Solar PV Permit in Reno, Nevada
Required for installation of rooftop or ground-mounted solar photovoltaic systems on residential and commercial properties in Reno. Processed as a valuation-based permit (Solar PV Systems) requiring plans including structural calculations, electrical design, and equipment specifications.
Verified 2026-06-30 · Source
When you need this permit
- Rooftop solar panel installation — single-family and multi-family
- Ground-mounted solar array installation
- Battery storage system installation associated with solar
- Valuation-based permit — both plan review and inspection fees apply
- Licensed electrical contractor or journeyman required on site for inspections (Reno Ordinance No. 6400)
- Structural calculations required (roof load analysis including snow 29 psf min and seismic SDC D2)
- Electrical single-line diagram and load calculations required
- Plans must be stamped by engineer of record
Required documents
- Req
Solar Permit Application (via onenv.us)
Apply as 'Solar (PV Systems)' permit type via ONE Regional portal
- Req
Solar Permit Guidelines (Jul 1, 2025)
Reno's current plan and submittal requirements for solar PV systems
- Req
Site Plan
Shows property lines, existing structures, location/layout of proposed modules, required fire access and pathways — CADD/line drawing required
- Req
Framing Details
Solar racking connections to the roof system; structural plans stamped by engineer
- Req
Electrical Plan
Wire type/sizing, ampacity, de-rating, load calculations; 3-line diagram; min/max overcurrent protection; location of all equipment including AC disconnect
- Req
Structural Calculations
For existing roof structure — stamped verification letter from engineer indicating adequacy (or required modifications); must include seismic (D2), wind (120 mph Vult), and snow (29 psf minimum) design criteria
- Req
Equipment Specifications
Manufacturer spec sheets for all equipment (panels, inverter, racking, battery if applicable)
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Application Fee | $45.00 | City of Reno FY26/27 Valuation Based Permit fee structure |
| Building Permit Fee (Inspection) — valuation-based | Varies — valuation-based per Permit Fee Table (construction cost of solar system) | City of Reno FY27 Valuation Based Permit Types: 'Solar (PV Systems) — Single Family Roof Top Mounted' is listed as a valuation-based residential permit |
| Plan Review Fee | 65% of the Building Permit Fee | — |
| Permit Issuance Fee | $45.00 | — |
Review timeline
~10–20 business days
Typical estimate — confirm current times with the Reno building department
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement — before walls or ceiling cover
- 2
Final — Structural / Racking
Panel mounting, racking attachment, roof penetration sealing verified
- 3
Final — Electrical
All connections, inverter, and interconnection point verified; licensed contractor/journeyman must be on site
Tips
- Reno's solar permit is valuation-based — fees depend on the total cost of the solar system installation.
- Structural calculations must account for Reno's 29 psf minimum roof snow load, SDC D2 seismic, and 120 mph Vult wind speed — these are notable for Northern Nevada.
- De-rated main service panels must have a permanently applied label indicating the new rating; electrical load calculations are required for all de-rated panels.
- NV Energy (NV Energy.com) is the utility for interconnection approval in Reno.
- The 2024 NEC (with NNICC amendments) contains specific NEC Article 690 solar requirements, including DC PV circuit marking requirements.
Frequently asked questions
- How much does a solar permit cost in Reno?
- Reno processes solar PV systems as a valuation-based permit, so the exact fee depends on the construction cost of the installation. You pay an application fee ($45.00), a permit fee based on valuation using the Permit Fee Table, a plan review fee (65% of permit fee), and a permit issuance fee ($45.00).
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
- City of Reno Development Services — Building and Safety Division — official building department
- City of Reno Solar Permit Guidelines (Jul 1, 2025)
- City of Reno FY27 Valuation Based Permit Fee Schedule
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Reno building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Reno
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.