Required for installation or modification of automatic fire sprinkler systems in new and existing residential and commercial buildings in Reno. Fire Sprinkler is its own 'Plans Required, 10-day Review' permit category — distinct from Fire Alarm — listed under both the Residential and Commercial building permit types published by the City; commercial buildings with kitchen hoods or special-hazard suppression may additionally require the City's separate 'Fire Suppression' permit category. Plans are reviewed by both Development Services and the Reno Fire Department (RFD).

Reviewed 2026-07-22 · Source

When you need this permit

  • Fire Sprinkler is listed as its own 'Plans Required, 10-day Review' category under both Residential (One/Two-Family) and Commercial (incl. Apartments/Condos) permit types, per the City of Reno Building Permit Types document (06/01/2026)
  • Cover sheet must cite the specific applicable code editions and standards (e.g., a specific IFC/NNICC amendment year and specific NFPA edition) — RFD's published guidance states generic language such as 'all applicable codes' will place the plan on HOLD
  • RFD's published fire-alarm guidance states that Fire Alarm Plans AND Fire Suppression System Plans require a minimum Level II NICET stamp or a Nevada-licensed Professional Engineer stamp (NAC 477.300) from the submitting company; confirm directly with RFD Fire Prevention whether this applies to standard water-based sprinkler system plans specifically, since RFD's own document text names 'Fire Suppression System Plans' rather than 'Fire Sprinkler' by that exact term
  • Systems must be installed by a licensed contractor; stamps must be current Contractor
  • Apply via onenv.us; a separate hourly Fire Inspection Fee applies to Reno Fire Department plan review/inspection

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation-basedCity of Reno FY27 Valuation Based Permit Fee Schedule
Varies — no separate published Fire Sprinkler-specific fee schedule was located; billed under the same valuation-based Building Permit Fee Table used for other plans-required permits
Application Fee
$45.00
Plan Review Fee
65% of the Building Permit Fee
Permit Issuance Fee
$45.00
Fire Inspection Fee (hourly)City of Reno FY27 EZ Permits, Misc Fees, Admin Fees, Permit Revisions, Building Compliance Fees Schedule
$135.00 per hour

Review timeline

Plan reviewTypical estimate — confirm current times with the Reno building department
~10–30 business days

How long did your Fire Sprinkler Permit permit actually take in Reno?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underground / Rough-In

    Piping, hangers, and riser installation before concealment

  2. 2

    Fire Flow / Acceptance Test

    System flow test witnessed by Reno Fire Department; verify against approved hydraulic calculations

  3. 3

    Final

    All work complete per approved plans, RFD sign-off obtained

See the full Reno inspection guide — scheduling & re-inspection fees →

Tips

  • RFD's published guidance requires cover sheets to cite exact code editions and standard years — generic 'all applicable codes' language will place the plan on HOLD.
  • Commercial kitchen hood or special-hazard suppression is a separate 'Fire Suppression' permit category in Reno's Building Permit Types list — do not assume it is covered under the Fire Sprinkler permit.
  • A $135.00/hour Fire Inspection Fee applies in addition to the standard valuation-based permit fees.
  • No dedicated Fire Sprinkler fee schedule (comparable to the Sign Permit schedule) was found — confirm the exact fee breakdown with Permit Services at project intake.

Frequently asked questions

Reno requires a fire sprinkler permit for: Fire Sprinkler is listed as its own 'Plans Required, 10-day Review' category under both Residential (One/Two-Family) and Commercial (incl. Apartments/Condos) permit types, per the City of Reno Building Permit Types document (06/01/2026); Cover sheet must cite the specific applicable code editions and standards (e.g., a specific IFC/NNICC amendment year and specific NFPA edition) — RFD's published guidance states generic language such as 'all applicable codes' will place the plan on HOLD; RFD's published fire-alarm guidance states that Fire Alarm Plans AND Fire Suppression System Plans require a minimum Level II NICET stamp or a Nevada-licensed Professional Engineer stamp (NAC 477.300) from the submitting company; confirm directly with RFD Fire Prevention whether this applies to standard water-based sprinkler system plans specifically, since RFD's own document text names 'Fire Suppression System Plans' rather than 'Fire Sprinkler' by that exact term; Systems must be installed by a licensed contractor; stamps must be current; Apply via onenv.us; a separate hourly Fire Inspection Fee applies to Reno Fire Department plan review/inspection. If your project isn't listed, confirm with City of Reno Development Services — Building and Safety Division at (775) 334-2063 before starting work.

In Reno, the published Building Permit Fee — valuation-based is: Varies — no separate published Fire Sprinkler-specific fee schedule was located; billed under the same valuation-based Building Permit Fee Table used for other plans-required permits. Additional published fees: Application Fee — $45.00; Plan Review Fee — 65% of the Building Permit Fee; Permit Issuance Fee — $45.00; Fire Inspection Fee (hourly) — $135.00 per hour. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for a fire sprinkler permit in Reno typically runs 10–30 business days. This is an estimate, not a published figure — confirm current review times with City of Reno Development Services — Building and Safety Division at (775) 334-2063.

You'll need: Fire Sprinkler Permit Application (via onenv.us); Fire Sprinkler System Plans / Hydraulic Calculations. See the required-documents checklist on this page for details on each.

Reno requires 3 inspection(s) for a fire sprinkler permit, in order: Underground / Rough-In, Fire Flow / Acceptance Test, Final. Schedule each through City of Reno Development Services — Building and Safety Division ((775) 334-2063).

Apply through City of Reno Development Services — Building and Safety Division at 1 E. 1st Street, Reno, NV 89505. Phone: (775) 334-2063, email: permits@reno.gov. Office hours: Mon–Fri (contact department for current hours). Official information: https://www.reno.gov/business-development/development-services/building-permits.php.

Reno, Nevada has adopted: 2024 International Building Code (IBC) — with 2024 Northern Nevada ICC Amendments (NNICC); effective July 1, 2025; 2024 International Residential Code (IRC) — with 2024 Northern Nevada ICC Amendments; effective July 1, 2025; 2024 International Existing Building Code (IEBC) — with 2024 Northern Nevada ICC Amendments; 2024 International Energy Conservation Code (IECC) — with 2024 Northern Nevada ICC Amendments; 2024 International Fuel Gas Code (IFGC) — with 2024 Northern Nevada ICC Amendments; 2024 International Mechanical Code (IMC) — with 2024 Northern Nevada ICC Amendments (commercial/multi-family); 2024 Uniform Mechanical Code (UMC) — with 2024 Northern Nevada ICC Amendments (residential single-family); 2024 Uniform Plumbing Code (UPC) — with 2024 Northern Nevada ICC Amendments (NOTE: Reno uses UPC, not IPC); 2023 National Electrical Code (NEC) — with 2024 Northern Nevada ICC Amendments; effective July 1, 2025; Nevada Blue Book (2020) — statewide construction industry reference, incorporates NRS/NAC provisions. Local amendments apply — see the Reno overview page for the full list.

Yes. The City of Reno's Building Permit Types document lists 'Fire Sprinkler' as its own Plans-Required permit category (10-day review target) for both residential and commercial buildings, reviewed by both Development Services and the Reno Fire Department.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-22.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Reno building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.