Solar Photovoltaic (PV) Permit in Rio Rancho, New Mexico

Required for residential and commercial solar photovoltaic installations in Rio Rancho. A building permit, electrical permit, and PNM interconnection documentation are all required. Questions on solar permits are directed to Permits@rrnm.gov or Solar@rrnm.gov.

Verified 2026-07-02 · Source

When you need this permit

  • Effective March 20, 2017, a copy of the PNM Notice of Complete and Notice of Technical Screening Review is required as part of the submittal, showing the type and size of the system to be installed, before a solar permit is applied for
  • Electrical permit required for the photovoltaic system connection
  • Building permit required for roof-mounted or ground-mounted structural attachment
  • Comply with Rio Rancho Chapter 154 zoning and setback requirements for ground-mounted systems

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Residential/Commercial Photovoltaic, 0-10 KVAElectrical Permit application form, City of Rio Rancho (rrnm.gov/DocumentCenter/View/76076)
$66.00
Each additional 0-10 KVAElectrical Permit application form, City of Rio Rancho
$66.00
Administrative FeeElectrical Permit application form, City of Rio Rancho
$23.00 on all permits

Review timeline

Plan reviewTypical estimate — confirm current times with the Rio Rancho building department
~3–10 business days

How long did your Solar Photovoltaic (PV) Permit permit actually take in Rio Rancho?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In (Electrical)

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final Inspection

    Electrical connections and interconnection point verified after installation is complete

See the full Rio Rancho inspection guide — scheduling & re-inspection fees →

Tips

  • Contact PNM before starting for the Notice of Complete and Notice of Technical Screening Review — this has been required since March 20, 2017.
  • Solar permit questions go to Permits@rrnm.gov or Solar@rrnm.gov, or leave a voicemail at (505) 891-5005.
  • Fees for the photovoltaic electrical connection are $66.00 per each 0-10 KVA increment, plus the $23.00 administrative fee.

Frequently asked questions

Yes. Effective March 20, 2017, you must submit a copy of the PNM Notice of Complete and Notice of Technical Screening Review, showing the type and size of system to be installed, before applying for the solar permit. Source: City of Rio Rancho Building Division page.

The electrical fee for a residential photovoltaic system is $66.00 per 0-10 KVA increment (e.g., a 20 KVA system would be $132.00), plus a $23.00 administrative fee. A separate building permit fee applies for the structural/roof-mounting work. Source: City of Rio Rancho Electrical Permit application form.

Plan review for a solar photovoltaic (pv) permit in Rio Rancho typically runs 3–10 business days. This is an estimate, not a published figure — confirm current review times with City of Rio Rancho Development Services — Building Inspection Division at (505) 891-5005.

You'll need: PNM Notice of Complete and Notice of Technical Screening Review; Electrical Permit Application; Electrical Single-Line Diagram. See the required-documents checklist on this page for details on each.

Rio Rancho requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: Rough-In (Electrical), Final Inspection. Schedule each through City of Rio Rancho Development Services — Building Inspection Division ((505) 891-5005).

Apply through City of Rio Rancho Development Services — Building Inspection Division at 3200 Civic Center Circle NE, Suite 130, Rio Rancho, NM 87144. Phone: (505) 891-5005, email: Permits@rrnm.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.rrnm.gov/77/Building-Division.

Rio Rancho, New Mexico has adopted: 2021 International Building Code (IBC) — with New Mexico state amendments; 2021 International Residential Code (IRC) — with New Mexico state amendments; 2021 Uniform Mechanical Code (UMC) — with New Mexico state amendments; 2021 Uniform Plumbing Code (UPC) — with New Mexico state amendments; 2020 National Electrical Code (NEC) — with New Mexico state amendments; 2021 International Energy Conservation Code (IECC); 2021 International Existing Building Code (IEBC) — with New Mexico state amendments; 2017 ICC/ANSI A117.1 Accessibility Code; 2021 International Fire Code (IFC); 2012 Swimming Pool, Spa, and Hot Tub Code; Current New Mexico Administrative Code (NMAC) Title 14 construction code chapters, as adopted and amended by the Construction Industries Division; City of Rio Rancho Code of Ordinances, Title XV Land Use: Chapter 151 (Building Regulations), Chapter 152 (Flood and Erosion Control), Chapter 153 (Storm Drainage Requirements), Chapter 154 (Planning and Zoning). Local amendments apply — see the Rio Rancho overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rio Rancho building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.