Fire Sprinkler System Permit (NFPA 13 / 13R / 13D) in Las Vegas, Nevada

Required for installation, alteration, or extension of automatic fire sprinkler systems -- commercial NFPA 13, residential NFPA 13R (up to 4 stories), and NFPA 13D one- and two-family dwelling systems -- in the City of Las Vegas. Issued by Las Vegas Fire & Rescue (LVF&R) Fire Prevention Division, Fire Engineering section, separate from the Department of Building & Safety's structural/building permit. Governed by the 2024 International Fire Code with Southern Nevada and City of Las Vegas amendments (Ordinance #6918), effective January 5, 2026.

Verified 2026-07-22 · Source

When you need this permit

  • Fire permit required for all new, altered, or extended automatic fire sprinkler systems under NFPA 13 (commercial), NFPA 13R (residential up to 4 stories), or NFPA 13D (one- and two-family dwellings)
  • Submitted through the City's Citizen Portal to Fire Engineering prior to installation; contractor must hold an appropriate Nevada State Contractors Board fire protection license and class
  • Full plans with hydraulic calculations required above the letter-submittal threshold; a simplified letter submittal is allowed for NFPA 13/13R systems with 5 heads or less, or a standardized NFPA 13D residential tract system
  • Must comply with the 2024 International Fire Code and Southern Nevada amendments (City of Las Vegas Ordinance #6918), effective January 5, 2026
  • An incomplete initial submittal requires a new, clean resubmittal rather than marked-up corrections to the original

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

NFPA 13 / 13R System -- up to 200 heads, including 1 hydraulic calculationLas Vegas Fire & Rescue Fire Engineering Fee Schedule, adopted under Ordinance #6769 effective July 1, 2021 (current schedule re-confirmed live 2026-07-22 at files.lasvegasnevada.gov/fire-rescue/2024/Fire-Engineering-Fee-Schedule.pdf); plus each additional head $1.00/head and each additional hydraulic calculation $110.00
$148.00
NFPA 13 / 13R -- Letter submittal (5 heads or less), each address/unitLas Vegas Fire & Rescue Fire Engineering Fee Schedule
$93.00
NFPA 13D System (one/two-family) -- up to 200 heads, including 1 hydraulic calculationLas Vegas Fire & Rescue Fire Engineering Fee Schedule; plus each additional head $1.00/head and each additional hydraulic calculation $110.00
$137.00
NFPA 13D -- Letter for Standardized Residential Tract Home Fire Sprinkler System, eachLas Vegas Fire & Rescue Fire Engineering Fee Schedule
$137.00
Permit Issuance / Administrative Fee, per permitApplied to every Fire Engineering permit
$55.00
Over The Counter (OTC) Review, per permitOptional expedited review; 3 business days; Monday-Thursday only
$117.00 additional
Overtime (OT) ReviewOptional expedited review; does not guarantee same-day approval
$220.00/hour, 1-hour minimum, per review & per permit
Demo work only (plans or letter), each address/unitLas Vegas Fire & Rescue Fire Engineering Fee Schedule
$80.00

Review timeline

Plan reviewLas Vegas’s published plan-review target
14–21 business days

How long did your Fire Sprinkler System Permit (NFPA 13 / 13R / 13D) permit actually take in Las Vegas?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underground / Rough-In Inspection

    Required before piping is concealed; verifies pipe sizing, hangers, and rough sprinkler head layout against approved plans

  2. 2

    Hydrostatic Test

    Required pressure test of sprinkler piping per NFPA 13/13R/13D before concealment or final acceptance

  3. 3

    Final Acceptance Test

    Required final flow/functional test of the completed system, witnessed by Fire Prevention/Inspections, before the system is placed in service

See the full Las Vegas inspection guide — scheduling & re-inspection fees →

Tips

  • A simplified 'letter' submittal (no hydraulic calculations required) is available for NFPA 13/13R systems with 5 heads or less, or a standardized NFPA 13D residential tract system -- faster and cheaper than a full plan submittal.
  • Fire Engineering's standard queue runs about 2-3 weeks; Over-The-Counter (OTC) review is available Monday-Thursday for eligible small-scope projects (3 business days, additional $117), and Overtime (OT) expedited review is $220/hour with a 1-hour minimum but does not guarantee same-day approval.
  • Submittals deemed incomplete require a brand-new, clean resubmittal rather than marked-up corrections to the original.

Frequently asked questions

Las Vegas requires a fire sprinkler system permit (nfpa 13 / 13r / 13d) for: Fire permit required for all new, altered, or extended automatic fire sprinkler systems under NFPA 13 (commercial), NFPA 13R (residential up to 4 stories), or NFPA 13D (one- and two-family dwellings); Submitted through the City's Citizen Portal to Fire Engineering prior to installation; contractor must hold an appropriate Nevada State Contractors Board fire protection license and class; Full plans with hydraulic calculations required above the letter-submittal threshold; a simplified letter submittal is allowed for NFPA 13/13R systems with 5 heads or less, or a standardized NFPA 13D residential tract system; Must comply with the 2024 International Fire Code and Southern Nevada amendments (City of Las Vegas Ordinance #6918), effective January 5, 2026; An incomplete initial submittal requires a new, clean resubmittal rather than marked-up corrections to the original. If your project isn't listed, confirm with City of Las Vegas Building & Safety (Community Development Department) at (702) 229-6251 before starting work.

In Las Vegas, the published NFPA 13 / 13R System -- up to 200 heads, including 1 hydraulic calculation is: $148.00. Additional published fees: NFPA 13 / 13R -- Letter submittal (5 heads or less), each address/unit — $93.00; NFPA 13D System (one/two-family) -- up to 200 heads, including 1 hydraulic calculation — $137.00; NFPA 13D -- Letter for Standardized Residential Tract Home Fire Sprinkler System, each — $137.00; Permit Issuance / Administrative Fee, per permit — $55.00; Over The Counter (OTC) Review, per permit — $117.00 additional; Overtime (OT) Review — $220.00/hour, 1-hour minimum, per review & per permit; Demo work only (plans or letter), each address/unit — $80.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Las Vegas's published plan-review target for a fire sprinkler system permit (nfpa 13 / 13r / 13d) is 14–21 business days.

You'll need: Fire Permit Application (Las Vegas Fire & Rescue, Fire Engineering); Fire Sprinkler Plans and Hydraulic Calculations; NV State Contractor License / Fire Marshal MC#. See the required-documents checklist on this page for details on each.

Las Vegas requires 3 inspection(s) for a fire sprinkler system permit (nfpa 13 / 13r / 13d), in order: Underground / Rough-In Inspection, Hydrostatic Test, Final Acceptance Test. Schedule each through City of Las Vegas Building & Safety (Community Development Department) ((702) 229-6251).

Apply through City of Las Vegas Building & Safety (Community Development Department) at First Floor Lobby, City Hall, 495 S. Main St., Las Vegas, NV 89101. Phone: (702) 229-6251, email: techs@lasvegasnevada.gov. Office hours: Mon–Thu 7:00 AM – 5:30 PM, Fri 7:00 AM – 11:30 AM (closed holidays). Official information: https://www.lasvegasnevada.gov/Business/Planning-Zoning/Building-Safety.

Yes. Fire sprinkler systems are permitted separately through Las Vegas Fire & Rescue's Fire Engineering section via the Citizen Portal, in addition to any Building & Safety structural/building permit for the project.

The standard Fire Engineering queue runs approximately 2-3 weeks. Eligible small-scope projects can use Over-The-Counter review (3 business days, additional $117 fee, Monday-Thursday only), or request Overtime expedited review at $220/hour (1-hour minimum), though OT does not guarantee same-day approval.

Sources & verification

Verified against official sources. Last reviewed 2026-07-22.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Las Vegas building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.