation $2,001 to $25,000
$72.75 for the first $2,000, plus $14.70 per each additional $1,000 or fraction thereof
Building Permit — valuation $25,001 to $50,000
$410.75 for the first $25,000, plus $10.60 per each additional $1,000 or fraction thereof
Building Permit — valuation $50,001 to $100,000
$676.00 for the first $50,000, plus $7.35 per each additional $1,000 or fraction thereof
Building Permit — valuation $100,001 to $500,000
$1,043.50 for the first $100,000, plus $5.90 per each additional $1,000 or fraction thereof
Building Permit — valuation $500,001 to $1,000,000
$3,395.50 for the first $500,000, plus $5.00 per each additional $1,000 or fraction thereof
Building Permit — valuation $1,000,001 and up
$5,889.25 for the first $1,000,000, plus $3.85 per each additional $1,000 or fraction thereof
Plan Check FeeAdditional Planning & Zoning Plan Check Fee (70% of Plan Check Fee) and Fire Department Plan Check Fee (70% of Plan Check Fee) also apply per the same schedule
65% of the Building Permit Fee
Development Impact Fee — Single Family (Fire/Parks/Police/Streets combined)Permit, Impact & Water Fees schedule, effective October 1, 2024
$2,092.00 (Fire) + $1,047.00 (Parks) + $104.00 (Police) + $4,492.00 (Streets) = $7,735.00

Review timeline

Plan reviewKetchum’s published plan-review target
25–25 business days

How long did your Residential Building Permit (New Construction / Additions) permit actually take in Ketchum?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footings / Foundation

    Before concrete pour — forms, rebar, and foundation elements verified

  2. 2

    Framing

    Structural framing verified before insulation or wall cover

  3. 3

    Insulation

    Insulation and energy code compliance verified before drywall

  4. 4

    Masonry / Concrete

    Masonry and concrete work verified as applicable to the project

  5. 5

    Roofing

    Roof assembly and covering verified

  6. 6

    Pre-Final

    Pre-final inspection required on all permits (except re-roofs) before departmental finals commence

  7. 7

    Final Building Inspection

    Last inspection before Certificate of Occupancy/Certificate of Completion, after Fire, Planning, and Engineering finals are complete

See the full Ketchum inspection guide — scheduling & re-inspection fees →

Tips

  • As of February 27, 2026, Ketchum buckets permit types into Short (7 calendar days first review), Medium (15 calendar days), and Standard (25 calendar days) review timelines; New Construction and Additions are in the Standard tier. All additional review rounds are 7 calendar days.
  • The City's building department now uses CommunityConnect for permit applications, tracking, and inspection scheduling.
  • 24-hour advance notice is required to schedule any city building inspection; call (208) 727-5079 or use CommunityConnect.
  • Construction activity (noise-generating work) is limited to 7:30 AM–7:00 PM on weekdays and Saturdays; work is prohibited on Sundays and holidays per Ketchum Municipal Code 8.08.050.14.
  • Electrical, plumbing, and mechanical/HVAC work is NOT permitted or inspected by the City — those trades are permitted directly through the State of Idaho Division of Building Safety (DBS/DOPL) via eTRAKiT or dbs.idaho.gov.

Frequently asked questions

Yes. All new residential construction and additions in Ketchum require a building permit and plan review approval from the Planning & Building Department, submitted through CommunityConnect.

In Ketchum, the published Building Permit — valuation $501 to $2,000 is: $24.75 for the first $500, plus $3.20 for each additional $100 or fraction thereof. Additional published fees: Building Permit — valuation $2,001 to $25,000 — $72.75 for the first $2,000, plus $14.70 per each additional $1,000 or fraction thereof; Building Permit — valuation $25,001 to $50,000 — $410.75 for the first $25,000, plus $10.60 per each additional $1,000 or fraction thereof; Building Permit — valuation $50,001 to $100,000 — $676.00 for the first $50,000, plus $7.35 per each additional $1,000 or fraction thereof; Building Permit — valuation $100,001 to $500,000 — $1,043.50 for the first $100,000, plus $5.90 per each additional $1,000 or fraction thereof; Building Permit — valuation $500,001 to $1,000,000 — $3,395.50 for the first $500,000, plus $5.00 per each additional $1,000 or fraction thereof; Building Permit — valuation $1,000,001 and up — $5,889.25 for the first $1,000,000, plus $3.85 per each additional $1,000 or fraction thereof; Plan Check Fee — 65% of the Building Permit Fee; Development Impact Fee — Single Family (Fire/Parks/Police/Streets combined) — $2,092.00 (Fire) + $1,047.00 (Parks) + $104.00 (Police) + $4,492.00 (Streets) = $7,735.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the City's February 2026 permit process update, New Construction and Additions fall in the 'Standard' review tier: 25 calendar days for first review. Additional review rounds (if plans need revision) take 7 calendar days each.

You'll need: Building Permit Application (CommunityConnect); Construction Drawings; Construction Activity Plan (CAP) or CAP Affidavit. Depending on your project, Ketchum may also ask for: Contractor Affidavit. See the required-documents checklist on this page for details on each.

Ketchum requires 7 inspection(s) for a residential building permit (new construction / additions), in order: Footings / Foundation, Framing, Insulation, Masonry / Concrete, Roofing, Pre-Final, Final Building Inspection. Schedule each through City of Ketchum Planning & Building Department ((208) 726-7801).

Apply through City of Ketchum Planning & Building Department at 191 5th St. West (P.O. Box 2315), Ketchum, ID 83340. Phone: (208) 726-7801, email: participate@ketchumidaho.org. Office hours: Mon–Fri 8:30 AM – 5:00 PM. Official information: https://www.ketchumidaho.org/planning-building/page/building-services.

Ketchum, Idaho has adopted: 2018 International Building Code (IBC) — as amended by the Idaho Building Code Board, with Appendix O; 2018 International Residential Code (IRC) — as amended by the Idaho Building Code Board, Parts I–III and IX, with Appendix F; 2018 International Energy Conservation Code (IECC) — as amended by the Idaho Building Code Board; 2018 International Existing Building Code (IEBC) — as amended by the Idaho Building Code Board; 2018 International Swimming Pool and Spa Code (ISPSC) — adopted by State and City without amendment; 2018 International Property Maintenance Code (IPMC) — adopted by City of Ketchum; 2018 International Fire Code (IFC) — with Appendix Chapters B, C, D, E, and F; ICC A117.1 — Accessible and Usable Buildings and Facilities (as referenced in the adopted IBC); Electrical, plumbing, and mechanical trade work is regulated and permitted by the State of Idaho Division of Building Safety (DBS) / Division of Occupational and Professional Licenses (DOPL) — Ketchum does not issue its own trade permits; Modular buildings and structures are regulated by the State of Idaho Division of Building Safety (DBS). Local amendments apply — see the Ketchum overview page for the full list.

No. The City of Ketchum's own building services page states that mechanical, electrical, and plumbing permits and inspections are handled directly by the State of Idaho — not the city. Homeowners and contractors obtain these permits through the Idaho Division of Building Safety (dbs.idaho.gov) or by calling (208) 332-4700.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ketchum building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.