Residential Building Permit — New Construction (Custom Single-Family) in Las Vegas, Nevada

Required for all new single-family custom homes in the City of Las Vegas. Covers structural, framing, envelope, and all associated systems under 2024 IRC.

Verified 2026-06-30 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
New Single-Family Custom (Type VB) — 1,000 sq ft$1,488 total (Admin: $55 + Plans Check: $488 + Inspection: $945)Estimated from City of Las Vegas Permit Fee Estimator; final fees determined at application
New Single-Family Custom (Type VB) — 1,500 sq ft$1,961 totalEstimated from City of Las Vegas Permit Fee Estimator
New Single-Family Custom (Type VB) — 2,000 sq ft$2,432 total (Admin: $55 + Plans Check: $967 + Inspection: $1,410)Estimated from City of Las Vegas Permit Fee Estimator
New Single-Family Custom (Type VB) — 2,500 sq ft$2,904 totalEstimated from City of Las Vegas Permit Fee Estimator
New Single-Family Custom (Type VB) — 3,000 sq ft$3,250 totalEstimated from City of Las Vegas Permit Fee Estimator
New Single-Family Custom (Type VB) — 4,000 sq ft$3,943 total (Admin: $55 + Plans Check: $1,260 + Inspection: $2,628)Estimated from City of Las Vegas Permit Fee Estimator
Administration Fee (all permits)$55Flat fee applied to all building permits
Additional fees NOT included: Residential Construction Tax1% of construction valuation or $1,000 per dwelling unit (whichever is less) — effective Jan 1, 2024Habitable space only; separate from building permit fee
Additional fees NOT included: Clark County Transportation Tax$1,000 per single-family dwelling unitSeparate from building permit fee
Additional fees NOT included: Traffic Impact Fee$195 per single-family dwellingSeparate from building permit fee; exceptions may apply
Additional fees NOT included: Sewer Connection$3,235 per ERU (equivalent residential unit) — effective January 1, 2026Separate utility fee; not a building permit fee

Review timeline

1014 business days

Las Vegas’s published plan-review target

Inspection process

  1. 1

    Footing / Foundation Inspection

    Required before concrete pour; verifies footing dimensions, rebar, and grade compliance

  2. 2

    Framing Inspection

    Required when framing is complete and before insulation or drywall is installed

  3. 3

    Insulation Inspection

    Required after insulation is installed, before drywall

  4. 4

    Drywall / Sheathing Inspection

    Required before taping and texturing

  5. 5

    Final Inspection

    Required upon completion; all systems must be operational; Certificate of Occupancy issued upon approval

Tips

Frequently asked questions

Can I use the 2018 codes if I started my project before January 5, 2026?
Yes. Projects submitted before January 5, 2026 could elect to use 2018 or 2024 codes. All new submittals from January 5, 2026 forward must use 2024 codes per the City's Industry Notice on 2024 Code Adoption.
Does Las Vegas use IPC (International Plumbing Code) or UPC (Uniform Plumbing Code)?
Las Vegas uses the 2024 Uniform Plumbing Code (UPC), not the IPC. Similarly, Las Vegas uses the 2024 Uniform Mechanical Code (UMC), not the IMC. This is different from many other states.
What is the standard plan review timeline for new residential construction?
The City of Las Vegas Building & Safety publishes a 2-week standard for structural plan reviews (which includes new residential construction). Express Plan Review is available for an additional fee by appointment.

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Las Vegas building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Las Vegas

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.