Commercial Building Permit — Hobbs, New Mexico · Requirements sheet
Verified 2026-08-01 · Source: https://www.hobbsnm.gov/files/building/COH%20Comm%20const%20guide.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Hobbs, New Mexico
Required for new commercial construction, commercial additions, and commercial remodels/alterations in Hobbs and its 5-mile Extra-Territorial Jurisdiction (Municode 15.04.030(A)). Hobbs is NOT a CID-direct jurisdiction: although New Mexico's Construction Industries Division (CID) issues permits directly in uncertified localities, the City of Hobbs runs its own Building Inspection Department (a unit of Planning/Engineering) that issues commercial building permits locally as the AHJ, enforcing the statewide NMAC code set (2021 New Mexico Commercial Building Code, NMAC 14.7.2, based on the 2021 IBC) adopted by Municode 15.04.010. The process, plan-set standard, and inspections are set out in the City of Hobbs Commercial Construction Guide (Revised 06-10-24); fees are valuation-based per Municode 15.28.010 plus a 20% commercial plan-review fee.
Verified 2026-08-01 · Source
When you need this permit
- The licensed GB98 contractor requesting the permit must sign the City of Hobbs Building Permit Application, which must state description of work, building address, construction material, total square footage, specific use of building, project owner's name/address, contractor's business name/address/license number, and architect's name/address/license number (Commercial Construction Guide, Permit Application Data)
- Planning approval from the City of Hobbs Planning & Engineering Department is required BEFORE applying for a commercial building permit in most cases; the City's Design Review Team (DRT) of City-wide Division Directors meets Thursdays as a pre-conference forum for new commercial projects — call 575-391-8158 to get on the DRT agenda, or Planning & Engineering at 575-397-9232
- Two complete scaled sets of plans (1/4 inch = 1 foot minimum) and specifications, sufficiently clear to show the project in its entirety, following the Guide's 16-item minimum plan-set standard (cover sheet with IBC design criteria, site plan, foundation plan, floor plan, framing/roof framing plans, exterior elevations, building/wall sections, mechanical, plumbing, and electrical systems, structural calculations where required, and specifications); use the commercial checklist when preparing the submittal
- Cover sheet must annotate applicable codes and a design criteria list: IBC Chapter 6 construction type, square footage per floor and total, IBC Chapter 3 occupancy group (including mixed occupancies), IBC Chapter 10 Section 1004 occupant load, allowable area calculations, exiting requirements, IBC Chapter 29/UPC plumbing fixture counts, fire sprinklers, height and number of stories, land-use setbacks, location, and seismic location
- Signed contract between project owner and contractor required for valuation purposes (fees are based on total valuation including materials, labor, electrical, mechanical, and plumbing per Municode 15.28.010)
- 2021 NM Commercial Energy Conservation Code energy calculations must be submitted; software programs such as ComCheck are permitted (Guide, plan-submittal item 10)
- Fire sprinkler system plans are approved by the City of Hobbs Fire Marshal's Office within the same submittal (Guide, plan-submittal item 9)
- Accessibility per 2021 IBC Chapter 11 as amended by NMAC 14.7.2.19, with ICC/ANSI A117.1-2017 as the adopted standard; site plan must show all required parking including accessible parking, access aisles, and ramps per ANSI
- Commercial demolition and renovation: the NM Air Pollution Control Bureau (1-800-224-7009) must be notified 10 days in advance of any demolition or renovation of existing commercial structures for asbestos-containing-material handling (Commercial Construction Guide)
- Projects outside City limits but within the 5-mile ETJ require a Lea County Address & New Construction application approved by Lea County prior to permit issuance (City Building Safety & Permitting Services page)
- New commercial buildings must provision EV charging capacity for 1-5% of parking spaces depending on building use per the 2021 New Mexico Commercial Energy Conservation Code (14.7.9 NMAC) — see the ev-charger-permit entry
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation Inspection
After excavations for footings are complete and required reinforcing steel is in place; forms in place prior to inspection for concrete foundations; all foundation materials on the job except ready-mixed concrete
- 2
Concrete Slab or Under-Floor Inspection
After all in-slab or under-floor building service equipment, conduit, piping accessories, and ancillary equipment are in place, but before concrete is placed or floor sheathing (including subfloor) is installed
- 3
Frame Inspection
After the roof, all framing, fire blocking, and bracing are in place, all pipes/chimneys/vents complete, and rough electrical, plumbing, and heating are approved
- 4
Lath & Metal Fabric Inspection
- 5
Energy-Insulation Inspections
- 6
Special Inspections
As required for the project; the Construction Inspector may also make or require other inspections to ascertain compliance with the New Mexico Building Code (Guide, Other Inspections)
- 7
Gypsum Board Inspection
- 8
Weather-Resistive Barrier Inspection
After installation of the weather-resistive barrier and before it is covered
- 9
Final Inspection (Certificate of Occupancy)
After finish grading and the building is completed and ready for occupancy; final electrical, plumbing, and mechanical inspections must be conducted prior to the final general construction inspection. The City issues the Certificate of Occupancy to the contractor after approving final general construction inspections.
See the full Hobbs inspection guide — scheduling & re-inspection fees →
Tips
- Hobbs does NOT publish a separate tenant-improvement permit product. The Commercial Construction Guide covers 'new commercial construction, additions, and remodels' under one application, one plan-set standard, and one fee schedule, and Municode 15.28.010's 20% commercial plan-review fee applies identically to 'new/remodel/addition' — a TI/remodel is simply a Commercial Building Permit valued at the cost of the improvement work.
- For tenant improvements or renovations of existing commercial space, the NM Air Pollution Control Bureau must be notified 10 days in advance (1-800-224-7009) for asbestos-containing-material handling — build this into your schedule before demolition of finishes begins.
- Get on the Design Review Team agenda early: the DRT (all City Division Directors) meets Thursdays as a pre-conference for new commercial projects, and planning approval is required before applying for the building permit in most cases (575-391-8158).
- Despite Hobbs's Permian Basin oilfield economy, no distinct industrial/large-building or man-camp/workforce-housing permitting track is published by the City — large industrial and workforce-housing projects within city limits or the 5-mile ETJ go through the same Commercial Building Permit + DRT process (disclosed gap: any such project should confirm scope with Planning & Engineering at 575-397-9232; sites outside the ETJ fall under Lea County, not the City).
- Trade work (electrical, mechanical, plumbing) is permitted separately to the licensed trade contractors — commercial mechanical/plumbing fees are codified at Municode 15.28.081 and electrical at 15.28.090 — and those licensed trade contractors are responsible for coordinating their own inspections.
- The City's website has moved from hobbsnm.org to hobbsnm.gov (301 redirect observed 2026-08-01); the .org URLs still redirect but new links should use .gov.
- Completed permit sets are accepted by email at hobbs.permits@hobbsnm.org; if mailing a final set, call ahead for the fee amount first.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hobbs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Hobbs.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Hobbs
Commercial Building Permit in other cities
Compare commercial building permit fees across New Mexico →
Look up this fee in a different city →