Fire Alarm System Permit (Plan Review) in Town of Taos, New Mexico

Following the same self-administered Fire Marshal framework documented in this file's Fire Sprinkler System Permit entry, fire alarm system plan review in the Town of Taos is a separate checkbox line item ('Commercial Fire Alarm System Plans') within the Town of Taos Fire Department's 'Fire Inspection Request Application' — organized distinctly from Fire Sprinkler Plans on the same form, with its own device-count-based fee. This is DIFFERENT from the Town's separate 'Alarm User Permit' under Town of Taos Code of Ordinances Chapter 8.04 (Burglar and Fire Alarm Systems), which governs monitoring/false-alarm liability for systems connected to the Town's central alarm-response panel, not the physical installation's code-compliance review.

Verified 2026-07-22 · Source

When you need this permit

  • Fire Inspection Request Application (Town of Taos Fire Department) with the 'Commercial Fire Alarm System Plans' Plan Review Fees checkbox selected, listing the total number of devices
  • A set of plans must be submitted for plan review, per the application's own checklist
  • Installation must comply with the 2015 International Fire Code as adopted and locally modified by Town of Taos Code of Ordinances § 8.12.010
  • For commercial, industrial, or large-scale-residential projects, plans must be stamped by a licensed engineer and/or architect per Town of Taos Code of Ordinances § 16.12.070.3(E)
  • If the installed fire alarm system will be monitored or connected to the Town's central alarm-response panel, a SEPARATE Alarm User Permit is additionally required under Town of Taos Code of Ordinances Chapter 8.04 (§ 8.04.040) — this is a distinct permit governing monitoring/false-alarm liability, not the Fire Department's plan-review permit for the alarm system's construction/installation compliance, and carries its own fee (see Fees)
  • A contractor performing the physical installation must separately hold a current New Mexico Construction Industries Division (CID) license for the applicable fire-alarm trade, a statewide licensing requirement distinct from this Town-administered plan-review/permit process
  • Failure to secure a required fire-code permit is a citable offense under the Town's fire code citation program, carrying a $250.00 citation fee per violation, in addition to any permit fee — Town of Taos Code of Ordinances § 8.12.020

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Commercial Fire Alarm System Plans (plan review)Town of Taos Fire Inspection Request Application, Town of Taos Fire Department, updated 02/22/2017; applicant must list the total number of devices on the application
$50.00 + $1.00 per device over 50
Alarm User Permit (separate permit, only if centrally monitored)Town of Taos Code of Ordinances, Appendix A Fee Schedule § A.40.010, referencing §§ 8.04.050/8.04.060. This is a distinct permit governing alarm monitoring/false-alarm response, not the plan-review fee above.
$100.00 initial connection fee, then $50.00 per calendar year (systems connected to the town's central alarm panel); $10.00 per calendar year (all other alarm user permits)
False Alarm Service Fees (Alarm User Permit track only, if applicable)Town of Taos Code of Ordinances, Appendix A Fee Schedule § A.40.020, referencing §§ 8.04.090/8.12.020
No fee for the first 2 false alarms per calendar year; $50.00 for the 3rd-4th; $100.00 for the 5th and beyond; $500.00 if 7+ false alarms are found to result from negligence; $125.00 no-key-holder-response fee

Review timeline

Plan review
Not published — contact the department

How long did your Fire Alarm System Permit (Plan Review) permit actually take in Town of Taos?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Marshal Plan Review

    Town of Taos Fire Department reviews submitted fire alarm system plans and device count for compliance with the adopted 2015 International Fire Code.

  2. 2

    Fire Alarm System Inspection

    Physical inspection of the installed fire alarm system by the Town of Taos Fire Department; coordinated with the fire department's final-inspection sign-off required before a Certificate of Occupancy may be issued under § 16.12.070.4(C).

See the full Town of Taos inspection guide — scheduling & re-inspection fees →

Tips

  • Do not confuse this Fire Department plan-review permit for a fire alarm system's construction/installation compliance with the separate Chapter 8.04 'Alarm User Permit,' which governs monitoring and false-alarm liability for systems connected to the Town's central alarm-response panel and carries its own $100 initial / $50-or-$10 annual fee.
  • Unlike Electrical, Plumbing, and Mechanical/HVAC — routed entirely to the state CID per §§ 16.12.070.2(D)/16.12.070.3(H) — fire alarm plan review, permitting, and inspection are self-administered directly by the Town's own Fire Marshal/Fire Department, the same pattern documented for Building and for Fire Sprinkler plan review in this file.
  • Commercial fire alarm projects need the total device count on hand before submitting — it directly drives the per-device fee component above 50 devices.

Frequently asked questions

Town of Taos requires a fire alarm system permit (plan review) for: Fire Inspection Request Application (Town of Taos Fire Department) with the 'Commercial Fire Alarm System Plans' Plan Review Fees checkbox selected, listing the total number of devices; A set of plans must be submitted for plan review, per the application's own checklist; Installation must comply with the 2015 International Fire Code as adopted and locally modified by Town of Taos Code of Ordinances § 8.12.010; For commercial, industrial, or large-scale-residential projects, plans must be stamped by a licensed engineer and/or architect per Town of Taos Code of Ordinances § 16.12.070.3(E); If the installed fire alarm system will be monitored or connected to the Town's central alarm-response panel, a SEPARATE Alarm User Permit is additionally required under Town of Taos Code of Ordinances Chapter 8.04 (§ 8.04.040) — this is a distinct permit governing monitoring/false-alarm liability, not the Fire Department's plan-review permit for the alarm system's construction/installation compliance, and carries its own fee (see Fees); A contractor performing the physical installation must separately hold a current New Mexico Construction Industries Division (CID) license for the applicable fire-alarm trade, a statewide licensing requirement distinct from this Town-administered plan-review/permit process; Failure to secure a required fire-code permit is a citable offense under the Town's fire code citation program, carrying a $250.00 citation fee per violation, in addition to any permit fee — Town of Taos Code of Ordinances § 8.12.020. If your project isn't listed, confirm with Town of Taos Planning, Community and Economic Development Department (handles zoning review for building permits; the former standalone 'Building Safety Division' name appears on some older documents but current applications and the department's own letterhead identify it as the Planning, Community and Economic Development Department) at 575-751-2016 before starting work.

In Town of Taos, the published Commercial Fire Alarm System Plans (plan review) is: $50.00 + $1.00 per device over 50. Additional published fees: Alarm User Permit (separate permit, only if centrally monitored) — $100.00 initial connection fee, then $50.00 per calendar year (systems connected to the town's central alarm panel); $10.00 per calendar year (all other alarm user permits); False Alarm Service Fees (Alarm User Permit track only, if applicable) — No fee for the first 2 false alarms per calendar year; $50.00 for the 3rd-4th; $100.00 for the 5th and beyond; $500.00 if 7+ false alarms are found to result from negligence; $125.00 no-key-holder-response fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Town of Taos does not publish a plan-review timeline for this permit. Contact Town of Taos Planning, Community and Economic Development Department (handles zoning review for building permits; the former standalone 'Building Safety Division' name appears on some older documents but current applications and the department's own letterhead identify it as the Planning, Community and Economic Development Department) at 575-751-2016 for current turnaround.

You'll need: Fire Inspection Request Application — Commercial Fire Alarm System Plans; Set of Fire Alarm System Plans; Alarm Device Count. Depending on your project, Town of Taos may also ask for: Alarm User Permit Application. See the required-documents checklist on this page for details on each.

Town of Taos requires 2 inspection(s) for a fire alarm system permit (plan review), in order: Fire Marshal Plan Review, Fire Alarm System Inspection. Schedule each through Town of Taos Planning, Community and Economic Development Department (handles zoning review for building permits; the former standalone 'Building Safety Division' name appears on some older documents but current applications and the department's own letterhead identify it as the Planning, Community and Economic Development Department) (575-751-2016).

Apply through Town of Taos Planning, Community and Economic Development Department (handles zoning review for building permits; the former standalone 'Building Safety Division' name appears on some older documents but current applications and the department's own letterhead identify it as the Planning, Community and Economic Development Department) at 400 Camino de la Placita, Taos, NM 87571. Phone: 575-751-2016, email: planning@taosnm.gov. Office hours: Monday, Wednesday, Thursday: walk-ins welcome (appointments prioritized); Tuesday, Friday: by appointment only; no same-day appointments (per Town of Taos Planning Division office-hours notice, effective June 9, 2025). Official information: https://www.taosnm.gov/203/Planning-Community-Economic-Development.

The Town of Taos Fire Department's own fire marshal reviews fire alarm system plans directly, using the Department's Fire Inspection Request Application — self-administered by the Town, not routed to the state Construction Industries Division, the same pattern as fire sprinkler plan review in Taos.

No. The Fire Inspection Request Application's Commercial Fire Alarm System Plans line item covers plan review of the physical alarm system's fire-code compliance. A separate Alarm User Permit under Town of Taos Code of Ordinances Chapter 8.04 is required only if the system will be monitored or connected to the Town's central alarm-response panel, and covers false-alarm liability, not construction compliance.