Solar Photovoltaic (PV) Permit — Worley, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://dopl.idaho.gov/wp-content/uploads/2023/10/BLD-Rules.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit in Worley, Idaho
Required for installing a rooftop or ground-mounted solar photovoltaic system within Worley city limits. Unlike many Idaho cities that run their own local building department, Worley relies entirely on the State of Idaho DOPL for BOTH the structural building permit and the electrical permit — plan review and inspection for all trades (building, electrical, mechanical, plumbing) are performed by DOPL under the statewide program, with the City of Worley only handling permit application intake at City Hall. Neither DOPL's Table 1-A Building Permit Fees nor its Electrical Permit Worksheet publishes a dedicated solar/PV-specific building fee, but DOPL's electrical fee schedule does publish a dedicated Solar/Renewable Energy formula.
Verified 2026-07-20 · Source
When you need this permit
- State of Idaho DOPL building permit required for the structural/roof-mount or ground-mount portion, per Idaho Code § 39-4109 and IDAPA 24.39.30 (Rules of Building Safety) — application picked up/submitted at Worley City Hall, plan review and inspection performed by DOPL
- State of Idaho DOPL electrical permit required for the PV wiring/interconnection portion — purchased through dopl.idaho.gov; NOT issued locally, as Worley has no city electrical program
- Solar/Renewable Energy box must be checked on the DOPL Electrical Permit Worksheet, with the total cost of the electrical system entered as the Job Value Amount
- Grid-Connected Renewable Energy systems require a plan check permit number FIRST (contact DOPL at 1-800-955-3044) before the installation permit can be purchased
- Plans must comply with the 2018 IBC / Idaho Residential Code (2020 edition) and Idaho Energy Conservation Code as adopted by the Idaho Building Code Board
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
DOPL Building Inspection (structural)
Racking, roof/ground-mount attachment, and structural connections verified by the DOPL-assigned building inspector for the Worley/Kootenai County area
- 2
DOPL Electrical Rough-In/Final
All electrical work performed under a DOPL permit must be inspected by the Division of Occupational and Professional Licensing; at Final inspection the scope of work, valuation, and permit fees are verified against actual costs
See the full Worley inspection guide — scheduling & re-inspection fees →
Tips
- Worley is unusual even among small Idaho cities: DOPL administers BOTH the structural building permit and the electrical permit — the City itself only handles application intake at City Hall, with no local plan review or inspection staff of its own for either trade.
- DOPL's solar electrical fee formula is tiered by total system cost, not wattage: 2% of cost plus $60 up to $10,000; 1% of the amount over $10,000 plus $260 up to $100,000; 0.5% of the amount over $100,000 plus $1,160 above that.
- A grid-connected system needs a plan-check permit number from DOPL BEFORE you can purchase the installation permit — budget extra lead time for this step.
- DOPL's Table 1-A Building Permit Fee has no solar-specific discount or line item — the racking/mounting portion of a PV installation is valued and charged the same as any other construction.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Worley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Worley
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Idaho →
Look up this fee in a different city →
Now live
Build your Worley project checklist
Describe your project once and get every permit, document, and fee it triggers in Worley — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →