Electric Vehicle Charging Station Permit (via Town Electrical Permit) — Darby, Montana · Requirements sheet
Verified 2026-07-20 · Source: https://www.darbymt.net/a/wp-content/uploads/2022/03/Electrical_Permit_Application_2021-TOD.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle Charging Station Permit (via Town Electrical Permit) in Darby, Montana
Darby is a Montana DLI-certified jurisdiction for Electrical permitting (effective September 16, 2021) and self-administers electrical permits directly rather than routing to the state -- the same mechanism documented in this file's electrical-permit and solar-pv-permit entries. The Town's own Electrical Permit Application (2021), the same form and valuation-based fee table used for all electrical work in Darby, does not contain a distinct EV charger/EVSE line item or checkbox; an EV charger installation is therefore billed under the Town's general valuation-based Electrical Permit, with no separate EV-specific permit or fee. Re-chased 2026-07-20: directly re-fetched and confirmed the Town's live Electrical Permit Application PDF still hosts this exact same fee table verbatim, so it remains the real, currently-effective governing figure for this permit.
Verified 2026-07-20 · Source
When you need this permit
- Complete the Town of Darby Electrical Permit Application for the charger circuit/installation work, submitted in person at Town Hall or electronically
- Contractor license number and master/journeyman license number required on the application Contractor
- No EV-charger-specific line item exists on the Town's own Electrical Permit Application form, confirmed by direct review of the PDF; the installation is declared and billed at its construction valuation like any other electrical work
- For a Level 3 or commercial-scale charger requiring a new structure (e.g., a canopy), a separate Town of Darby Residential/Commercial Building Permit would additionally apply for that structural portion, since Darby holds full local Building certification
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
New circuit/conduit for the charger before covering/energizing (if applicable)
- 2
Final
Charger installed and connected, circuit verified before energizing
Tips
- Darby's own Electrical Permit Application form (2021) has no EV charger/EVSE-specific checkbox or fee line -- an EV charger installation is filed and billed as standard electrical work under the same valuation-based fee table used for any other electrical project in town.
- Because Darby holds full local Building certification (unlike most small Montana towns, which route electrical work to the state), the Electrical Permit for an EV charger is issued directly by the Town, not the state DLI Building Codes Bureau.
- Confirm with Darby's contracted building inspector (Construct Montana, LLC, (406) 552-3238) whether an EV charger installation also needs a Building Permit for any structural component (e.g., a mounting canopy).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Darby building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Darby
Electric Vehicle Charging Station Permit (via Town Electrical Permit) in other cities
Compare electric vehicle charging station permit (via town electrical permit) fees across Montana →
Look up this fee in a different city →
Related guides
Now live
Build your Darby project checklist
Describe your project once and get every permit, document, and fee it triggers in Darby — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →