Electric Vehicle (EV) Charging Station / EVSE Permit (State Electrical Permit) — Unincorporated Yellowstone County, Montana · Requirements sheet
Verified 2026-07-20 · Source: https://bsd.dli.mt.gov/building-codes-permits/permit-applications/electrical-permits/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charging Station / EVSE Permit (State Electrical Permit) in Unincorporated Yellowstone County, Montana
Unincorporated Yellowstone County has no county-run electrical program and no dedicated EV charger/EVSE permit or fee line. All electrical work, including EV charging station/EVSE circuit installation, requires a State Electrical Permit from the Montana Building Codes Bureau (Title 50, Chapter 60, Section 604, MCA), the same statewide program used for the county's general electrical-permit entry, since Yellowstone County is not a certified local government for electrical code enforcement. The Bureau's Application for Residential/Homeowner Electrical Permit fee schedule (ARM 24.301.431) was checked directly and contains no distinct 'electric vehicle,' 'EV charger,' 'EVSE,' or 'charging station' line item; an EVSE circuit addition would be billed under an existing general-purpose fee category -- most likely 'Alternative Energy connection (residential change of service)' ($45) if tied to a service change, or the '1 additional circuit or piece of equipment' ($45) / '2-3 additional circuits or pieces of equipment' ($70) categories for a standalone dedicated circuit -- depending on project scope.
Verified 2026-07-20 · Source
When you need this permit
- No standalone EV charger/EVSE permit application exists; apply for a State Electrical Permit (Residential or Homeowner) from the Montana Building Codes Bureau, the same permit used for all other electrical work in unincorporated Yellowstone County
- Homeowners may self-perform the EVSE circuit wiring on their own home/garage/premises via a Homeowner Electrical Permit; otherwise a Montana-licensed electrical contractor (UCO or LCO license) must pull the permit Owner-builder
- The Bureau's numeric fee schedule (ARM 24.301.431) has no EV-specific line item; the applicable fee category depends on project scope -- a new dedicated circuit/piece of equipment, a service change, or an alternative-energy-style connection
- Governed by the 2020 NEC (effective June 11, 2022, with Technical Advisory NEC_TIA-23-3_210.8), which includes NEC Article 625 (Electric Vehicle Power Transfer System) provisions for EVSE circuits and disconnects
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Electrical permit holders must call for rough-in inspection and give 48 hours' notice before covering up the EVSE circuit work
- 2
Final
Final inspection by a State Electrical Inspector; wiring must meet 2020 NEC requirements including Article 625 (Electric Vehicle Power Transfer System)
See the full Unincorporated Yellowstone County inspection guide — scheduling & re-inspection fees →
Tips
- Do not look for a county EV charger permit or a county electrical inspector -- unincorporated Yellowstone County electrical work, including EV charging stations, is permitted and inspected by the Montana Building Codes Bureau's statewide State Electrical Permit program, the same one used for all other electrical work here.
- There is no dedicated EV/EVSE fee line on the state's fee schedule -- the closest matching categories are the 'additional circuit or piece of equipment' fees ($45-$70) or the 'Alternative Energy connection' fee ($45) if paired with a service change; confirm which applies with the Building Codes Bureau (406-841-2056) before applying.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Yellowstone County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Yellowstone County
Electric Vehicle (EV) Charging Station / EVSE Permit (State Electrical Permit) in other cities
Look up this fee in a different city →
Related guides
Now live
Build your Unincorporated Yellowstone County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Yellowstone County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →