Electrical Permit in Las Vegas, Nevada

Required for all new electrical service installations, panel upgrades, service change-outs, wiring work, and rooftop solar PV systems. Governed by the 2023 National Electrical Code (NEC) with local amendments.

Verified 2026-06-30 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Panel same-for-same change-out (no upgrade)$96 inspection only (no plan check required)Over-the-counter permit; from City of Las Vegas Permit Fee Estimator — Electrical
Service change / upgrade$97 inspection + $102 plan check = $199 total (plus $55 admin)From City of Las Vegas Permit Fee Estimator — Electrical
New service up to 1,000A$140 inspection + $102 plan check = $242 total (plus $55 admin)From City of Las Vegas Permit Fee Estimator — Electrical
Minor electrical work (fewer than 5 devices/circuits)$64 inspection + $102 plan check = $166 total (plus $55 admin)From City of Las Vegas Permit Fee Estimator — Electrical

Review timeline

~15 business days

Typical estimate — confirm current times with the Las Vegas building department

Inspection process

  1. 1

    Rough Electrical Inspection

    Required before walls are closed; verifies wiring, boxes, and panel rough-in

  2. 2

    Final Electrical Inspection

    Required when all devices, fixtures, and connections are complete

Tips

Frequently asked questions

What NEC edition does Las Vegas enforce?
The 2023 National Electrical Code (NEC) with City of Las Vegas local amendments, effective January 5, 2026.

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Las Vegas building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Las Vegas

Related guides

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.