Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) in Ketchum, Idaho

Covers new non-residential construction, commercial additions, and commercial interior or exterior remodels and tenant improvements in Ketchum. There is no separate commercial or tenant-improvement permit product — these projects go through the same Building Permit categories used for residential work (New Construction, Additions, Internal Remodel, External Repair & External Remodel) via the CommunityConnect portal, with plans for non-residential structures reviewed against the 2018 IBC rather than the 2018 IRC used for one- and two-family dwellings, per Ketchum Municipal Code Title 15. The Building Permit fee table, the 65% Plan Check Fee, and the added 70% Planning & Zoning and 70% Fire Department Plan Check fees are the same for commercial and residential projects; the Development Impact Fee is the one line that differs, charged per square foot for commercial use rather than as a flat per-unit amount. Non-residential and mixed-use exterior work also triggers Design Review under the City's Land Development Code in every zoning district, not just the downtown Community Core.

Verified 2026-08-25 · Source

When you need this permit

  • A building permit is required for new non-residential construction, commercial additions, and commercial interior or exterior remodels and tenant-improvement work, submitted through CommunityConnect — the same online platform and Building Permit product used for residential projects
  • Non-residential structures are reviewed against the 2018 International Building Code (as amended by the Idaho Building Code Board, with Appendix O), rather than the 2018 IRC used for one- and two-family dwellings, per Ketchum Municipal Code Title 15, Chapter 15.04
  • As of February 27, 2026, the City buckets first-review timelines by project type rather than by residential/commercial occupancy: New Construction and Additions fall in the Standard tier (25 calendar days), while Internal Remodel and External Repair & External Remodel projects fall in the Medium tier (15 calendar days) — a commercial project's timeline depends on which category the work falls into
  • Design Review is required, in all zoning districts, for building, developing, or substantially altering the exterior of any nonresidential, public/semipublic, or mixed-use building, per the City's Land Development Code Section 16.04.080.B; a separate Preapplication Design Review step is additionally required ahead of that for new non-residential development meeting the size and scale thresholds in Section 16.07.030.C
  • Projects within the City's Mountain Overlay District — a mapped hillside and steep-slope overlay, not itself a snow-load or wildfire designation — face additional siting standards and must complete Design Review before a Building Permit, excavation/grading permit, or construction may begin, per Land Development Code Section 16.02.070.D
  • Electrical, plumbing, and mechanical/HVAC work on commercial projects is not permitted by the City; those permits are issued directly by the State of Idaho Division of Building Safety/Division of Occupational and Professional Licenses (DOPL)
  • 24-hour advance notice is required for City-scheduled inspections; construction activity is limited to 7:30 AM-7:00 PM on weekdays and Saturdays and prohibited on Sundays and holidays, per Ketchum Municipal Code 8.08.050.14
  • A Construction Activity Plan (CAP) is required for projects in the Community Core/downtown; a CAP Affidavit may substitute for eligible, less complex project types outside the Community Core

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee (valuation-based)
City of Ketchum Permit, Impact & Water Fees schedule, effective October 1, 2024 — one citywide table for both residential and commercial construction; Show full citationCity of Ketchum Permit, Impact & Water Fees schedule, effective October 1, 2024 — one citywide table for both residential and commercial construction; the City does not publish a separate valuation table for commercial projects. See the Residential Building Permit for the full tier-by-tier breakdown.
The same seven-tier valuation schedule used for the Residential Building Permit, from $24.75 for the first $500 of valuation up to $5,889.25 for the first $1,000,000 plus $3.85 per each additional $1,000
Plan Check FeeCity of Ketchum Permit, Impact & Water Fees schedule, effective October 1, 2024 — the same rate applied to residential projects
65% of the Building Permit Fee
Planning & Zoning Plan Check FeeCity of Ketchum Permit, Impact & Water Fees schedule, effective October 1, 2024 — assessed where Planning & Zoning review of the project is required
70% of the Plan Check Fee
Fire Department Plan Check FeeCity of Ketchum Permit, Impact & Water Fees schedule, effective October 1, 2024 — billed by the City alongside the Building Permit and Plan Check fees, assessed where Fire Department review of the project is required
70% of the Plan Check Fee
Development Impact Fee — Commercial (Fire, Police, Streets; Parks not charged)
City of Ketchum Permit, Impact & Water Fees schedule, effective October 1, 2024 — calculated per square foot for commercial use, versus a flat per-unit charge for Single Family ($2,092.00 Fire +… Show full citationCity of Ketchum Permit, Impact & Water Fees schedule, effective October 1, 2024 — calculated per square foot for commercial use, versus a flat per-unit charge for Single Family ($2,092.00 Fire + $104.00 Police + $4,492.00 Streets + $1,047.00 Parks) and Multi-Family ($1,616.00 Fire + $80.00 Police + $3,471.00 Streets + $809.00 Parks) development
$0.454 per square foot (Fire) + $0.022 per square foot (Police) + $0.968 per square foot (Streets) + $0.00 per square foot (Parks)

Review timeline

Plan reviewKetchum’s published plan-review target
15–25 business days

How long did your Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) permit actually take in Ketchum?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footings / Foundation

    Before concrete pour — forms, rebar, and foundation elements verified

  2. 2

    Framing

    Structural framing verified before insulation or wall cover

  3. 3

    Insulation

    Insulation and energy code compliance verified before drywall

  4. 4

    Masonry / Concrete

    Masonry and concrete work verified as applicable to the project

  5. 5

    Roofing

    Roof assembly and covering verified

  6. 6

    Pre-Final

    Pre-final inspection required on all permits except re-roofs, before departmental finals commence

  7. 7

    Final Building Inspection

    Last inspection before Certificate of Occupancy/Certificate of Completion, after Fire, Planning, and Engineering finals are complete

See the full Ketchum inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate commercial or tenant-improvement permit in Ketchum; non-residential work uses the same New Construction, Additions, Internal Remodel, and External Repair & External Remodel categories as residential projects, with the 2018 IBC substituting for the 2018 IRC as the code that governs plan review.
  • Design Review attaches to nonresidential exterior work in every zoning district, not only the Community Core — budget time for it ahead of Building Permit submittal, and check whether the project also triggers the separate Preapplication Design Review step required for larger new non-residential developments.
  • The Building Permit fee table, the 65% Plan Check Fee, and the 70%/70% Planning and Fire Department add-on fees are identical to residential; the Development Impact Fee is the one line that is genuinely commercial-specific, billed per square foot rather than as a flat per-unit charge.
  • Electrical, plumbing, and mechanical permits for commercial projects are obtained directly from the State of Idaho Division of Building Safety/DOPL, not the City of Ketchum.
  • Idaho Code 39-4117 gives the City 20 business days to determine whether a commercial application is complete enough to enter review — separate from, and shorter than, the City's own 15- to 25-calendar-day first-review timelines.
  • Projects in the Mountain Overlay District face added siting standards on top of Design Review; check the Ketchum zoning map for whether a given parcel falls inside that district before assuming a standard commercial review track applies.

Frequently asked questions

Ketchum requires a commercial building permit (new construction, additions, remodels & tenant improvements) for: A building permit is required for new non-residential construction, commercial additions, and commercial interior or exterior remodels and tenant-improvement work, submitted through CommunityConnect — the same online platform and Building Permit product used for residential projects; Non-residential structures are reviewed against the 2018 International Building Code (as amended by the Idaho Building Code Board, with Appendix O), rather than the 2018 IRC used for one- and two-family dwellings, per Ketchum Municipal Code Title 15, Chapter 15.04; As of February 27, 2026, the City buckets first-review timelines by project type rather than by residential/commercial occupancy: New Construction and Additions fall in the Standard tier (25 calendar days), while Internal Remodel and External Repair & External Remodel projects fall in the Medium tier (15 calendar days) — a commercial project's timeline depends on which category the work falls into; Design Review is required, in all zoning districts, for building, developing, or substantially altering the exterior of any nonresidential, public/semipublic, or mixed-use building, per the City's Land Development Code Section 16.04.080.B; a separate Preapplication Design Review step is additionally required ahead of that for new non-residential development meeting the size and scale thresholds in Section 16.07.030.C; Projects within the City's Mountain Overlay District — a mapped hillside and steep-slope overlay, not itself a snow-load or wildfire designation — face additional siting standards and must complete Design Review before a Building Permit, excavation/grading permit, or construction may begin, per Land Development Code Section 16.02.070.D; Electrical, plumbing, and mechanical/HVAC work on commercial projects is not permitted by the City; those permits are issued directly by the State of Idaho Division of Building Safety/Division of Occupational and Professional Licenses (DOPL); 24-hour advance notice is required for City-scheduled inspections; construction activity is limited to 7:30 AM-7:00 PM on weekdays and Saturdays and prohibited on Sundays and holidays, per Ketchum Municipal Code 8.08.050.14; A Construction Activity Plan (CAP) is required for projects in the Community Core/downtown; a CAP Affidavit may substitute for eligible, less complex project types outside the Community Core. If your project isn't listed, confirm with City of Ketchum Planning & Building Department at (208) 726-7801 before starting work.

In Ketchum, the published Building Permit Fee (valuation-based) is: The same seven-tier valuation schedule used for the Residential Building Permit, from $24.75 for the first $500 of valuation up to $5,889.25 for the first $1,000,000 plus $3.85 per each additional $1,000. Additional published fees: Plan Check Fee — 65% of the Building Permit Fee; Planning & Zoning Plan Check Fee — 70% of the Plan Check Fee; Fire Department Plan Check Fee — 70% of the Plan Check Fee; Development Impact Fee — Commercial (Fire, Police, Streets; Parks not charged) — $0.454 per square foot (Fire) + $0.022 per square foot (Police) + $0.968 per square foot (Streets) + $0.00 per square foot (Parks). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

It depends on the project type. Under the City's February 2026 tiering, new construction and additions are in the Standard tier at 25 calendar days for first review; interior remodels and exterior repair/remodel projects are in the Medium tier at 15 calendar days for first review. Additional review rounds, in either tier, take 7 calendar days.

You'll need: Building Permit Application (CommunityConnect); Construction Drawings. Depending on your project, Ketchum may also ask for: Design Review Application; Construction Activity Plan (CAP) or CAP Affidavit. See the required-documents checklist on this page for details on each.

Ketchum requires 7 inspection(s) for a commercial building permit (new construction, additions, remodels & tenant improvements), in order: Footings / Foundation, Framing, Insulation, Masonry / Concrete, Roofing, Pre-Final, Final Building Inspection. Schedule each through City of Ketchum Planning & Building Department ((208) 726-7801).

Apply through City of Ketchum Planning & Building Department at 191 5th St. West (P.O. Box 2315), Ketchum, ID 83340. Phone: (208) 726-7801, email: participate@ketchumidaho.org. Office hours: Mon–Fri 8:30 AM – 5:00 PM. Official information: https://www.ketchumidaho.org/planning-building/page/building-services.

No. New non-residential construction and additions go through the same 'New Construction' and 'Additions' Building Permit categories used for residential projects, and commercial interior or exterior remodels use the same 'Internal Remodel' or 'External Repair & External Remodel' categories — all submitted through CommunityConnect. The only difference is which adopted code governs plan review: the 2018 IBC for non-residential structures versus the 2018 IRC for one- and two-family dwellings.

Yes, in most cases. The City's Land Development Code requires Design Review for building, developing, or substantially altering the exterior of any nonresidential, public/semipublic, or mixed-use building, in every zoning district — not only the downtown Community Core. Larger new non-residential developments must also complete a separate Preapplication Design Review step first.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Ketchum.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.