Mechanical / HVAC Permit in Las Vegas, Nevada

Required for installation, replacement, or alteration of heating, ventilation, and air conditioning systems. Governed by the 2024 Uniform Mechanical Code (UMC) — NOT the IMC.

Verified 2026-06-30 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
HVAC exact same-for-same change-out$100 inspection + $83 plan check = $183 total (plus $55 admin)From City of Las Vegas Permit Fee Estimator — Mechanical
Boilers / tankless water heaters$190 inspection + $102 plan check = $292 total (plus $55 admin)From City of Las Vegas Permit Fee Estimator — Mechanical

Review timeline

~15 business days

Typical estimate — confirm current times with the Las Vegas building department

Inspection process

  1. 1

    Rough Mechanical Inspection

    Required before duct systems are concealed

  2. 2

    Final Mechanical Inspection

    Required when all HVAC equipment and ductwork is installed and operational

Tips

Frequently asked questions

Is a permit required for a straight HVAC replacement?
Yes. Even a same-for-same HVAC change-out requires a mechanical permit in Las Vegas ($100 inspection + $83 plan check + $55 admin).

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Las Vegas building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Las Vegas

Related guides

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.