Residential Solar Photovoltaic (PV) Permit in Gallup, New Mexico

Rooftop or ground-mount residential solar PV installation in Gallup is regulated by the state Construction Industries Division (CID), the same agency that has issued electrical permits in Gallup both before and after the City's July 6, 2026 general-construction transition. CID's electrical classification rules (14.6.6 NMAC) require anyone bidding or contracting a solar PV electric system installation to hold an EE-98, EL-1, or ER-1 license classification (or, for structural modifications to the mounting/racking, a GB-2 residential or GB-98 general building classification, now also CID-administered in Gallup post-transition). CID's published Electrical Bureau fee schedule does not itemize a solar/PV-specific line, so the electrical scope is billed under the Electrical Bureau's general schedule; a City of Gallup Site Development Permit (zoning) prerequisite may also apply if the installation is part of new construction or requires a structural addition.

Verified 2026-07-23 · Source

When you need this permit

  • Contractor bidding/installing the solar PV electric system must hold a valid CID EE-98, EL-1, or ER-1 license classification (14.6.6 NMAC, Electrical Classifications, PV-specific scope)
  • Installer performing the physical PV electrical work must hold a valid CID journeyman certificate (EE-98J, EL-1J, or ER-1J) or be a certified apprentice working under direct journeyman supervision
  • If the installation requires structural modifications to the roof or mounting structure, that work must be performed under a GB-2 (residential) or GB-98 (general) building license classification — filed as a CID General Construction Building Permit, since Gallup's own certified building official retired and the City no longer issues general-construction building permits as of July 6, 2026
  • City of Gallup Site Development Permit (zoning compliance, infrastructure review) may be required first if the PV installation is part of new construction or a structural addition, per the City's July 2026 CID Transition notice
  • Governed by the 2020 New Mexico Electrical Code (NMAC 14.10.4) / 2020 NEC as statewide-adopted

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Minimum Inspection Fee for Items not ListedNM RLD Construction Industries Division Fees page, Electrical Bureau schedule. No solar/PV-specific line item is published in CID's Electrical Bureau fee schedule; this is the closest published catch-all line for an electrical scope of work with no itemized fee of its own. If the PV installation is tied to a new or upgraded electrical service, the applicable service-amperage tier fee (e.g., $45-$360, per the electrical-permit entry) would apply instead.
$27
CID General Construction Building Permit Fee (if structural modification required)N.M. Admin. Code 14.5.5.11(A) — applies only if racking/mounting work requires structural modification under a GB-2/GB-98 classification, now CID-administered since Gallup's own certified building official position was not filled.
$3.00 per $1,000.00 valuation up to $15,000; $1.00 per $1,000.00 valuation over $15,000
City of Gallup Site Development Permit fee (if applicable)RE-CHASE 2026-07-23: resolves the prior 'GENUINELY UNPUBLISHED' gap. R2004-40 (gallupnm.gov/DocumentCenter/View/4612) is directly attached as the fee schedule to the City's CURRENT, live Contractor's and Homeowner's Site Development Permit Applications (gallupnm.gov/DocumentCenter/View/4601 and /4606) — it is not merely historical/legacy context, it is the document the City itself packages as this permit's fee schedule as of today. Confirm exact total for a PV-driven structural application with narchie@gallupnm.gov / (505) 863-1240.
Valuation-based per Resolution No. R2004-40 (see residential-building-permit entry for the full fee table)

Review timeline

Plan reviewGallup’s published plan-review target
3–4 business days

How long did your Residential Solar Photovoltaic (PV) Permit permit actually take in Gallup?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection (CID Electrical Bureau)

    Interconnection, disconnect placement, and wiring verified per the 2020 NEC

  2. 2

    Frame/Final Inspection (if structural building permit required)

    Racking/mounting attachment and roof penetration sealing verified against approved CID building permit plans

See the full Gallup inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate 'solar permit' fee line published by CID — a PV installation's electrical scope is billed under the Electrical Bureau's general fee schedule (service-amperage tier if applicable, otherwise the $27 minimum/not-listed fee).
  • If your PV installation requires structural roof/mounting modifications, that scope now goes through CID (not the City of Gallup) as a General Construction Building Permit, since the City stopped issuing general-construction permits effective July 6, 2026 — filed under a GB-2 (residential) or GB-98 (general) contractor license. Contractor
  • Confirm whether a City of Gallup Site Development Permit (zoning) applies to your specific installation before applying to CID — this City permit is governed by Resolution No. R2004-40's valuation-based fee schedule (confirmed 2026-07-23, attached to the current live application packet).
  • The nearest permanent CID office to Gallup/McKinley County is Albuquerque, (505) 222-9800/9801.
  • Re-chase pass (2026-07-20): independently re-verified NMAC 14.5.5.11 general-construction building-permit fee tiers ($3.00/$1,000 up to $15,000, $1.00/$1,000 thereafter) against the Cornell LII mirror and confirmed the CID fee page's $27 minimum-inspection-fee and amperage-tier electrical schedule are still live and unchanged; these remain the governing, citable dollar figures for the solar PV permit's electrical and (if applicable) structural scopes. The City of Gallup Site Development Permit fee remains the only unresolved line item.

Frequently asked questions

Gallup requires a residential solar photovoltaic (pv) permit for: Contractor bidding/installing the solar PV electric system must hold a valid CID EE-98, EL-1, or ER-1 license classification (14.6.6 NMAC, Electrical Classifications, PV-specific scope); Installer performing the physical PV electrical work must hold a valid CID journeyman certificate (EE-98J, EL-1J, or ER-1J) or be a certified apprentice working under direct journeyman supervision; If the installation requires structural modifications to the roof or mounting structure, that work must be performed under a GB-2 (residential) or GB-98 (general) building license classification — filed as a CID General Construction Building Permit, since Gallup's own certified building official retired and the City no longer issues general-construction building permits as of July 6, 2026; City of Gallup Site Development Permit (zoning compliance, infrastructure review) may be required first if the PV installation is part of new construction or a structural addition, per the City's July 2026 CID Transition notice; Governed by the 2020 New Mexico Electrical Code (NMAC 14.10.4) / 2020 NEC as statewide-adopted. If your project isn't listed, confirm with City of Gallup Planning & Development Department (site development / zoning / fence / sign permits and mandatory zoning-compliance prerequisite review); New Mexico Regulation and Licensing Department, Construction Industries Division (CID) — building, electrical, mechanical, and plumbing permit issuance, plan review, and inspections at City of Gallup Planning & Development: (505) 863-1240 (fax (505) 722-5131 / 5134); CID Albuquerque: (505) 222-9800/9801; CID Santa Fe: (505) 476-4700; CID inspection scheduling: (505) 222-9813 or (877) 243-0979 before starting work.

CID does not publish a solar/PV-specific fee line. The PV system's electrical scope is billed under the Electrical Bureau's general fee schedule — the applicable service-amperage tier if a new/upgraded electrical service is involved, or the $27 minimum inspection fee for items not otherwise listed. If structural roof/mounting modification is required, a separate valuation-based CID General Construction Building Permit fee also applies, and a City of Gallup Site Development Permit (governed by Resolution No. R2004-40's valuation-based fee schedule) may be required first.

Gallup's published plan-review target for a residential solar photovoltaic (pv) permit is 3–4 business days.

You'll need: Multi Purpose State Building Application / Electrical Permit Application (CID). Depending on your project, Gallup may also ask for: City of Gallup Site Development Permit Application (if applicable). See the required-documents checklist on this page for details on each.

Gallup requires 2 inspection(s) for a residential solar photovoltaic (pv) permit, in order: Electrical Inspection (CID Electrical Bureau), Frame/Final Inspection (if structural building permit required). Schedule each through City of Gallup Planning & Development Department (site development / zoning / fence / sign permits and mandatory zoning-compliance prerequisite review); New Mexico Regulation and Licensing Department, Construction Industries Division (CID) — building, electrical, mechanical, and plumbing permit issuance, plan review, and inspections (City of Gallup Planning & Development: (505) 863-1240 (fax (505) 722-5131 / 5134); CID Albuquerque: (505) 222-9800/9801; CID Santa Fe: (505) 476-4700; CID inspection scheduling: (505) 222-9813 or (877) 243-0979).

Apply through City of Gallup Planning & Development Department (site development / zoning / fence / sign permits and mandatory zoning-compliance prerequisite review); New Mexico Regulation and Licensing Department, Construction Industries Division (CID) — building, electrical, mechanical, and plumbing permit issuance, plan review, and inspections at City of Gallup Planning & Development: 110 W. Aztec Avenue, Gallup, NM 87301 (mailing: PO Box 1270, Gallup, NM 87305). Nearest CID office: Albuquerque, 5500 San Antonio Dr. Suite F, Albuquerque, NM 87109. Phone: City of Gallup Planning & Development: (505) 863-1240 (fax (505) 722-5131 / 5134); CID Albuquerque: (505) 222-9800/9801; CID Santa Fe: (505) 476-4700; CID inspection scheduling: (505) 222-9813 or (877) 243-0979, email: City of Gallup Planning & Development fee questions: narchie@gallupnm.gov; CID permit help: CID.PERMITHELP@rld.nm.gov; CID inspections: CID.Inspection@state.nm.us. Office hours: City of Gallup Planning & Development Department: Monday-Friday 8:00 a.m.-5:00 p.m. (MST). Official information: https://gallupnm.gov/779/Building-Permits.

Gallup, New Mexico has adopted: AUTHORITY TRANSITION (effective July 6, 2026): Per the City of Gallup Planning & Development Department's June 4, 2026 'Immediate Release: Letter to Contractors - CID Transition,' the City's sole Certified Building Official/Building Inspector (John Margis) retired effective July 2, 2026, and after an unsuccessful multi-state recruitment effort the City 'will no longer be able to issue building permits for general construction.' Effective July 6, 2026, the City of Gallup no longer accepts building permit applications for general construction; 'all building permits for anything related to the International Building Code, International Residential Code, International Existing Buildings Code and ADA will go through the New Mexico Regulation & Licensing Department, Construction Industries Division (CID) for permitting and inspection.' The City transitions to issuing a 'site development permit' covering zoning compliance, fire, water, wastewater, electric services, solid waste, drainage, and pedestrian/vehicular safety infrastructure review, and continues to issue permits for fencing, retaining walls, and signs directly. Source: City of Gallup News Flash, 'Immediate Release: Letter to Contractors - CID Transition,' posted June 8, 2026 (gallupnm.gov/m/newsflash/home/detail/1309), signed by Clyde (C.B.) Strain, Planning & Development Director; Mechanical, electrical, and plumbing (MEP) permits in Gallup were ALREADY issued directly by the CID prior to this transition and are unaffected in routing by the July 2026 change — 'The State of New Mexico provides their own permits and inspections for plumbing, mechanical and electrical' (City of Gallup Homeowner's Building Permit Application, PLANNING-HBP APP REV. 03/2020, page 1) — the July 2026 change specifically adds general construction/building (IBC/IRC/IEBC/ADA) permitting to CID's existing MEP role in Gallup; Statutory basis for CID's role as the default statewide Authority Having Jurisdiction where a municipality cannot maintain a certified local building department: N.M. Admin. Code 14.5.2.8 (Permits Required) and the Construction Industries Licensing Act; CID's general building permit fee structure is set by N.M. Admin. Code 14.5.5.11 (General Construction Building Permit Fees), electrical fees by 14.5.5.12, and mechanical/plumbing fees by 14.5.5.13; 2021 New Mexico Commercial Building Code (based on 2021 IBC) — per City of Gallup Building Permits - Governing Codes & Laws page; enforced by CID for general-construction permits post-transition; 2021 New Mexico Residential Building Code (based on 2021 IRC) — per City of Gallup Building Permits - Governing Codes & Laws page; 2021 New Mexico Existing Building Code — per City of Gallup Building Permits - Governing Codes & Laws page; 2021 New Mexico Earthen Building Materials Code — per City of Gallup Building Permits - Governing Codes & Laws page (reflects the region's traditional adobe/earthen construction); 2021 New Mexico Historic Earthen Buildings code — per City of Gallup Building Permits - Governing Codes & Laws page; 2018 New Mexico Residential Energy Conservation Code — per City of Gallup Building Permits - Governing Codes & Laws page; 2018 New Mexico Commercial Energy Conservation Code — per City of Gallup Building Permits - Governing Codes & Laws page; ICC A117.1-2017 Accessible and Usable Buildings and Facilities — per City of Gallup Building Permits - Governing Codes & Laws page; 2020 New Mexico Electrical Code (based on 2020 NEC), NMAC 14.10.4 — statewide CID-enforced code for electrical permits (consistent with CID's statewide electrical code cited in the Alamogordo, NM jurisdiction record; no Gallup-specific electrical code deviation was found); 2021 New Mexico Plumbing Code, NMAC 14.8.2, and 2021 New Mexico Mechanical Code, NMAC 14.9.2 — statewide CID-enforced codes for plumbing and mechanical permits; New Mexico Administrative Code, Title 14, Housing and Construction, Chapters 5 through 10 and 12, cited by the City of Gallup as the governing regulatory framework for building permits, land use, and zoning within the jurisdiction (City of Gallup Building Permits - Governing Codes & Laws page). Local amendments apply — see the Gallup overview page for the full list.

The State (CID) issues both the electrical permit for the PV system and, as of July 6, 2026, the general-construction building permit for any structural racking/mounting work, since Gallup's own certified building official position was not filled. The City of Gallup retains only the zoning-compliance Site Development Permit as a possible prerequisite.