Commercial Building Permit (New Construction & Tenant Improvement) in Farmington, New Mexico
Required for new commercial construction and commercial tenant improvements in Farmington. Farmington is its own Authority Having Jurisdiction (AHJ) under 14.5.1 NMAC — its Building Inspection Division (a full-service department with a full-time certified building official) issues commercial building permits locally rather than the State Construction Industries Division (CID) administering them, enforcing the 2021 New Mexico Commercial Building Code (2021 IBC as amended, 14.7.2 NMAC). Tenant improvements are NOT a separate permit type — they run through this same commercial building permit process, with the only published difference being submittal volume: up to six (6) sets of construction drawings for new commercial projects versus up to four (4) sets for commercial tenant improvements, per the City's Commercial Building Requirements page. All applications and building plans must be submitted as hard copies in person — no online permitting or payment.
Verified 2026-08-01 · Source
When you need this permit
- Up to six (6) sets of construction drawings must be submitted for new commercial projects; up to four (4) sets for commercial tenant improvements — per the City's Commercial Building Requirements page
- Per the Commercial New Construction bulletin: submit six (6) complete sets of plans including building computations and specifications indicating type of construction and occupancy group per the International Building Code; plot plan; floorplan; footing/foundation plan; roof plan; foundation, wall and roof section drawings; plumbing and mechanical plans; electrical plan; and any specification/project manual
- Plot plan must indicate proposed paving, off-street parking layout (including striping and handicapped-accessible parking with posted signage), and trash receptacle location with any required screening per City standards
- Farmington Fire Department approves all commercial plans and automatic fire-sprinkler systems — no permit is issued until ALL applicable departments/agencies have approved their portion of the application
- Any commercial building, regardless of valuation, must be permitted to a general contractor licensed in the State of New Mexico (GB-98) Contractor
- NM professional seal thresholds (per the City's Commercial New Construction bulletin and 14.5.2.10 NMAC): occupant load over 10, or Group E, Daycare H (Hazardous), or I (Institutional) occupancies, require a New Mexico Architect's and/or Registered Engineer's stamp; occupant load over 50 OR valuation greater than $400,000 requires plans stamped/signed by BOTH a New Mexico Licensed Architect and a New Mexico Registered Professional Engineer — all pages of the plans must be stamped and signed
- Under 14.5.2.10 NMAC, alterations to buildings or structures that present no unusual conditions or hazards and no change in occupancy are excepted from the architect/engineer seal requirement (at the building official's discretion) — relevant to many tenant improvements
- Electrical: installations with calculated service capacity over 100 kVA single-phase or over 225 kVA three-phase must be stamped by a registered electrical engineer; mechanical/plumbing work valued at $50,000+ or in commercial buildings three stories and higher may require a PE stamp (14.5.2.10 NMAC)
- Restrooms and building access must be accessible per the New Mexico Commercial Building Code and ICC/ANSI A117.1-2003; eating establishments where food is consumed on premises must have accessible public restrooms
- Secondary permits for electrical, mechanical, and plumbing work may be submitted without accompanying construction drawings, though equipment cut-sheets may be required
- A City of Farmington Business License is required for the general contractor and all subcontractors working within city limits
- Applications and payment made in person only at 805 Municipal Drive, Annex Building, 2nd floor — hard copies required, no online permitting or payment
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection
The City of Farmington requires a final inspection for ALL permits issued. Schedule by calling (505) 599-1304 at least one business day in advance. The City does not publish a full commercial inspection sequence (footing, framing, etc.) online — confirm required intermediate inspections with your inspector at permit issuance.
- 2
Departmental Finals / Certificate of Occupancy Inspections
Final inspections from all relevant departments (building, fire/life-safety, and others depending on the occupant) are required before a Certificate of Occupancy is issued; life-safety system finals (fire sprinkler, fire alarm, hood suppression) are performed by the Fire Marshal's Office.
See the full Farmington inspection guide — scheduling & re-inspection fees →
Tips
- Tenant improvements are NOT a separate permit in Farmington — they go through the same commercial building permit process. The only published TI-specific difference is submittal volume: up to four (4) sets of construction drawings versus up to six (6) for new commercial construction.
- Many tenant improvements can avoid the NM architect/engineer seal requirement: 14.5.2.10 NMAC excepts alterations presenting no unusual conditions or hazards and no change in occupancy — but this is at the building official's discretion, and any change of occupancy triggers Fire Marshal plan review and seal requirements.
- Budget real lead time for the seal thresholds: occupant load over 50 or valuation over $400,000 requires BOTH a NM Licensed Architect and a NM Registered Professional Engineer to stamp and sign every page.
- No fee schedule is published. Per the City's Manual of Fees page, permitting fees are based on type of construction, square footage, type of materials, and construction codes — call a Building Inspector at (505) 599-1304 for an exact quote before bidding.
- The Building Inspection Division requires hard-copy plans in person, but the Fire Marshal's Office accepts only digital plan submittals for life-safety systems — plan for both formats on any project with sprinklers or fire alarm.
- No permit is issued until every applicable department/agency has approved its portion — Fire Department approval of plans is mandatory for all commercial projects.
- No distinct industrial permitting track is published by the City — industrial and energy-sector buildings within city limits run through this same commercial building permit process (state/federal agencies separately regulate oil & gas operations themselves).
- Building permits are valid for 2 years from issuance; the permit becomes invalid if work does not begin within 180 days.
- Key contacts published on the Commercial New Construction bulletin: Building Inspection Division (505) 599-1304; Chief Building Inspector (505) 599-1305.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Farmington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Farmington.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Farmington
Commercial Building Permit (New Construction & Tenant Improvement) in other cities
Compare commercial building permit (new construction & tenant improvement) fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Farmington project checklist
Describe your project once and get every permit, document, and fee it triggers in Farmington — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →