EV Charger / Electric Vehicle Charging Station Permit — Farmington, New Mexico · Requirements sheet
Verified 2026-07-20 · Source: https://www.farmingtonnm.gov/906/State-of-NM-Adopted-Construction-Codes
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / Electric Vehicle Charging Station Permit in Farmington, New Mexico
Farmington has no dedicated EV charger permit, application, or fee schedule. Installation of an electric vehicle charging station (Level 1/2 EVSE) is electrical work and is processed under the City's standard Residential Electrical Permit, governed by the 2020 New Mexico Electrical Code (based on the 2020 NEC, which includes Article 625, Electric Vehicle Power Transfer System) — the same mechanism documented in the electrical-permit entry. No EV-specific provision or fee line was found published on the City's 'Do I need a Construction Permit?' page, the State of NM Adopted Construction Codes page, or the Manual of Fees. Re-chased 2026-07-20: located and directly checked the City's 'Manual of Fees' page -- its only linked document is a Water/Wastewater Division 'Set Price List' (utility tap/meter fees, unrelated to building/electrical permits); the page's own text states 'Permitting fees are based upon type of construction, square footage, type of materials and construction codes... contact one of our Building Inspectors at (505)599-1304' rather than publishing a table. Confirms the same gap already documented on this file's general electrical-permit entry (also confidence: verified, also fees: []), which this EV-charger entry mirrors exactly since it uses the identical Residential Electrical Permit.
Verified 2026-07-20 · Source
When you need this permit
- Permit required for the electrical work associated with EV charger/EVSE installation (new wiring, branch circuit, or panel/service work), same as any other electrical installation
- Must comply with the 2020 New Mexico Electrical Code (2020 NEC as amended, including Article 625) — 14.10.4 NMAC, effective March 28, 2023
- New Mexico's homeowner permit exemption (14.5.2 NMAC) allows a homeowner to obtain the electrical permit for their own primary residence, limited to appurtenant structures such as garages and carports, provided the homeowner performs the major portion of the work
- Only a New Mexico-licensed electrical contractor (or exempt homeowner) may perform and permit the work
- Applications and payment made in person only at the Building Inspection Division office
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection
Final inspection required for all permits, including the EV charger circuit/electrical work.
See the full Farmington inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate 'EV charger permit' in Farmington — apply for the standard Residential Electrical Permit for the charger's dedicated circuit or any associated service/panel upgrade.
- The City's adopted 2020 New Mexico Electrical Code (based on the 2020 NEC) includes Article 625 (Electric Vehicle Power Transfer System), which governs EVSE installation requirements even though no City-specific EV fee or checklist has been published.
- The Farmington Electric Utility System (FEUS) also performs a separate electrical Service Connect inspection for new/upgraded service — schedule this at (505) 599-8310, (505) 599-8312, or (505) 599-8317, separate from the (505) 599-1304 permit line.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Farmington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Farmington
EV Charger / Electric Vehicle Charging Station Permit in other cities
Compare ev charger / electric vehicle charging station permit fees across New Mexico →
Look up this fee in a different city →
Related guides
Now live
Build your Farmington project checklist
Describe your project once and get every permit, document, and fee it triggers in Farmington — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →