Residential/Commercial Solar Photovoltaic (PV) Permit — Town of Taos, New Mexico · Requirements sheet
Verified 2026-07-20 · Source: https://www.taosnm.gov/DocumentCenter/View/4705/Residential-Multi-Family-and-Commercial-Zoning-Review-Application-PDF
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential/Commercial Solar Photovoltaic (PV) Permit in Town of Taos, New Mexico
Required for installation of a rooftop or ground-mounted solar photovoltaic system within the Town of Taos. Following the same trade split documented for this file's Residential Building Permit entry, a solar PV installation splits across two authorities: the racking/mounting structural scope is self-administered by the Town (Zoning Review Application for Building Permit, $250.00 residential fee, per Town of Taos Code of Ordinances § 15.04.010), while the electrical interconnection scope is NOT covered by the Town's permit and instead requires a separate state Construction Industries Division (CID) Electrical Permit, per Town of Taos Code of Ordinances §§ 16.12.070.2(D) and 16.12.070.3(H). No Town of Taos-specific solar application, checklist, or fee line distinct from these two general mechanisms was found published as of 2026-07-20.
Verified 2026-07-20 · Source
When you need this permit
- Zoning Review Application (for Building Permit) required for the racking/mounting structural scope, using the same $250.00 (residential, up to 5 dwellings) or $500.00 (commercial/6+ dwellings) fee documented in this file's Residential Building Permit entry
- Electrical interconnection is NOT covered by the Town's Zoning Review/Building Permit — a separate State of New Mexico Construction Industries Division (CID) Electrical Permit is required, per Town of Taos Code of Ordinances §§ 16.12.070.2(D) and 16.12.070.3(H), the same trade split documented for all other electrical work in this file
- Construction Mitigation Checklist required per Town of Taos Code of Ordinances § 16.12.070.6 before any building permit (including one covering solar racking) may be issued
- A homeowner self-performing the racking/mounting work under the State of New Mexico Homeowner Building Permit Application may not self-perform the electrical interconnection — 'a separate application is required for these trades,' per the same exclusion documented in this file's Residential Building Permit entry
- If the parcel is within 150 feet of the centerline of an established arroyo, a Drainage Plan sealed by a Registered Licensed NM Engineer is required for ground-mounted array foundations
- New Mexico's Construction Industries Division publishes solar-specific plan-review guidance (e.g., a Solar Array Plan Review document) for the state-administered electrical/interconnection permitting track; the specific fee figures within that document were not independently extractable from the source PDF during this research pass and are not asserted here
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Racking (ground-mount only)
Footing/foundation inspection for ground-mounted racking systems, per the same framework documented in this file's Residential Building Permit entry.
- 2
State Electrical Inspection (interconnection)
Conducted by the New Mexico Construction Industries Division for the interconnection/wiring scope, since the Town does not self-administer Electrical.
- 3
Town Final Inspection
Requires the state final electrical sign-off to already be in hand, per the same mechanism documented in this file's Residential Building Permit entry.
See the full Town of Taos inspection guide — scheduling & re-inspection fees →
Tips
- Budget for two separate permits and two separate fee tracks, exactly as with any other electrical work in Taos: the Town's Zoning Review Application for the racking/mounting structure ($250 residential), and a State of New Mexico CID Electrical Permit for the interconnection wiring.
- No Town of Taos-specific solar application, checklist, or fee line distinct from the general Building/Electrical trade split was found published as of 2026-07-20 — this is a genuine documentation gap rather than an inferred figure.
- If the installation is on a homeowner-occupied residence and the homeowner intends to self-perform the racking/mounting work, remember that the electrical interconnection portion cannot be self-performed under the State Homeowner Building Permit Application — a licensed electrician must pull the separate CID Electrical Permit. Owner-builderContractor
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Town of Taos building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Town of Taos
Residential/Commercial Solar Photovoltaic (PV) Permit in other cities
Compare residential/commercial solar photovoltaic (pv) permit fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Town of Taos project checklist
Describe your project once and get every permit, document, and fee it triggers in Town of Taos — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →