Because Hardin holds no DLI certification in Electrical (only a residential-only Building certification), EV charger circuit work anywhere within Hardin city limits -- residential or commercial -- requires an Electrical Permit issued directly by the Montana DLI Building Codes Bureau in Helena, not by the City of Hardin, under the 2020 NEC. The state's Application for Residential Electrical Permit (Rev. 11/25) has no dedicated EV/EVSE line item -- it lists an 'Alternative Energy' line (K, $45) that only covers Solar/Wind/Hydro generation, not vehicle-charging loads. A single EV charger circuit added to an existing home instead falls under line H, '1 additional circuit or piece of equipment' ($45), the same category used for a hot tub or A/C circuit.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit issued by the Montana DLI Building Codes Bureau (Helena), not the City of Hardin, per Title 50, Chapter 60, Section 604 MCA and ARM 24.301.431
  • No EV/EVSE-specific line item exists on the state's Residential or Commercial Electrical Permit application -- do NOT check the 'Alternative Energy Source' box, which is scoped to Solar/Wind/Hydro generation systems, not EV charging
  • A single charger circuit added to an existing single-family home falls under line H, '1 additional circuit or piece of equipment'
  • New-construction wiring for a charger circuit is included in the applicable new-dwelling amperage-tier fee (lines A-D)
  • Larger, multi-unit, or commercial charger installations use the Commercial Electrical Permit's valuation-based tiers

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Single-family interior/exterior wire or rewire -- 1 additional circuit or piece of equipment (applies to a single EV charger circuit added to an existing home)Montana Building Codes Bureau, Application for Residential Electrical Permit, line H (Rev. 11/25) -- same category used for a hot tub or A/C circuit; no dedicated EV/EVSE line item exists
$45
Commercial Electrical Permit -- valuation-based (for larger/commercial charger installs)Montana Building Codes Bureau, Application for Commercial Electrical Permit (Rev 6/24)
$45 for the 1st $500 plus 6% of balance ($0-$1,000); $75 for the 1st $1,000 plus 2% of balance ($1,001-$10,000); $255 for the 1st $10,000 plus 0.5% of balance ($10,001-$50,000); $455 for the 1st $50,000 plus 0.3% of balance ($50,001+)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Hardin?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    Tips

    • Hardin has no EV-specific permit or fee -- since the City is not electrically certified, any charger install is a STATE electrical permit through the Building Codes Bureau in Helena, not the City.
    • A single charger circuit added to an existing home is priced the same as adding a hot tub or A/C circuit ($45 flat) -- do not check the 'Alternative Energy Source' box, which is for Solar/Wind/Hydro generation only.
    • Mail applications and payment to PO Box 200517, Helena, MT 59620-0517, or apply online at aca-prod.accela.com/bcb.

    Frequently asked questions

    Hardin requires an ev charger / evse permit for: Electrical permit issued by the Montana DLI Building Codes Bureau (Helena), not the City of Hardin, per Title 50, Chapter 60, Section 604 MCA and ARM 24.301.431; No EV/EVSE-specific line item exists on the state's Residential or Commercial Electrical Permit application -- do NOT check the 'Alternative Energy Source' box, which is scoped to Solar/Wind/Hydro generation systems, not EV charging; A single charger circuit added to an existing single-family home falls under line H, '1 additional circuit or piece of equipment'; New-construction wiring for a charger circuit is included in the applicable new-dwelling amperage-tier fee (lines A-D); Larger, multi-unit, or commercial charger installations use the Commercial Electrical Permit's valuation-based tiers. If your project isn't listed, confirm with City of Hardin Building & Code Department — Building Inspectors Joe Connelly and Nathan McConnell; city-certified for Building (B), RESIDENTIAL ONLY. Commercial building permits, and Electrical, Plumbing, and Mechanical/HVAC permits of ANY project type, within Hardin city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at (406) 665-9260 Ext. 106 before starting work.

    In Hardin, the published Single-family interior/exterior wire or rewire -- 1 additional circuit or piece of equipment (applies to a single EV charger circuit added to an existing home) is: $45. Additional published fees: Commercial Electrical Permit -- valuation-based (for larger/commercial charger installs) — $45 for the 1st $500 plus 6% of balance ($0-$1,000); $75 for the 1st $1,000 plus 2% of balance ($1,001-$10,000); $255 for the 1st $10,000 plus 0.5% of balance ($10,001-$50,000); $455 for the 1st $50,000 plus 0.3% of balance ($50,001+). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    Hardin does not publish a plan-review timeline for this permit. Contact City of Hardin Building & Code Department — Building Inspectors Joe Connelly and Nathan McConnell; city-certified for Building (B), RESIDENTIAL ONLY. Commercial building permits, and Electrical, Plumbing, and Mechanical/HVAC permits of ANY project type, within Hardin city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at (406) 665-9260 Ext. 106 for current turnaround.

    You'll need: Application for Residential Electrical Permit (or Commercial Electrical Permit for larger projects). See the required-documents checklist on this page for details on each.

    Apply through City of Hardin Building & Code Department — Building Inspectors Joe Connelly and Nathan McConnell; city-certified for Building (B), RESIDENTIAL ONLY. Commercial building permits, and Electrical, Plumbing, and Mechanical/HVAC permits of ANY project type, within Hardin city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at 406 N. Cheyenne Ave, Hardin, MT 59034. Phone: (406) 665-9260 Ext. 106, email: jconnelly@hardinmt.com. Office hours: City Administrative Office, 406 N. Cheyenne Ave, Hardin, MT 59034. For Building Inspector questions call (406) 665-9260 Ext. 106 — Joe Connelly (jconnelly@hardinmt.com) or Nathan McConnell (nmcconnell@hardinmt.com). Applications may also be submitted online via the City of Hardin Citizen Portal (hardinmt2.portal.iworq.net).. Official information: http://www.hardinmt.com/Permits-Forms.html.

    Hardin, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code; non-certified trades — and, where a city's Building certification is itself partial (e.g. residential-only), non-certified project types — fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs (bsd.dli.mt.gov/building-codes-permits).; Hardin is a Montana DLI-certified jurisdiction for Building (B), RESIDENTIAL ONLY, within city limits; certified official on file with DLI: Joseph Connolly (listed on City of Hardin's own site as 'Joe Connelly'), (406) 665-9264. Verified directly against the DLI Building Codes Bureau's 'Montana Certified Local Government Program' roster PDF, updated 04/22/2026 (fetched and text-extracted directly from the source PDF): 'Hardin | B (residential only) | Joseph Connolly | 665-9264 | City Limits'. This is a NARROWER certification than the B-only-but-all-project-types pattern seen in Choteau/Conrad/Cut Bank/Glasgow/Lewistown/Red Lodge — Hardin's own certification does not cover COMMERCIAL building work at all, meaning commercial building permits in Hardin route to the state DLI Building Codes Bureau exactly as they would in a non-certified jurisdiction, in addition to Electrical/Plumbing/Mechanical for all project types. Source: https://bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf; Hardin, MT Code of Ordinances, Title 4 Building Regulations, Chapter 1 Building Codes (current through Ord. 2025-04, passed 12-4-2025) contains three sections: 4-1-1 Adoption Of Codes And Regulations, 4-1-2 Building Code Adopted, and 4-1-3 Other Codes Enforced By State Officials — a notably thin chapter (no locally-authored fee schedule or plan-review-timeline section), consistent with a small, partially-certified jurisdiction that enforces state-adopted code editions rather than authoring independent code text or a distinct administrative process. Section 4-1-3's title ('Other Codes Enforced By State Officials') is itself corroborating evidence of the residential-only/state-routed-commercial split described by the DLI roster. Source: https://codelibrary.amlegal.com/codes/hardinmt/latest/hardin_mt/0-0-0-994; Per the Montana DLI Building Codes Bureau's Current Codes page (statewide effective date June 11, 2022, applicable uniformly to all certified and state-enforced jurisdictions): 2021 IBC, 2021 IRC, 2021 IEBC, 2021 IMC, 2021 IFGC, 2021 IECC, 2021 ISPSC, 2021 UPC, 2020 NEC, 2017 ICC A117.1 Accessibility. Hardin's own Building Permit Application form cites Title 50, Chapter 60, Section 104, MCA and ARM 24.301.131 (the same statutory/administrative basis as the state's own BCP-1 form), consistent with a residential-certified jurisdiction enforcing the state-adopted editions without independently amended local code text. Source: bsd.dli.mt.gov/building-codes-permits/current-codes; City of Hardin Building Permit Application PDF (hardinmontana.info/Building_Permit_application011019.pdf). Local amendments apply — see the Hardin overview page for the full list.

    The Montana Department of Labor & Industry Building Codes Bureau issues electrical permits for Hardin -- the city holds no Electrical certification. There is no EV/EVSE-specific permit; a single charger circuit added to an existing home is billed under the state's '1 additional circuit or piece of equipment' line ($45).