Fire Sprinkler / Fire Alarm Permit in Farmington, New Mexico
Required for installation of fire protection (sprinkler) systems and fire alarm systems in Farmington. Both 'Fire Protection Systems' and 'Sprinkler System' are explicitly listed among work requiring a permit on the City's 'Do I need a Construction Permit?' page. Plan review and inspections for these life-safety systems are handled by the Farmington Fire Marshal's Office, which reviews plans for new construction and for alterations involving significant changes or a change in occupancy, and requires digital plan submittal. The Fire Marshal's Office enforces the 2021 International Fire Code as adopted and locally amended by City Ordinance No. 2024-1358.
Verified 2026-07-22 · Source
When you need this permit
- Both fire protection (sprinkler) systems and fire alarm systems are explicitly listed among work requiring a permit on the City's 'Do I need a Construction Permit?' page
- Plans for new construction and for alterations involving significant changes or a change in occupancy are reviewed by the Fire Marshal's Office, which maintains a working relationship with the City Building Department
- The Fire Marshal's Office (FMO) will only accept digital plan submittals, in accordance with current Building Department procedures
- Governed by the 2021 International Fire Code as adopted and locally amended by City of Farmington Ordinance No. 2024-1358
- A complete set of as-built plans must be printed and available on-site at final inspection, and a digital copy of as-built plans must be submitted to the FMO prior to or at the time of final inspection
- Applications and payment made in person only at the Building Inspection Division office, 805 Municipal Drive, Annex Building, 2nd floor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Flow Test / Rough-In Inspection
Flow testing of the underground water supply for sprinkler systems and rough-in inspections, performed by the Fire Marshal's Office per its published Fire Inspections process.
- 2
Hydro Pressure Test & Fire Supply Line Flush
Hydrostatic pressure test and fire supply line flush, performed by the Fire Marshal's Office.
- 3
Sprinkler Final Inspection
Final inspection of the completed fire sprinkler system, required before the life safety system final is accepted.
- 4
Building Final Inspection
Building final inspection; the City requires final inspections (including life safety system finals covering fire sprinkler, fire alarm, and hood suppression systems) prior to issuing a Certificate of Occupancy.
See the full Farmington inspection guide — scheduling & re-inspection fees →
Tips
- The Fire Marshal's Office only accepts digital plan submittals — coordinate with your fire protection contractor to submit plans electronically per current Building Department procedures, not paper copies.
- Bring both a printed as-built plan set on-site AND submit a digital as-built copy to the Fire Marshal's Office before or at final inspection — both are required, per the Building Inspection Division's published Final Inspections / As-Built Requirements.
- Fire alarm systems must be inspected and certified annually even after the initial installation permit and final inspection, per the City's Fire Business Inspection Checklist.
- The Fire Marshal's Office is a separate contact from the general Building Inspection line: call (505) 599-1430, Option 1, versus (505) 599-1304 for general building permits.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Farmington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Farmington
Fire Sprinkler / Fire Alarm Permit in other cities
Compare fire sprinkler / fire alarm permit fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Farmington project checklist
Describe your project once and get every permit, document, and fee it triggers in Farmington — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →