Demolition Permit in Reno, Nevada
Required for demolition of structures in Reno. Requires a demolition bond of $2,500. A Demolition Checklist and Bond Agreement form must be submitted with the application.
Verified 2026-06-30 · Source
When you need this permit
- Demolition bond of $2,500 required
- Submit Demolition Checklist and Bond Agreement (available at reno.gov building permits page)
- Utility disconnects (gas, electric, water, sewer) must be verified or arranged prior to demolition
- Structure demolition permit (plans required, 10-day review) — NOT an EZ permit
- Interior-only commercial demolition is an EZ permit
- Apply via onenv.us
Required documents
- Req
Demolition Checklist and Bond Agreement
Required form listing utility disconnects, asbestos abatement documentation, and bond agreement
- Req
Demolition Permit Application (via onenv.us)
Online application through ONE Regional portal
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Permit (flat rate, includes $2,500 bond requirement) | $287.00 (includes application and permit issuance fees) | City of Reno FY27 Flat Rate Permit Types — both Residential and Commercial demolition are $287.00 flat rate |
| Bond | $2,500 required | Demolition bond ($2,500) required per Reno permit requirements — returned after cleanup completion |
Review timeline
~10–15 business days
Typical estimate — confirm current times with the Reno building department
Inspection process
- 1
Pre-Demolition Utilities Verification
Verification that gas, electric, water, and sewer are disconnected before demolition begins
- 2
Final
Site cleared and graded, all debris removed, utilities properly capped
Tips
- Demolition requires a $2,500 bond — plan for this upfront cost.
- The Demolition Checklist and Bond Agreement form is available on the Reno building permits page.
- Asbestos abatement documentation may be required for older structures — check with Northern Nevada Public Health (NNPH) before demolition.
- Commercial interior-only demolition is an EZ permit (no plans required) — different from full structure demolition.
Frequently asked questions
- How much does a demolition permit cost in Reno?
- The demolition permit flat fee is $287.00 (includes application and permit issuance fees). A $2,500 demolition bond is also required per the FY26/27 fee schedule.
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
- City of Reno Development Services — Building and Safety Division — official building department
- City of Reno FY27 Flat Rate Permit Fee Schedule — Demolition
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Reno building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Reno
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.