Las Vegas building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Las Vegas, Nevada.
Verified 2026-07-16 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- First Floor Lobby, City Hall, 495 S. Main St., Las Vegas, NV 89101
- Phone
- (702) 229-6251
- Office hours
- Mon–Thu 7:00 AM – 5:30 PM, Fri 7:00 AM – 11:30 AM (closed holidays)
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit — New Construction (Custom Single-Family)
- 1
Footing / Foundation Inspection
Required before concrete pour; verifies footing dimensions, rebar, and grade compliance
- 2
Framing Inspection
Required when framing is complete and before insulation or drywall is installed
- 3
Insulation Inspection
Required after insulation is installed, before drywall
- 4
Drywall / Sheathing Inspection
Required before taping and texturing
- 5
Final Inspection
Required upon completion; all systems must be operational; Certificate of Occupancy issued upon approval
Applies to: Accessory Dwelling Unit (ADU / Guest House — Class I Accessory Structure)
- 1
Foundation Inspection
Required before concrete pour
- 2
Framing Inspection
Required when framing complete, before insulation
- 3
Final Inspection
Required upon completion; Certificate of Occupancy or equivalent issued
Applies to: Commercial Tenant Improvement (TI)
- 1
Framing / Rough-In Inspection
Required when new framing and rough-in of systems are complete, before drywall
- 2
Fire Sprinkler / Alarm Inspection
Required if fire suppression or alarm systems are installed or modified
- 3
Final Inspection / Certificate of Occupancy
Required upon completion; new Certificate of Occupancy required if use or occupancy changes
Applies to: Fire Sprinkler System Permit (NFPA 13 / 13R / 13D)
- 1
Underground / Rough-In Inspection
Required before piping is concealed; verifies pipe sizing, hangers, and rough sprinkler head layout against approved plans
- 2
Hydrostatic Test
Required pressure test of sprinkler piping per NFPA 13/13R/13D before concealment or final acceptance
- 3
Final Acceptance Test
Required final flow/functional test of the completed system, witnessed by Fire Prevention/Inspections, before the system is placed in service
Applies to: Swimming Pool / Spa Permit
- 1
Pre-Gunite / Shell Inspection
Required before concrete or shell is placed; verifies rebar, plumbing rough-in, bonding
- 2
Deck / Equipment Inspection
Required when deck and equipment are installed
- 3
Final Pool Inspection
Required before pool is filled; verifies barrier, fencing, bonding, and equipment operation
Applies to: Block / Screen Wall Permit
- 1
Footing Inspection
Required for masonry block walls before concrete footing is poured
- 2
Final Wall Inspection
Required when wall or fence construction is complete
Applies to: Demolition Permit
- 1
Pre-Demolition Site Inspection
Inspector verifies utility disconnection and site conditions before demolition begins
- 2
Final Site Inspection
Required after demolition is complete to confirm site is cleared and graded properly
Applies to: Electrical Permit
- 1
Rough Electrical Inspection
Required before walls are closed; verifies wiring, boxes, and panel rough-in
- 2
Final Electrical Inspection
Required when all devices, fixtures, and connections are complete
Applies to: Fire Alarm System Permit
- 1
Rough-In Inspection
Required before devices, wiring, and conduit are concealed; verifies device placement and wiring against approved plans
- 2
Final Acceptance / Functional Test
Required final test of all initiating and notification devices, panel programming, and (if applicable) central station reporting, witnessed by Fire Prevention/Inspections
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical Inspection
Required before duct systems are concealed
- 2
Final Mechanical Inspection
Required when all HVAC equipment and ductwork is installed and operational
Applies to: Plumbing Permit
- 1
Rough Plumbing Inspection
Required before walls are closed; verifies supply and drainage rough-in
- 2
Final Plumbing Inspection
Required when all fixtures and connections are complete
Applies to: Residential Addition / Remodel
- 1
Framing Inspection
Required when framing is complete and before insulation or drywall
- 2
Final Inspection
Required upon completion of addition/remodel
Applies to: Rooftop Solar PV Permit
- 1
Rough Electrical Inspection
Required before conduit and wiring are concealed
- 2
Final Inspection
Required when system is fully installed; must be approved before utility energization
Applies to: Sign Permit
- 1
Sign Placement / Structural Inspection
Required before final approval; verifies footing (for pole and monument signs), attachment, and placement match approved plans
- 2
Electrical Inspection
Required for illuminated signs with a new electrical power supply, in addition to the separate electrical permit's own rough and final inspections
Sources & verification
Verified against official sources. Last reviewed 2026-07-16.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Las Vegas building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Las Vegas building permits
Get alerts for Las Vegas
We'll email you when Las Vegas's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.