Required for rooftop or ground-mounted solar PV installation in Ketchum. The City issues a flat-fee Solar Permit for the structural/building portion (using a Building Affidavit and CAP Affidavit in place of full review); the electrical interconnection is separately permitted and inspected by the State of Idaho Division of Building Safety (DBS/DOPL), not the City.

Verified 2026-07-08 · Source

When you need this permit

  • City Solar Permit required for structural mounting of rooftop or ground-mounted panels
  • Building Affidavit and CAP Affidavit apply to Solar in place of full Building Plan Check / Construction Activity Plan review
  • Separate State of Idaho electrical permit required for panel wiring, inverter, and grid interconnection — obtained through DBS/DOPL, not the City of Ketchum
  • Grid-connected renewable energy systems require a State plan check permit number prior to purchasing the state electrical installation permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

City Solar Permit (structural/building portion)City of Ketchum Permit, Impact & Water Fees schedule, 'Various Permits' table, effective October 1, 2024
$100 flat fee
State of Idaho Electrical Permit — grid-connected renewable energy (structural/electrical installation)Idaho DOPL Electrical Permit Worksheet (Homeowner), 'Other Installations including Solar/Renewable Energy' table, revised 8/17/2022. Grid-connected systems additionally require a state plan-check permit number before the installation permit can be purchased.
Up to $10,000 system cost: (cost x 0.02) + $60. $10,001–$100,000: ((cost − $10,000) x 0.01) + $260. Over $100,001: ((cost − $100,000) x 0.005) + $1,160

Review timeline

Plan reviewKetchum’s published plan-review target
7–7 business days

How long did your Solar Photovoltaic (PV) Permit permit actually take in Ketchum?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final — Building/Structural (City)

    Panel mounting and racking attachment verified by the City of Ketchum

  2. 2

    Electrical Inspection (State of Idaho)

    Wiring, inverter, and interconnection inspected by DBS/DOPL — scheduled separately via eTRAKiT or (208) 332-4700

See the full Ketchum inspection guide — scheduling & re-inspection fees →

Tips

  • Solar is in the City's Short review tier: 7 calendar days for first review of the structural/building permit.
  • Two separate permits and two separate agencies are involved: the City of Ketchum handles the structural mounting permit ($100 flat fee); the State of Idaho DBS/DOPL handles the electrical interconnection permit (cost-based formula).
  • Grid-connected renewable energy systems must obtain a State plan-check permit number before purchasing the state electrical installation permit — contact DOPL at 1-800-955-3044.
  • CAP Affidavit and Building Affidavit both apply to Solar permits as of February 2026, streamlining the City-side review.

Frequently asked questions

Ketchum requires a solar photovoltaic (pv) permit for: City Solar Permit required for structural mounting of rooftop or ground-mounted panels; Building Affidavit and CAP Affidavit apply to Solar in place of full Building Plan Check / Construction Activity Plan review; Separate State of Idaho electrical permit required for panel wiring, inverter, and grid interconnection — obtained through DBS/DOPL, not the City of Ketchum; Grid-connected renewable energy systems require a State plan check permit number prior to purchasing the state electrical installation permit. If your project isn't listed, confirm with City of Ketchum Planning & Building Department at (208) 726-7801 before starting work.

The City of Ketchum charges a flat $100 Solar Permit fee for the structural/building portion. A separate State of Idaho electrical permit is also required for the wiring and interconnection, calculated as a percentage of system cost (2% of cost up to $10,000, plus a $60 base fee, per the DOPL fee worksheet).

Ketchum's published plan-review target for a solar photovoltaic (pv) permit is 7–7 business days.

You'll need: Building Permit Application (CommunityConnect); Building Affidavit; State of Idaho Electrical Permit Application. See the required-documents checklist on this page for details on each.

Ketchum requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: Final — Building/Structural (City), Electrical Inspection (State of Idaho). Schedule each through City of Ketchum Planning & Building Department ((208) 726-7801).

Apply through City of Ketchum Planning & Building Department at 191 5th St. West (P.O. Box 2315), Ketchum, ID 83340. Phone: (208) 726-7801, email: participate@ketchumidaho.org. Office hours: Mon–Fri 8:30 AM – 5:00 PM. Official information: https://www.ketchumidaho.org/planning-building/page/building-services.

Ketchum, Idaho has adopted: 2018 International Building Code (IBC) — as amended by the Idaho Building Code Board, with Appendix O; 2018 International Residential Code (IRC) — as amended by the Idaho Building Code Board, Parts I–III and IX, with Appendix F; 2018 International Energy Conservation Code (IECC) — as amended by the Idaho Building Code Board; 2018 International Existing Building Code (IEBC) — as amended by the Idaho Building Code Board; 2018 International Swimming Pool and Spa Code (ISPSC) — adopted by State and City without amendment; 2018 International Property Maintenance Code (IPMC) — adopted by City of Ketchum; 2018 International Fire Code (IFC) — with Appendix Chapters B, C, D, E, and F; ICC A117.1 — Accessible and Usable Buildings and Facilities (as referenced in the adopted IBC); Electrical, plumbing, and mechanical trade work is regulated and permitted by the State of Idaho Division of Building Safety (DBS) / Division of Occupational and Professional Licenses (DOPL) — Ketchum does not issue its own trade permits; Modular buildings and structures are regulated by the State of Idaho Division of Building Safety (DBS). Local amendments apply — see the Ketchum overview page for the full list.

No. Electrical permitting and inspection for solar installations — like all electrical work in Ketchum — is handled by the State of Idaho Division of Building Safety (DBS/DOPL), not the City. Only the structural mounting permit is issued by the City.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ketchum building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.